Big Black Friday Sale 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exams65

ExamsBrite Dumps

Project Management Professional (2025 Version) Question and Answers

Project Management Professional (2025 Version)

Last Update Nov 30, 2025
Total Questions : 2040

We are offering FREE PMP PMI exam questions. All you do is to just go and sign up. Give your details, prepare PMP free exam questions and then go for complete pool of Project Management Professional (2025 Version) test questions that will help you more.

PMP pdf

PMP PDF

$139.65  $399
PMP Engine

PMP Testing Engine

$157.15  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$209.65  $599
Questions 1

An organization is altering their schedule, and the project team is now expected to be in the office together once a week. Despite everyone being dedicated to the project, the team members all follow their functional teams' schedules, which differ from one another.

How should the project manager address this situation?

Options:

A.  

Look into the option of changing the status of all team members to being fully remote.

B.  

Look into changing the company's policy from 1 day to 2 days on-site.

C.  

Work with the team to determine if the in-person project day is required.

D.  

Work with the functional managers and get an exception for the team members.

Discussion 0
Questions 2

A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case.

What should the project manager do?

Options:

A.  

Ensure the client representative is involved in the estimation.

B.  

Review the completion costs of similar projects.

C.  

Ensure that a 20% contingency is included in the estimation.

D.  

Review the lessons learned from similar projects.

Discussion 0
Questions 3

A customer's technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog. At the end of the sprint, all of the planned stories were not completed because the new feature took more time.

What should the project manager do next?

Options:

A.  

Agree with the project team to modify and delete some of the stories in the current sprint backlog

B.  

Obtain approval from the project team and add the new story to the product backlog

C.  

Receive an agreement from the product owner and add the new story to the product backlog

D.  

Negotiate with the scrum master before adding the new story to the sprint backlog

Discussion 0
Questions 4

A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project's value and caused a delay in the approval.

What should the project manager have done to avoid this setback?

Options:

A.  

Assessed feasibility and impacts

B.  

Developed benchmarking

C.  

Analyzed stakeholders

D.  

Detailed the project charter

Discussion 0
Questions 5

During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule.

What should the project manager do first?

Options:

A.  

Perform an impact analysis with subject matter experts (SMEs).

B.  

Inform the government representative about the impact of the separate project.

C.  

Implement a change request to increase the budget and schedule.

D.  

Consult and update the risk register with the project stakeholders.

Discussion 0
Questions 6

A team has had issues with behavior on an ongoing project, which is causing conflicts. As a result, the team is losing momentum and falling

behind in its sprints.

How should the project manager handle this situation?

Options:

A.  

Engage a counselor to reconcile the situation between the team members affected.

B.  

Control backlog assignments and reduce direct communications between team members.

C.  

Revisit the ground rules and team communication protocols, and discuss what is happening.

D.  

Require team members experiencing the conflicts to take a day off from work.

Discussion 0
Questions 7

In a financial company, a strategic project has been planned to use a predictive approach. During project planning, the product leader requests

that milestones be submitted for review. There is a defined scope and an established deadline to conclude the project.

What should the project manager do first to meet the product leader's expectations?

Options:

A.  

Change the project charter to indicate that the approach will be different.

B.  

Inform the product leader that they must wait until the end of the project.

C.  

Meet with the software team to review the possibility of monthly milestone reviews.

D.  

Modify the project management plan to use an agile framework to incorporate milestones.

Discussion 0
Questions 8

A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected.

What should the project manager do?

Options:

A.  

Support the team in identifying the area of development and address the gap.

B.  

Dissolve the team and include the team members in other existing teams.

C.  

Identify the struggling team members and move them out of the team.

D.  

Set up a clear expectation that the team is to deliver as in their previous projects.

Discussion 0
Questions 9

A project manager is working on a project to transform the service delivery model in the organization. As part of the scope, this project includes diverse elements that have been well defined by the product owner. The team has expressed that the scope is not clearly defined.

How should the project manager address this situation?

Options:

A.  

Distribute the release plan among the team members.

B.  

Ask the team members to focus only on their assignments.

