Summer Sale 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exams65

ExamsBrite Dumps

Project Management Professional (PMP) July 2026 Update Question and Answers

Project Management Professional (PMP) July 2026 Update

Last Update Jul 27, 2026
Total Questions : 187

We are offering FREE PMP PMI exam questions. All you do is to just go and sign up. Give your details, prepare PMP free exam questions and then go for complete pool of Project Management Professional (PMP) July 2026 Update test questions that will help you more.

PMP pdf

PMP PDF

$139.65  $399
PMP Engine

PMP Testing Engine

$157.15  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$209.65  $599
Questions 1

A project manager was assigned to lead a construction project where a hybrid approach is recommended. A team with high levels of knowledge and experience is

required.

What should the project manager do next?

Options:

A.  

Develop a risk register that includes the risk of a lack of experienced professionals.

B.  

Develop a resource management plan that includes the roles and responsibilities to be met.

C.  

Develop a procurement strategy that includes hiring external resources with the right skill sets.

D.  

Develop a financial management plan that includes the budget to hire dedicated professionals.

Discussion 0
Questions 2

Acompany is transitioning all projects under the portfolio of IT from a predictive to an adaptive approach. Some of the project managers and project team members

are unhappy about this change because they have been working in a predictive environment for years, and several projects are currently in progress.

What are two tasks the project manager should ask support from the company ' s management team to ensure smooth transition to the new approach? (Choose 2)

Options:

A.  

Allow projects in the portfolio to operate freely for the next three months without measuring their performance.

B.  

Organize learning programs for everyone in the portfolio to educate them about the adaptive approach.

C.  

Highlight the pros of an adaptive approach and convince everyone that change is inevitable.

D.  

Enforce the change on everyone and on every project without taking time to acknowledge their resistance.

E.  

Develop new processes, standards, guidelines, and templates to follow for working in the adaptive way.

Discussion 0
Questions 3

During the execution of an agile project, the quality of one vendor ' s deliverables decreases significantly. After analyzing possible solutions, the project manager identifies an alternative vendor who can deliver similar components in smaller batches.

What should the project manager do?

Options:

A.  

Meet with the current vendor to discuss alternatives for solving the situation.

B.  

Adjust the project execution cadence to consider the alternative vendor.

C.  

Update the project management plan and inform all the stakeholders about the new iteration lengths with the current vendor.

D.  

Register the occurrence in the issue log and continue the project execution with the new vendor and shorter iterations.

Discussion 0
Questions 4

The regional sales manager (RSM) calls the project manager and expresses the need to add functionalities to the project scope and change the project ' s priorities. Making these alterations as soon as possible will significantly increase the project ' s adoption.

What should the project manager do?

Options:

A.  

Organize a meeting with the RSM and their team to identify their needs and priorities and propose it for discussion at the next project meeting.

B.  

Explain to the RSM that the scope cannot be changed just like that and to implement it as is.

C.  

Add the new requirements to the scope and change the scheduling as requested by the RSM and send it to the project sponsor for approval.

D.  

Instruct the RSM to use the project tracking tool to add the requests of the new features.

Discussion 0
Questions 5

During a project status meeting, two project stakeholders disagree about what should be included in the next deliverable. One of the stakeholders would like the team to include a finalized version of the new component in the release. Using the finalized version will impact the project timeline. The second stakeholder would like the team to include a beta version of the new component to allow the client to provide feedback before the component is finalized.

What should the project manager do next?

Options:

A.  

Implement the beta version of the component because it will not impact the project timeline.

B.  

Mediate the disagreement by scheduling a meeting to agree on a solution.

C.  

Implement the finalized version of the component because it will impact the project timeline.

D.  

Choose the inclusion that will result in the least amount of risk.

Discussion 0
Questions 6

Akey stakeholder has been mostly silent until now. To optimize resources, the stakeholder wants to move one team member to another project but the project

manager does not agree.

What should the project manager do?

Options:

A.  

Schedule a meeting to review the backlog assignments with the team.

B.  

Suggest the stakeholder observe project activities first, then decide.

C.  

Explain to the stakeholder that resource planning was already approved.

D.  

Track the actual usage of resources and compare with estimated usage.

Discussion 0
Questions 7

The project manager is utilizing a hybrid management approach for a creative project. The organization is undergoing a change aimed at improving cross-functional

collaboration, which may impact the project scope.

What should the project manager do first?

Options:

A.  

