Tools and techniques used for Plan Communications include the communication:
Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:
Which document defines how a project is executed, monitored and controlled, and closed?
The following is a network diagram for a project.
The free float for Activity E is how many days?
While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?
Which of the following tools will be used to produce performance reports that provide information to stakeholders about project cost, schedule progress, and performance?
Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?
Which of the following is a measure of the value of work completed compared to the actual cost or progress made on the project?
The process of formalizing acceptance of the completed project deliverables is known as:
Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?
The number of potential communication channels for a project with 5 stakeholders is:
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?
Which of the following is an input to the Direct and Manage Project Execution process?
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
Which of the following strategic considerations often results in project authorization?
In an organization with a projectized organizational structure, who controls the project budget?
In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?
What component of the project scope definition defines project exclusions?
The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:
What is a deliverable-oriented hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:
Which tool is used to develop technical details within the project management plan?
Which of the following Process Groups covers all Project Management Knowledge Areas?
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:
Which process is included in the Project Integration Management Knowledge Area?
Which of the following is contained within the communications management plan?
When does the project team determine which dependencies are discretionary?
Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:
Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?
Organizational theory is a tool used in which Project Human Resource Management process?
Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?
Which quality tool may prove useful in understanding and estimating the cost of quality in a process?
Which of the following is used to illustrate the connections between work packages or activities and project team members?
Which document in the project management plan can be updated in the Plan Procurement Management process?
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
When closing a project or phase, part of the process may require the use of which type of analysis?
Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?
Which of the following is a tool or technique of the Define Activities process?
Which is the correct formula for calculating expected activity cost for three-point estimating?
Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?
What is the number of stakeholders, if the project has 28 potential communication channels?
Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?
Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
Which tool or technique is used to manage change requests and the resulting decisions?
What quality control tool graphically represents how various elements of a system interrelate?
A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:
Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?
Which of the Project Time Management processes analyzes activity sequencing, durations, resource requirements, and schedule constraints?
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:
Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?
An associate who calculates fees daily to support the department is doing which of the following?
Ensuring that projects and programs are reviewed to prioritize resource allocation is a focus of which of the following?
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedulevariance (SV) for Task 8?
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:
An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?
A primary function of a project management office is to support project managers in a variety of ways, including which of the following?
Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?
Technical capability, past performance, and intellectual property rights are examples of:
Which Process Group and Knowledge Area include the Sequence Activities process?
The project scope statement and resource calendars are inputs to which Project Time Management process?
Which process involves developing an approximation of the monetary resources needed to complete project activities?
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?
In which process is a project manager identified and given the authority to apply resources to project activities?
Which technique is commonly used for the Perform Quantitative Risk Analysis process?
Which tools or techniques will a project manager use for Develop Project Team?
A project manager requesting industry groups and consultants to recommend project intervention is relying on:
Which stakeholder communicates with higher levels of management to gather organizational support and promote project benefits?
In which of the following types of organizations is resource availability moderate to high?
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?