C.  

Ask the product owner to clarify the project's vision with the team.

D.  

Meet with the product owner to validate the backlog prioritization.

Discussion 0
Questions 10

A project for a financial organization is in the proposal phase for the selection of a software tool. There have been conflicting opinions on the software that was ranked in the selection. After analyzing the issue, the project manager realizes that two out of the eight teams have concerns about the tool's scalability to support their business needs.

How should the project manager resolve this conflict and reach a consensus?

Options:

A.  

Escalate this to senior management and ensure that the team's acceptance is achieved.

B.  

Communicate to the two teams that the tool has won per the selection process and they need to accept the outcome.

C.  

Ignore the conflict as the tool is selected per the proposal guidelines and the project is complete.

D.  

Discuss the outcome of the proposal process and the ranking, then influence the team for acceptance.

Discussion 0
Questions 11

In a global project, the main definitions were developed in country A, and the delivery of the project will be completed in phases in countries B, C, and D. Country B discovers that one of the legal requirements was not addressed.

What should the project manager have done to avoid this situation?

Options:

A.  

Selected countries that had similar regulatory requirements.

B.  

Asked procurement to assign resources located in each country.

C.  

Managed risk mitigation strategies specific to each country.

D.  

Identified the regulatory differences among the countries.

Discussion 0
Questions 12

A project manager has just been hired by a company without a project management governance structure. During the kick-off meeting, a key stakeholder emphasizes the

importance of the project meeting the company's strategy, investment, and compliance requirements.

What should the project manager do?

Options:

A.  

Replicate the organizational governance to the project governance.

B.  

Put into place a project governance model in line with the requirements.

C.  

Create an organizational project management governance.

D.  

Ask the organization to create a project portfolio governance.

Discussion 0
Questions 13

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?

Options:

A.  

Ask the team to raise blockers or impediments in daily meetings.

B.  

Prioritize deliverables based on business value and define frequent releases.

C.  

Ask the team to challenge the project estimations for a faster delivery.

D.  

Prioritize the tasks with high risks to reduce the number of iterations required.

Discussion 0
Questions 14

A project management office (PMO) is currently stretched for project control resources. Specifically, the cost control resources are short of the staff required for this activity level. A new project is about to start soon.

What should the project lead do to obtain the needed resources?

Options:

A.  

Evaluate running the project without the required resources and depend on the lessons learned from similar past projects.

B.  

Prepare to perform the duties of the cost controller for the duration of the project.

C.  

Meet with the PMO team and review the resource management plan ahead of the project kickoff to ensure resource availability.

D.  

Inform the project sponsor and initiate a recruitment exercise outside of the PMO.

Discussion 0
Questions 15

A project management office (PMO) director finds that the project managers leading software development projects are not consistently seeking approval from other division leaders in cybersecurity and operations before deploying code into production. The PMO director asks the project manager to develop a solution for this issue.

What should the project manager do to fix this problem?

Options:

A.  

Establish a daily scrum meeting and invite division leaders to attend so they can be aware of upcoming code releases.

B.  

Provide division leaders with a teleconference phone number to call if they have concerns after code is deployed into production.

C.  

Create a new policy requiring project managers to email division leaders before deploying code into production.

D.  

Launch an enterprise governance structure comprised of division leaders to establish policies for code releases.

Discussion 0
Questions 16

A project manager was suddenly asked to take over an ongoing project without any handover. During the first meeting, the project sponsor raised concerns about whether the project was on track to deliver the intended benefits.

What should the new project manager do first?

Options:

A.  

Review the business case to gather information about the project.

B.  

Initiate a rebaselining of the project based on the project sponsor's concerns.

C.  

Discuss the items in the requirements register with the project team.

D.  

Meet with the project stakeholders to understand the project sponsor's concerns.

Discussion 0
Questions 17

A project manager is leading an integration project for a retail company. The project demands a lot of time from the stakeholders to make important business decisions. The project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this project?

Options:

A.  

Add time reserve in the project schedule to allow extra time for the stakeholders to make decisions.

B.  