Initiate a review of the external business environment to anticipate and manage potential effects on the project scope and backlog.

B.  

|dentify stakeholders affected by the change and collaborate on an approach that aligns the project with organizational changes.

C.  

Analyze the breadth of the project to align with the new organizational directives, ensuring cross-functional collaboration is at the forefront.

D.  

Continue with the current project scope and backlog until change is defined and communicated through official channels.

Discussion 0
Questions 8

During a daily coordination meeting, the team reports that due to considerable challenges with the infrastructure, the planned tasks are now blocked and cannot move

forward. What should the project manager do?

Options:

A.  

Ask the product owner to suggest issue resolution.

B.  

Escalate the issue and its impact to the project sponsor.

C.  

Determine and apply a suitable strategy to remove or minimize the issues.

D.  

Ask the team members to explore trainings while waiting for issue resolution.

Discussion 0
Questions 9

A strategic project is nearing completion. The project manager discovers the project team is reluctant to prepare the knowledge transfer documentation to the relevant business department because they are being assigned to a new, urgent project.

What should the project manager do?

Options:

A.  

Emphasize the importance of knowledge transfer to the project team.

B.  

Ask project sponsor to push the project team for knowledge transfer.

C.  

Get all the details from project team members to provide knowledge transfer.

D.  

Convince project team to outsource the knowledge transfer work.

Discussion 0
Questions 10

Health Records Modernization at Hospital Case Study

A project manager led a health records modernization project at a hospital with a project budget of $US5 million and an 18-month timeline. The project involved multiple stakeholder groups including medical, administrative, and IT staff; board members; patients; insurance companies; external vendors; regulatory bodies; and union representatives.

Stakeholder management was complex and a major undertaking for the project manager, but it was critical to achieve a positive project outcome. When the project started, the project manager conducted stakeholder analysis, using the information to create both a power/interest and an influence/impact matrix. The analysis showed that while the hospital board members and regulatory bodies had high power but moderate interest, the medical staff (doctors and nurses) had both high influence and high impact on the project. Administrative staff showed high interest but lower power, while patients and insurance companies had moderate interest and varying levels of influence. Based on the analysis, the project manager created a stakeholder engagement strategy that documented expectations, communication preferences, and influence levels in a stakeholder register. The project manager also made a RACI (responsible, accountable, consulted, informed) chart to show roles and responsibilities; and created communication channels and frequency for each stakeholder group, an issue escalation system, and a feedback system for continuous stakeholder input.

To execute the modernization process of health records, the project manager realized that medical staff members would need to change their daily workflows. To facilitate change management for these stakeholders, the project manager created a clinical advisory committee, appointed department-specific “champions,” created focus groups for requirements gathering, started a training program, and developed key performance indicators (KPIs) to measure satisfaction.

During project execution, several challenges emerged. The doctors expressed concerns about the system’s impact on patient care, the nurses’ union raised workload concerns, the IT department faced resource constraints, the insurance companies requested additional features, and the administrative staff worried about data security. The project manager responded to these challenges by increasing the frequency of stakeholder meetings, implementing a change management program, creating a beta system for stakeholder testing, developing contingency plans for various stakeholder scenarios, and establishing an issue resolution process.

Despite these mitigation efforts, the medical staff required additional training, leading to a change request for a 2-month extension and a 10% budget increase. The board of directors approved this to help ensure high adoption and satisfaction rates among staff members. The project helped establish new good practices in future programs for stakeholder management in the organization’s project management office (PMO). The documented lessons learned became a reference for future projects of similar scope and complexity.

On a project to modernize health records at a hospital, the project manager proposed a two-month timeline extension to provide training on the new solution for medical staff. Approval from the board of directors is required to make the timeline change.

Which statement represents the justification for extending the timeline? (Refer to the Health Records Modernization at Hospital Case Study exhibit.)

Options:

A.  

Funding is readily available to support a high-value change.

B.  

Stakeholder adoption of the solution is critical to positive project outcomes.

C.  

Training is mandatory for use of the solution among all stakeholders.

D.  

A cost-benefit analysis of the delay supports the value of the training.

Discussion 0
Questions 11

Health Records Modernization at Hospital Case Study

A project manager led a health records modernization project at a hospital with a project budget of $US5 million and an 18-month timeline. The project involved multiple stakeholder groups including medical, administrative, and IT staff; board members; patients; insurance companies; external vendors; regulatory bodies; and union representatives.

Stakeholder management was complex and a major undertaking for the project manager, but it was critical to achieve a positive project outcome. When the project started, the project manager conducted stakeholder analysis, using the information to create both a power/interest and an influence/impact matrix. The analysis showed that while the hospital board members and regulatory bodies had high power but moderate interest, the medical staff (doctors and nurses) had both high influence and high impact on the project. Administrative staff showed high interest but lower power, while patients and insurance companies had moderate interest and varying levels of influence. Based on the analysis, the project manager created a stakeholder engagement strategy that documented expectations, communication preferences, and influence levels in a stakeholder register. The project manager also made a RACI (responsible, accountable, consulted, informed) chart to show roles and responsibilities; and created communication channels and frequency for each stakeholder group, an issue escalation system, and a feedback system for continuous stakeholder input.

To execute the modernization process of health records, the project manager realized that medical staff members would need to change their daily workflows. To facilitate change management for these stakeholders, the project manager created a clinical advisory committee, appointed department-specific “champions,” created focus groups for requirements gathering, started a training program, and developed key performance indicators (KPIs) to measure satisfaction.

During project execution, several challenges emerged. The doctors expressed concerns about the system’s impact on patient care, the nurses’ union raised workload concerns, the IT department faced resource constraints, the insurance companies requested additional features, and the administrative staff worried about data security. The project manager responded to these challenges by increasing the frequency of stakeholder meetings, implementing a change management program, creating a beta system for stakeholder testing, developing contingency plans for various stakeholder scenarios, and establishing an issue resolution process.

Despite these mitigation efforts, the medical staff required additional training, leading to a change request for a 2-month extension and a 10% budget increase. The board of directors approved this to help ensure high adoption and satisfaction rates among staff members. The project helped establish new good practices in future programs for stakeholder management in the organization’s project management office (PMO). The documented lessons learned became a reference for future projects of similar scope and complexity.

During the execution phase of a project to modernize a hospital’s records system, the insurance company stakeholders requested additional features to support integration to their systems.

What should the project manager do first?

(Refer to the Health Records Modernization at Hospital Case Study exhibit.)

Options:

A.  

Contact the union representative to understand the necessity of the additional work.

B.  

Review the scope changes for validity and then notify the sponsor of the changes.

C.  

Evaluate the potential impact on the baseline and then present a change request.

D.  

Add the critical features to the scope in order to maintain stakeholder satisfaction.

Discussion 0
Questions 12

Abig corporation with a large quantity of well-documented procedures is planning to acquire a small company. The potential loss of key resources due to uncertainty

around the merger is a significant concern.

What should the project manager do?

Options:

A.  

Contract an external consulting firm to train new stakeholders in project management processes.

B.  

Review the stakeholder matrix and evaluate needs for future projects.

C.  

Create the risk register, evaluate the impact on projects, and share with the steering committee.

D.  

Allocate project resources to assess the impacts on the actual projects in execution.

Discussion 0
Questions 13

A product owner who possesses a strong technical background has been actively involved with the project team for several years. The product owner has been quite

vocal about the expected duration of the work. As a result, the project team has ceased providing development estimates to avoid causing any dissatisfaction with the

product owner.

What should the project manager do?

Options:

A.  

Conduct a meeting with the project team and the product owner to reset the ground rules for providing estimates.

B.  

Ask the project team to send the estimates via email and not to discuss them during planning meetings.

C.  

Facilitate the meetings and ask the project team for the estimates.

D.  

Meet with the product owner and project team separately to find a compromise.

Discussion 0
Questions 14

A project manager is leading a construction project for a retail store. The project manager is using a Gantt chart to present the workflow. One part of the project

includes custom software development to manage the store ' s lighting system, which uses solar energy.

How should the project manager accommodate software development in the project?

Options:

A.  

Group software development work into a single task block in the original schedule while using a hybrid management approach.

B.  

Revise the project schedule and run the project using an agile approach with iterations.

C.  

Isolate the software development tasks from the schedule to be a separate project.

D.  

Work with the project team to include software development as a unique task within the project schedule.

Discussion 0
Questions 15

A project team is tasked with implementing a new technology system for the end users. The project team currently lacks information on what the system is used for

and how the end users would use it.

What should the project manager do?

Options:

A.  

Request the project management office (PMO) if they can support with beneficial information.

B.  

Hire external expert resources who have the knowledge about the system.

C.  

Encourage the senior project resources to find out the purpose of the system.