Share the project schedule, milestones, and meeting agendas with the stakeholders ahead of time.

C.  

Work with the available stakeholders to make business decisions and keep all unavailable stakeholders informed.

D.  

Schedule meetings with all of the stakeholders to make business decisions when needed.

Discussion 0
Questions 18

When a project is in its final stage, the project manager will request from the team to prepare a delivery acceptance document. What is the

importance of this document to the project manager?

Options:

A.  

Needed to close the work breakdown structure (WBS).

B.  

Needed to share it with the stakeholders.

C.  

Needed to close out the project or a phase.

D.  

Needed to release the team at the end of the project.

Discussion 0
Questions 19

A startup company has just appointed a CEO that has no prior project experience. The CEO wants to execute projects with their own resources

and has appointed a project manager.

What should the project manager recommend that the CEO do first?

Options:

A.  

Create a framework to justify project execution.

B.  

Utilize an agile approach for all upcoming projects.

C.  

Create a framework to support project success.

D.  

Utilize a predictive approach for all upcoming projects.

Discussion 0
Questions 20

A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.

What two things should the project manager do? (Choose two)

Options:

A.  

Discuss the issue with the external supplier's authority.

B.  

Review the lessons learned from similar past projects.

C.  

Gather additional information and estimate the impact.

D.  

Update the risk log and bring this up in the meeting with the client.

E.  

Wait for the client to raise a concern and collect more information.

Discussion 0
Questions 21

A project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project.

What should the project manager do next?

Options:

A.  

Discuss this issue with the affected team members and support them during the transition.

B.  

Start looking for replacements as soon as possible to help prevent any schedule slippage.

C.  

Engage with the project sponsor to ensure that this change does not affect the project execution.

D.  

Determine the impact to the project and implement mitigations per the project management plan.

Discussion 0
Questions 22

A new file vault system vendor is being considered by a protect sponsor who has supported several projects over the previous year What should the project manager review to assist the sponsor on the decision?

Options:

A.  

Lessons learned database

B.  

Procurement strategy

C.  

Vendor's website

D.  

Appropriate financial regulations

Discussion 0
Questions 23

A team realizes that there is no access to data that the project depends on to complete the current iteration. This dependency was known; however, the team is unsure of the available options to remove this obstacle.

What should the project manager do next?

Options:

A.  

Guide the team to determine alternatives.

B.  

Move the dependent task to the next iteration.

C.  

Escalate the issue to the company's IT manager.

D.  

Escalate the issue to the project sponsor.

Discussion 0
Questions 24

In a software project using an agile approach, there have recently been work

overruns. After assessing the situation, the project manager concluded that the overruns are

occurring because of insufficiently refined product backlog items.

What should the project manager do to correct this issue?

Options:

A.  

Work with the sponsor to revise the product vision.

B.  

Create a definition of ready (DoR) for the backlog items.

C.  

Discuss the issue with the service request manager.

D.  

Refine the product backlog items with the stakeholders.

Discussion 0
Questions 25

A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items

What should the project manager do as a servant leader?

Options:

A.  

Ask the sponsor to submit a change request to the change control board (CCB)

B.  

Support the product owners decision to change the priority of the product backlog items

C.  

Accept the request and include the product backlog items in the next sprint

D.  

Review the impact of the change on the schedule management plan baseline

Discussion 0
Questions 26

A project team has installed software for the client, passed the knowledge to operations, sent the final report, and celebrated. Then 1 week later,

the client sendsa list of requirements that have not been met. The client is requesting to fix the issues quickly and within the initial budget.

What should the project manager have done to prevent this from happening?

Options:

A.  

Reviewed the acceptance criteria and obtained client approval.

B.  

Allocated a risk budget for any post-release improvements.

C.  

Conducted a pilot to understand the client's performance parameters.

D.  

Established meetings with the client throughout the project phases.

Discussion 0
Questions 27

A project manager analyzes the cumulative flow chart and identifies a bottleneck in the testing activities from a self-organizing team. After discussing it with the team, a gap related to testing skills is identified.