D.  

Ask the sponsor to define the project objectives and goals in the project documents.

Discussion 0
Questions 16

The project manager is creating a status report to show the progress of completed training artifacts intended for delivery to bank branches for a new project for both

new and existing customers. During the review process, it is discovered that some of the artifacts were duplicated by two project team members.

What should the project manager do?

Options:

A.  

Motivate and inspire team members consistently to concentrate diligently on their designated tasks.

B.  

Speak with both team members individually and assign them specific new tasks.

C.  

Take a proactive approach and select what artifacts they want to work on.

D.  

Create a RACI (responsible, accountable, consulted, informed) matrix to communicate roles and responsibilities.

Discussion 0
Questions 17

A new government project is taking place in a period of regulatory instability. Despite previous meetings between regulators and project stakeholders, progress toward

project goals is uncertain. The project team is frustrated by scope changes. Some project team members are openly considering moving to another project.

What should the project manager do?

Options:

A.  

Suggest regulatory boundaries to avoid project disruption.

B.  

Provide a project charter to the regulators before the start of the project.

C.  

Postpone the project until regulations stabilize and release the team.

D.  

Ask the project sponsor to mediate a change control board (CCB) meeting.

Discussion 0
Questions 18

A developer has been assigned to complete a project task. At the end of a project meeting, the developer expresses concern about their lack of experience in the technology being used, compromising the project schedule.

What should the project manager do?

Options:

A.  

Work with the development team to reassign the project task to a senior developer.

B.  

Break down the project task into subtasks and assign a second developer to assist.

C.  

Set up mentoring sessions to assist the developer in completing the project task on time.

D.  

Conduct a risk assessment and monitor the project task to make sure it is completed on time.

Discussion 0
Questions 19

An organization, which has no previous experience with adaptive approaches, is seeking to adopt agile practices to improve the speed of value delivery to its internal business units. An agile expert has been engaged to assist the project manager in facilitating this transformation.

What should the project manager do?

Options:

A.  

Empower the agile expert to make required changes to the legacy processes.

B.  

Introduce the agile expert to the continual improvement manager for collaboration.

C.  

Schedule regular training sessions with the agile expert to ensure a successful transition.

D.  

Collaborate with the agile expert to implement a tailored strategy.

Discussion 0
Questions 20

A project manager is overseeing a hybrid project with two distinct workstreams: hardware operating predictively and software operating adaptively. However, the procurement contract for the software vendor has been finalized with clauses based on a predictive way of working. Meanwhile, many software work items are undergoing different prioritizations on the Kanban board.

What should the project manager do?

Options:

A.  

Change the structure of the contract with the vendor.

B.  

Evaluate the option of developing the software internally.

C.  

Perform a risk-impact assessment.

D.  

Go through a formal change control process.

Discussion 0
Questions 21

A logistics project is anticipating significant delays in the next few months. The project manager makes a list of the causes of the delays before thinking about how to minimize them.

How should the project manager prioritize which delays to take action on? (Select each box from the Items list and drag and drop it into either the Risk Register or Issue Log box.)

Options:

Discussion 0
Questions 22

Ahigh-performing team is working diligently to deliver a project ahead of schedule. While the deliverables meet the necessary quality standards, the team member

responsible for this aspect of the project exhibits inadequate skills in quality management and lacks enthusiasm for the task.

What should the project manager do?

Options:

A.  

Mentor the team member and facilitate knowledge sharing on quality management by an expert.

B.  

Assign a specialist to assist in completing any quality reporting because the project is halfway through completion.

C.  

Use the available budget reserves and outsource the quality management activities to an external firm.

D.  

Escalate the issue to the team member ' s functional manager and request assistance with quality controls.

Discussion 0
Questions 23

A project manager is leading a software development project. During the second sprint, there is a change in the company ' s artificial intelligence (Al) policy that now

permits using the organization ' s proprietary generative Al model, which the software development team can use to increase coding efficiency.

What should the project manager do first?

Options:

A.  

Arrange for the needed training before implementing the change.

B.  

Trigger the change management process for immediate actions.

C.  

Assess the impact of the change to understand the risks involved.

D.  

Meet with the stakeholders to get their consensus about the change.

Discussion 0
Questions 24

A project team is planning a university graduation ceremony. During a team meeting, a team member disagrees with the project manager on the prioritization of

project activities. The team member thinks that it would be more efficient to prioritize the sponsorship instead of preparing a budget since a budget template already

exists.

What should the project manager do?

Options:

A.  

Meet with the individual and their manager to discuss activity concerns.

B.  

Review the list of activities with stakeholders.

C.  

Ask the team member to schedule a meeting with the sponsor.

D.  

Consider the team member ' s opinion.

Discussion 0
Questions 25

Amigration deployment is scheduled in 2 weeks, and a stakeholder is requesting a code change. The code change requires two developers, and testing the code will

require two quality engineers. Further, the change will push the planned deployment date back by 1 week and delay the start of the next migration.

What action should the project manager take?

Options:

A.  

Evaluate the priority and impact of the change and move the planned deployment by 1 week.

B.  

Ask another project team to make the change later and proceed with the planned deployment date.

C.  

Proceed with the current code and make the change after the planned deployment date.

D.  

Make the requested change and move the planned deployment date back by 1 week.

Discussion 0
Questions 26

During the execution phase of a project, a new regulation is published. A subject matter expert (SME) on the project team contacts the project manager and tells them

that the new regulation might heavily impact the project ' s delivery.

What should the project manager do?

Options:

A.  

Request an immediate meeting with the SME and customer to evaluate the impact of the new regulation.

B.  

Circulate the information about the new regulation to all stakeholders and ask for feedback.

C.  

Request the SME prepare an extensive impact analysis of the regulation and provide to the project sponsor.

D.  

Measure the compliance of the project deliverables with the regulation to implement next steps.

Discussion 0
Questions 27

A project manager is leading a project to use Al to optimize the content moderation process for an online game. The project sponsor expects to make cost savings

with this optimization. The project manager sourced a few Al technology vendors, making a final decision with the team. After launching the product with the new Al

feature, a key stakeholder questions why the team did not build a custom Al module to save money in the long term.

What should the project manager do?

Options:

A.  

Work with the senior management to initiate a change request of implementing a custom Al model.

B.  

Order the team to prepare an estimation of reimplementing the feature using a custom Al model.

C.  

Review project documents and make sure the implementation has followed the requirements.

D.  

Ask the providers to make a presentation about the potential savings in the long term.

Discussion 0
Questions 28

Alpha Project — Risk Management Report

The Alpha Project risk management report includes the following information:

- Risk monitoring is built into risk sessions.

- Risk identification / assessment is performed.

- Monthly review and reassessment are performed.

- 21 risks have been identified so far.

- Probability and impact have been estimated for every risk.

- All response plans have been completed.

- A probability and impact matrix is provided using green, yellow, and red severity zones.

The project manager of Alpha project is running a monthly risk review and reassessment meeting. During the meeting, the team confirms that risk 5 has materialized.

What should the project manager do?

(Refer to the Alpha Project — Risk Management Report exhibit.)

Options:

A.  

Coordinate execution of risk 5 response plan activities.

B.  

Communicate the issue to the project sponsor.

C.  

Focus on risk response plans for red risks.

D.  

Move risk 5 from the risk register to the issue log.

Discussion 0
Questions 29

After a client requested multiple changes to the project scope during a sprint, the sprint goal was no longer valid.

What should the Scrum Master do?

Options:

A.  

Use the sprint to review lessons learned and arrange training sessions.

B.  

Ask the product owner to determine whether the sprint should be canceled.

C.  

Ask the team to work on technical-debt items from the product backlog.

D.  

Escalate the issue to senior management to prevent further changes.

Discussion 0
Questions 30

A project manager is leading an online learning system development project for a government body. The project team is working on a new feature that needs a very

stable video streaming platform. A stakeholder from marketing suggests using a platform that has been used in other marketing projects. Following the endorsement

of senior management, the team soon adopts this platform. Yet during development, the team finds that the platform cannot handle multilanguage subtitles, which are

critical to the online learning system.

What should the project manager have done to avoid this situation?

Options:

A.  

Ensured identification and documentation of detailed requirements as well as acceptance criteria before selecting the solution.

B.  

Arranged a meeting between the stakeholder and the team to make sure the recommended streaming platform met all requirements.

C.  

Reviewed the process and made sure the technical staff was properly authorized to select the program that met all requirements.

D.  

Asked the streaming platform provider to give a presentation to all stakeholders and the project team.

Discussion 0
Questions 31

An agile project in progress has a large number of blocked items and the project manager does not have visibility on the underlying issues. What should the project manager do to allow transparency and remove the blockers?

Options:

A.  