What should the project manager do to address the issue?

Options:

A.  

Onboard a new project team member who has testing skills.

B.  

Provide training to the entire team so they all will be able to perform tests.

C.  

Support the team to identify an approach to resolve the problem.

D.  

Ask the development team to slow down so the testers can catch up.

Discussion 0
Questions 28

A project manager has completed an assessment of the project team's performance. Some team members have performed poorly on their assigned tasks.

What should the project manager do?

Options:

A.  

Develop different approaches based on team members’ motivation and ability.

B.  

Develop a standard approach to provide feedback to all team members.

C.  

Provide intensive oversight to the team members who performed poorly.

D.  

Create a new standard performance measure based on project requirements.

Discussion 0
Questions 29

During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not convinced that the return on investment (ROI) can be achieved.

How should the project manager address this issue?

Options:

A.  

Re-visit the project charter and seek other alternatives.

B.  

Proceed and issue the purchase order as this project is important.

C.  

Speak with the CEO and ask for their support to approve the offer.

D.  

Analyze the bounds of negotiations for project agreements.

Discussion 0
Questions 30

A project manager and project team are developing a strategic approach to engage the internal and external stakeholders. Which approach should be followed?

Options:

A.  

Schedule status meetings with all stakeholders to allow their participation in all project discussions and reports.

B.  

Analyze both internal and external stakeholders and develop a customized engagement strategy for each stakeholder.

C.  

Involve only the internal stakeholders, as the external stakeholders should not have access to confidential information.

D.  

Classify all high-risk stakeholders and request that the project sponsor communicate directly with them.

Discussion 0
Questions 31

A project with a hard timeline is starting its first iteration out of six. The project team is lacking the necessary skills to execute.

What should the project manager do?

Options:

A.  

Allow the team to proceed as they attempt to meet the timeline.

B.  

Add a subject matter expert (SME) to the project team.

C.  

Invite stakeholders to discuss a mitigation plan to finish on time.

D.  

Fill the skill gap personally to execute the project.

Discussion 0
Questions 32

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped

How should the project manager handle the situation?

Options:

A.  

Remove the items no longer applicable from the backlog and present the backlog to the project team

B.  

Continue working on the defined scope and review the risk matrix

C.  

Have a discussion with the project sponsor and cancel the project

D.  

Have a discussion with the sponsor and recommend the project business value be reassessed

Discussion 0
Questions 33

An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team Due to other priorities for the IT team the releases are delayed

What action should the project manager take?

Options:

A.  

Escalate the issue from the IT team to management and get the validation prioritized

B.  

Work with the IT team to prioritize the validation and release of the new features

C.  

Deliver the features when the IT team is able to validate them

D.  

Request the IT team to immediately release the product and then validate the features

Discussion 0
Questions 34

A steering committee member is complaining about the weekly report. They stated that the report is too long and has unnecessary details. As a result, they are unable to obtain the main message and take action.

What should the project manager do to avoid similar complaints?

Options:

A.  

Present the status at a weekly meeting with the steering committee.

B.  

Verify the information needed for steering committee members.

C.  

Send a shorter daily report to this steering committee member.

D.  

Demonstrate the weekly reports in a presentation for the steering committee member.

Discussion 0
Questions 35

A team member is openly criticized by others during a standup meeting for failing to

complete yesterday's tasks. What should the agile coach do first to address the situation?

Options:

A.  

Emphasize the ground rules and then focus on today's activities and impediments.

B.  

Let the discussion go on as it is important that the team is clear on priorities for theday.

C.  

Address the team members involved during the next sprint retrospective.

D.  

Avoid the discussion by referring to the team charter.

Discussion 0
Questions 36

A project manager is working on a project to develop a new watch at a matrix organization.

Which two key items should the project manager include in their feedback to external stakeholders? (Choose 2)

Options:

A.  

Schedule performance index (SPI) for the portfolio

B.  

Earned value in terms of resources

C.  

Expected return on investment (ROI) for portfolio projects

D.  

Earned value in terms of schedule

E.  