Create a shared kanban board for the team to have visibility of the items.

B.  

Hold a war room meeting with relevant people to address the blockers.

C.  

Change the project status to “on hold” to inform the sponsor about the blockers.

D.  

Conduct a retrospective meeting to gain visibility on what is happening.

Discussion 0
Questions 32

During a team ' s weekly status meeting, team members have minor disagreements about how to perform work and some defer to the team lead while others speak

confidently. The project manager realizes that team members have different expectations of the team ' s dynamics and operating model.

What should the project manager do?

Options:

A.  

Create a team charter to define and document the expectations at the team level.

B.  

Document the expectations based on a previous project and share these with the team.

C.  

Ask the sponsor to document the team expectations and share these with the team.

D.  

Create a team charter and ask the project sponsor to communicate the expectations.

Discussion 0
Questions 33

A project manager is assigned to a multimillion-dollar project. Senior stakeholders are not happy with the project objectives.

What should the project manager do?

Options:

A.  

Set up regular individual meetings with key stakeholders to explain the project objectives.

B.  

Send regular project reports to key stakeholders reminding them of the project objectives and vision.

C.  

Engage with key stakeholders to address their concerns and try to achieve a shared project vision.

D.  

Ensure key stakeholders are included in the stakeholder management plan as a risk for the project.

Discussion 0
Questions 34

During a sprint review, the customer described a strong market trend that will highly impact the product vision and the project management plan. What should the

project manager do?

Options:

A.  

Acknowledge the changed value proposition and request the team undo the scope of the last sprint.

B.  

Interrupt the customer and underline the importance to stick to the approved documents.

C.  

Review the customer ' s needs and define the backlog items according to the situation.

D.  

Continue executing the project backlog as planned and introduce the changes in later stages.

Discussion 0
Questions 35

A project manager is identifying stakeholders for a research project. The stakeholders that are included are individuals from academia, industry, and government.

What should the project manager do once stakeholders are identified?

Options:

A.  

Communicate with the stakeholders about the progress of the project on a regular basis.

B.  

Conduct facilitation sessions with the stakeholders to understand and align their expectations.

C.  

Focus on key stakeholders who are critical to the project.

D.  

Engage the stakeholders based on their influence on the project.

Discussion 0
Questions 36

Aclient in a consulting firm presents an aggressive product implementation schedule. Key aspects of the scope have not been defined, and several internal

stakeholder decisions are still pending. This situation is delaying the request for proposals (RFPs) from the vendors.

What should the project manager do?

Options:

A.  

Contact the client and offer to facilitate sessions with internal stakeholders to finalize the decisions.

B.  

Negotiate the initial proposals with the vendors and update the proposal accordingly once the scope definition is complete.

C.  

Inform the client that the key scope decisions must be completed before the proposals can be sent.

D.  

Update the schedule to accommodate the delays and set up a meeting to inform the client.

Discussion 0
Questions 37

A project team is working to plan a professional networking event. A RACI (responsible, accountable, consulted, informed) matrix was developed and validated by all

stakeholders. Two months before the event, enrollment is much lower than expected. It appears that the marketing team did not promote the event.

What should the project manager do next?

Options:

A.  

Email the marketing team the RACI matrix assignments and remind them of their commitments.

B.  

Email the executive board to alert the organization to the risk of lost profit on this event and ask for advice.

C.  

Follow up with the marketing team to confirm they have received the event information and understand their tasks.

D.  

Meet with the event sponsor to discuss potentially cancelling or postponing the event.

Discussion 0
Questions 38

A project manager is working for a multinational financial services company that does business in more than 100 countries. The company is rolling out a time

management system in multiple countries.

What should the project manager do?

Options:

A.  

Invite stakeholders to monthly, informal meetings.

B.  

Email the project schedule frequently to all stakeholders.

C.  

Communicate progress to stakeholders in their preferred ways.

D.  

Share the work breakdown structure (WBS) with stakeholders regularly.

Discussion 0
Questions 39

A scrum master is leading an agile project to develop a video game product. Midway through a sprint, the customer asks the team to immediately add a new feature

to the product. The team asks the scrum master for guidance.

What should the scrum master do first?

Options:

A.  

Add it to the product backlog.

B.  

Negotiate increasing the sprint length.

C.  

Estimate effort for the new feature.

D.  

Add it to the current sprint.

Discussion 0
Questions 40

A project in a fast-changing, demanding business environment has been initiated. An agile approach has been chosen to maximize collaboration and transparency.