Earned value in terms of cost

Discussion 0
Questions 37

Two members of a new project team disagree on the best approach to solve a problem. The conflict has been going on for 1 week. The two

members are tense around each other and are taking everything personally.

What should the project manager do?

Options:

A.  

Help the team members to resolve the conflict in a way that results in the best team performance.

B.  

Offer a compromise that is acceptable to both team members, even if it may not be the best solution.

C.  

Understand each team member's argument and select the one that results in less risk to the project.

D.  

Send both team members to the human resources (HR) department for an acceptable resolution.

Discussion 0
Questions 38

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some

reserves needed

What should the project manager do to successfully complete the next phase?

Options:

A.  

Request a reserve analysis and update the risk management plan

B.  

Update the risk response plan to include the needed reserve

C.  

Perform a schedule network analysis to avoid any critical path delays

D.  

Review the risk response plan to verify inclusion of the needed reserve

Discussion 0
Questions 39

A project manager is managing a government project that targets the development of

small businesses in remote towns. The project team is having difficulty conducting

entrepreneurship training in some of the targeted towns because the local municipal

governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?

Options:

A.  

The project should have constructed training centers in the remote towns.

B.  

The project did not identify and engage the correct stakeholders.

C.  

The project should have representatives in all the remote towns.

D.  

The project did not fully engage the project sponsor.

Discussion 0
Questions 40

A project manager has recently joined a small company. The company's chief

operating officer (COO) asked the team to skip some steps in the process in order to work

more quickly. The project manager wants to ensure that these steps are not skipped in the

future.

What should the project manager do?

Options:

A.  

Notify all team members that all steps in the process must be completed.

B.  

Escalate the issue to the other executive leadership members.

C.  

Schedule a review of the process steps with the team and the COO.

D.  

Redesign the process so the team can move more quickly.

Discussion 0
Questions 41

A company's board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff

What should the project manager do first?

Options:

A.  

Request a meeting with the project sponsor to discuss the viability of the project and determine the next actions

B.  

Request a meeting with the customer and discuss trade-offs to reduce the scope and product quality as a result of the lack of personnel

C.  

Request a meeting with the finance department to increase the budget of the project to hire temporary personnel to perform the affected activities

D.  

Request a meeting with the human resources (HR) department and demand they find a solution to retain the project team members

Discussion 0
Questions 42

A project manager has been assigned to lead a software project to generate savings at an important financial institution. Initially, the duration of the project was 13 months,

but due to various issues during execution, the project was extended to 16 months. By month 11, the expected savings were exceeded but not all of the functionalities

planned for that date were fulfilled.

How should the project manager inform the stakeholders of the project's progress?

Options:

A.  

Report that the project has not fulfilled all the expected functionalities.

B.  

Complete the outstanding functionalities before informing the sponsor of the project progress.

C.  

Communicate the benefit expectations and the action plan for the pending functionalities.

D.  

Send an email with the monthly project progress to all relevant stakeholders.

Discussion 0
Questions 43

An important national project is in (he execution phase. A time constraint activity must be conducted on-site by a specialist from another country. Due to travel restrictions, the specialist cannot perform the activity on-site. The activity cannot be completed without the specialist's expertise. The project team is actively seeking assistance in order to complete the job on time.

What should the project manager do to help the project team?

Options:

A.  

Reschedule the project until the local travel restrictions are lifted.

B.  

Schedule virtual sessions with the specialist to guide the team in completing the activity.

C.  

Seek additional budget to train the project team on the required skill set.

D.  

Refer to the organization's lessons learned repository and find an alternative solution.

Discussion 0
Questions 44

A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te«... that another team is working on a product that could work as a solution, but it is still a prototype

What should the project manager do to accelerate this solution?

Options:

A.  

Contact the other project team and ask them to organize a demo of the prototype

B.  

Perform iterative planning with the team to use the prototype

C.  

Check the burnup charts to see what progress has been made to integrate the solution

D.  

Prioritize the backlog with the customer to remove the feature

Discussion 0
Questions 45

A new sales software development project is underway The customer is still finalizing the requirements for the system when a new CEO is introduced. The new CEO is expected to make changes to the organization, which most likely will impact development. However, the most important criterion for the project is that the software must provide correct sales results. No intermediate results are required.

Which project approach should the project manager take?

Options:

A.  

Incremental

B.  

Predictive

C.  

Hybrid

D.  

iterative

Discussion 0
Questions 46

A project manager works at an organization that is transitioning to agile The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.

What should the project manager do to ensure effective communication throughout the project?

Options:

A.  

Advise the project management office (PMO) to use the burndown chart as the single communication channel.

B.  

Develop a communications management plan for each category in the stakeholder register.

C.  

Include the burndown chart in a monthly report that is distributed to all stakeholders.

D.  

Postpone the recommendation since the organization does not currently have a defined agile methodology.

Discussion 0
Questions 47

A project manager has been assigned to lead a project with limited funding and resources. During the requirements brainstorming session, several stakeholders request a long list of requirements for a new project, which exceeds the budget.

What should the project manager do first?

Options:

A.  

Host a requirements workshop and ask the stakeholders to prioritize the requirements based on critical needs.

B.  

Review the requirements and determine which of them can be removed, then advise the stakeholders of the changes.

C.  

Meet with the sponsor to obtain their feedback regarding critical requirements in the view of senior management.

D.  

Reach out to the sponsor and request additional budget and capacity in order to complete the project.

Discussion 0
Questions 48

A project manager has just been appointed to a project that has two major deliverables. Both deliverables have the same level of priority and are to be delivered at the same time. The members of the team are complaining about the lack of information regarding which deliverable needs to be finished first.

What should the project manager do?

Options:

A.  

Ask key stakeholders to cancel the project due to the difficulty of executing both deliverables at the same time.

B.  

Ask the team to start working on the easiest deliverable first so they gain experience to execute the second deliverable.

C.  

Meet with the project sponsor and key stakeholders to assess each deliverable's value to the organization and set execution priorities.

D.  

Require that the project team execute both deliverables at the same time, since this was requested and approved in the project charter.

Discussion 0
Questions 49

A project manager is leading a hybrid project. The self-organizing teams are

continually late in delivering their demos, resulting in low morale. The steering committee is

familiar with the reporting and planning associated with a predictive approach and is

concerned about the project because it is unclear if the expected value will be delivered.

What should the project manager do?

Options:

A.  

Emphasize to the teams the importance of reaching the agreed deadlines and value.

B.  

Request to coach the team to ensure motivated project team members are on board.

C.  

Update the project schedule with a buffer to reflect the expected delays being incurredby the team.

D.  

Suggest to the teams to limit the scope of work per iteration so they will start to delivermore reliably.

Discussion 0
Questions 50

A project manager agreed to a team member's request to have an alternative working schedule whereby they begin working at 12:00 p.m. each

day. This arrangement has worked well for the project, but has recently been scrutinized by members from other project teams because the

company's core working hours begin at 9:00 a.m.

What should the project manager have done to prevent this situation?

Options:

A.  

Broken down the situation to identify the root cause

B.  

Determined communication methods and channels

C.  

Analyzed the boundaries of the negotiations for agreement

D.  

Managed and rectified the ground rule violations

Discussion 0
Questions 51

A customer interacts directly with a Scrum team and continually requests changes in

priorities. This causes confusion among the team members and they complain to the project

manager.

What should the project manager do?

Options:

A.  

Advise the customer to discuss changes with the product owner.

B.  

Document this issue in the sprint backlog for discussion at a team meeting.

C.  

Ask the customer to submit a change request to the project sponsor.

D.  

Encourage the team to clarify the requests with the customer.

Discussion 0
Questions 52

A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.

Which two actions should the project manager take? (Choose two)

Options:

A.  

Interview the most resistant team members to persuade them to try to accept an agile approach.

B.  

Conduct training sessions with the team so that the team can understand what the agile approach and mindset are.

C.  

Ask the team to identify the product backlog and create a kanban board for the team to manage and follow the approach.

D.  