What should the agile project manager do to support these goals?

Options:

A.  

Create a work breakdown structure (WBS) for the team with an upfront project management plan.

B.  

Allow the team members to choose their work priorities and track their progress during daily coordination meetings.

C.  

Work with the product owner and team to create user stories and draft a high-level project management plan.

D.  

Schedule weekly review meetings with all stakeholders to discuss project progress candidly.

Discussion 0
Questions 41

A project team is in the process of selecting a module for the upcoming iteration. They have identified three potential modules as candidates. Despite several rounds

of review, the team remains undecided on which module to select.

What should the project manager do?

Options:

A.  

Aska colleague to select the module and inform the team of their decision.

B.  

Evaluate the options with the team and assess the workable option based on consensus.

C.  

Select the simplest module to develop since complex ones will require more iterations.

D.  

Select the most appropriate module to be placed in next iteration.

Discussion 0
Questions 42

A project team is gathering requirements for a commercial off-the-shelf technology product. The project manager is not sure if the requirements gathered was

complete.

What should the project manager do?

Options:

A.  

Ask the stakeholders to review the requirements and send them to the acquisition team.

B.  

Instruct the project team to analyze the collected requirements across the acceptance criteria.

C.  

Instruct the project team to collect secondary requirements from the stakeholders.

D.  

Prompt the artificial intelligence (Al) to generate the existing and the future requirements.

Discussion 0
Questions 43

A project manager works for a communications company. The manager of the mobile equipment department is concerned about the current project ' s activities.

According to the current project management plan, the department will need to purchase special equipment, but the cost was not planned. The project sponsor insists

the project should move forward because customers will be impacted if the equipment is not available.

What should the project manager do?

Options:

A.  

Escalate the conflict to the project sponsor.

B.  

Use the contingency reserve to fund the equipment cost.

C.  

Resolve the issue in favor of the department manager to continue the project.

D.  

Estimate the cost of purchasing the equipment and submit a change request.

Discussion 0
Questions 44

During project implementation, the project manager is communicating information about changes only at the executive level. Many people within the organization are uncertain about the project ' s status. There are rumors about changes to the project and how they may affect work activities.

What should the project manager do?

Options:

A.  

Host a town hall meeting to share the project details with the entire organization.

B.  

Create a project FAQ document, update it as needed, and distribute to all organizational levels.

C.  

Revise the communications management plan to share project information at all levels.

D.  

Maintain the current communication structure and address questions as they arise.

Discussion 0
Questions 45

At the postevent review of an annual conference, the project manager realizes that the team could benefit from improvements in how they handle sponsorship

agreements and event logistics. Specifically, the team found that having clearer contracts with sponsors earlier in the planning process would help avoid last-minute

issues.

How should the project manager handle the organizational process assets (OPAs)?

Options:

A.  

Focus on updating the OPAs with feedback from attendees about the sponsor contract process.

B.  

Align the OPAs with general event management guidelines based on industry good practices.

C.  

Wait until the next event is completed before updating the OPAs so the recommendations are validated before documenting.

D.  

Update the OPAs with the recommendations based on the current project evaluation of the sponsor contract process.

Discussion 0
Questions 46

A project manager is leading a project for a pharmaceutical company. Due to changes in the international market, the project has to be terminated. The project

manager is following company procedures to document the reasons for early termination.

What should the project manager do?

Options:

A.  

Communicate with stakeholders.

B.  

Initiate the project closing process.

C.  

Perform change control procedures.

D.  

Conduct risk management exercises.

Discussion 0
Questions 47

As part of a restructuring effort, a company has transitioned from a projectized to a functional organization. The project manager is concerned that the team members will become disengaged from their work on the current project because they are now reporting to a functional manager.

What should the project manager do?

Options:

A.  

Work with the functional manager to assign goals related to the project to the team.

B.  

Advise the functional manager to ask the organization for additional resources as part of a mitigation plan.

C.  

Update the resource management plan with the organizational changes.

D.  

Meet the team and explain that organizational changes are transparent to the team.

Discussion 0
Questions 48

A project to replace a legacy process is in the initiation phase. The project manager needs to send requests for proposals to potential vendors. The business case contains the project’s high-level goals, and all potential vendors have previously delivered similar projects.

What should the project manager do to ensure that activities and tools from the legacy process are retained when necessary?

Options:

A.  

Develop the solution design document (SDD) in consultation with business managers and developers.

B.  

Develop the business requirements document (BRD) in consultation with users of the previous system.

C.  

Develop the business requirements document (BRD) in consultation with business managers.

D.  

Develop the solution design document (SDD) in consultation with developers and suppliers.

Discussion 0
Questions 49

A virtual team updates a kanban board weekly with project progress. Recently, team members have raised concerns about properly tracking interdependent activities

How should the project manager address this issue?

Options:

A.  

Assign one team member as accountable to monitor interdependent activities that are related on an ongoing basis.

B.  

Assign activities that are interdependent to the same team members to avoid complexity and ensure progress monitoring.

C.  

Adapt the tool for better monitoring and reporting of the interdependent activities’ progress.

D.  

Register the issue in the project backlog so that the project team may address it in next iteration.

Discussion 0
Questions 50

In the last project status meeting, a team member reported some tasks with conflicting priorities. Now, other team members are delayed in their tasks due to the

dependencies.

What should the project manager do to address this situation?

Options:

A.  

Analyze the critical path and request additional resources.

B.  

Work with the team members to balance the workload.

C.  

Create a change request and update the project schedule.

D.  

Escalate the issue with the team member to their functional manager.

Discussion 0
Questions 51

In a project meeting, the development team reported a delay in a critical activity. The root cause of the delay was traced to a missing response from the legal department.

What should the project manager do?

Options:

A.  

Review the processes for reporting issues and the escalation paths with the project team.

B.  

Schedule a session with the legal and development teams to resolve the issue.

C.  

Work with the legal team and the project sponsor to resolve the issue immediately.

D.  

Escalate the issue to the project sponsor to get support for the development team.

Discussion 0
Questions 52

A project is delivering a new e-commerce platform. During execution, external market trends show shifting customer preferences toward mobile-first experiences.

There is uncertainty about whether the current feature set will meet user expectations.

What should the project manager do?

Options:

A.  

Complete the current release and evaluate customer feedback after launch.

B.  

Continue the current scope to maintain alignment with the original business case.

C.  

Change the current scope to remove low-priority features and reduce schedule risk.

D.  

Conduct a survey to gauge customer interest in the existing feature set.

Discussion 0
Questions 53

A project manager is leading an ongoing project for a highly reputable international client. A few hours before the final review meeting, during which the client is expected to accept the project and authorize a substantial payment, the project manager’s company suffers a cyberattack. The client is very strict and maintains that any missed deadlines will result in a considerable penalty.

What should the project manager do?

Options:

A.  

Call an internal meeting with senior leadership to define the next actions.

B.  

Follow the business continuity strategy to keep the project in operation.

C.  

Find an alternative communication platform on which to conduct the review meeting.

D.  

Consult the client to determine potential courses of action.

Discussion 0
Questions 54

A project manager works for a company that recently won a big government contract. The company has a flat hierarchy and self-organized teams. The client wants

the project manager to use a predictive management approach and an up-front project management plan. However, the project manager knows that a more agile

approach would be better due to the high uncertainty of the project scope.

What should the project manager do?

Options:

A.  

Use a predictive management approach and update the risk register to account for uncertainties.

B.  

Comply with the client ' s request and adjust the team ' s way of working to a predictive approach.

C.  

Propose a hybrid style to the client to accommodate the nature of the project and their work structure.

D.  

Identify the best project life cycle in collaboration with the project team and the stakeholders.

Discussion 0
Questions 55

A project team is equipping a small hospital. To complete the work, the team requires an additional service provided by an external supplier. The price quoted by the

supplier is surprisingly high, which may cause a significant increase in the budget.

What should the project manager do?

Options:

A.  

Utilize the contingency reserve to manage the procurement.

B.  

Discuss using the management reserve with the sponsor.

C.  

Ask the procurement manager to find another supplier.

D.  

Request the supplier fulfil their obligations by adjusting costs.

Discussion 0
Questions 56

A project manager is leading a project focused on developing a machine learning platform. Midway through the project, the project manager learns of a new

regulatory policy that will significantly change the way data is stored, processed, and manipulated.

What should the project manager do?

Options:

A.  

Reevaluate the scope, timeline, and work breakdown structure to include the new requirement.

B.  

Consult with the compliance experts to evaluate the possible impact.

C.  

Inform the project sponsor about the new policy and review the available budget.

D.  

Update the project scope and risk register to conform with the new policy.

Discussion 0