Meet with management to explain the team's resistance to the agile approach and request that they formally ask the team to implement agile.

E.  

Brainstorm with the team to understand the specifics of the team's project and to identity possible alternative approaches for the team.

Discussion 0
Questions 53

A project manager is leading a major water pipeline project and realizes midway into

the project that the project completion date is not achievable. Local farmers who rely on the

water for irrigation may be affected due to the delay. The project manager is afraid of their

displeasure and reaction, which will affect the project.

How should the project manager plan the communication to the stakeholders?

Options:

A.  

Document and accept this risk and communicate this decision to the project sponsor.

B.  

Collect feedback from the farmers and keep the information within the project team.

C.  

Deliver the information to the stakeholders with the project management office's (PMO)assistance.

D.  

Propose a solution to the stakeholders and communicate it to the local farmers.

Discussion 0
Questions 54

When a project manager is trying to determine a leadership style to use on a project what should they consider?

Options:

A.  

Number of tasks on the protect

B.  

Culture of the organization

C.  

Project timeline

D.  

Experience of the project manager

Discussion 0
Questions 55

A project sponsor insists that the project scope for a new product launch should include two geographical locations. However, after the project scoping session was done, a project charter was completed and approved with one location only.

What should the project manager do?

Options:

A.  

Ask the sponsor to increase the budget and schedule of the project to accommodate the additional scope.

B.  

Encourage the sponsor to start another project for the additional location so that the current project is not impacted.

C.  

Assess the impact to the scope and submit a change request for approval of the two locations before including them in the scope of the project.

D.  

Discuss with the sponsor that the project scope is approved and it is not possible to include two locations as it will affect the budget.

Discussion 0
Questions 56

Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

Options:

A.  

Develop requirements and designs to support a faster product release.

B.  

Emphasize the adoption of a predictive approach to minimize ambiguity.

C.  

Recommend an agile approach so the project can be delivered iteratively.

D.  

Outsource development of the product to a third party with more experience.

Discussion 0
Questions 57

A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.

What should the project manager do?

Options:

A.  

Ask the Scrum team members to share retrospectives.

B.  

Ask the scrum master to attend the workshops.

C.  

Invite the Scrum team members as optional participants.

D.  

Invite the Scrum team members as mandatory participants.

Discussion 0
Questions 58

A project manager receives a serious complaint from a functional manager about a

team member. What should the project manager do?

Options:

A.  

Replace the team member immediately to maintain a good relationship with thefunctional manager.

B.  

Discuss the issue with the functional manager to understand the reason for thecomplaint.

C.  

Support the team member and provide documentation to the functional managerproving their performance.

D.  

Protect the team member and ask the project sponsor to minimize any externalinterruptions.

Discussion 0
Questions 59

A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels the new methodology will impact the timely delivery of the project.

What should the project manager do?

Options:

A.  

Ask to execute the project with a predictive approach since there is a budget and schedule risk

B.  

agile tools and techniques used m the defined hybrid methodology for consistent application by all team members

C.  

Use the predictive approach tor team members who are not knowledgeable m agile project delivery practices

D.  

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update

Discussion 0
Questions 60

During the project planning phase, a project manager called a meeting to discuss the

product backlog with multiple stakeholders who represent the end users in various capacities.

Only one executive manager attended the meeting.

What should the project manager do?

Options:

A.  

Meet with each stakeholder individually to gather input to the product backlog andbegin project planning.

B.  

Proceed with prioritization of the product backlog based on previous lessons learnedand complete the project planning phase.

C.  

Reschedule the meeting to ensure the majority of stakeholders are present for theproduct backlog discussions.

D.  

Proceed with the meeting in order to keep the project on track and start prioritizing the product backlog.

Discussion 0
Questions 61

A project leader is assigned to a new project and is asked to assemble an effective

five-member agile team. If the project leader has no restrictions, which team should they

choose?

Options:

A.  

A team whose members work independently and are the best subject matter experts(SMES)

B.  

A team whose members have more general aptitudes but like to work individually

C.  

A team whose members have different skill sets and are spread out geographically

D.  

A team whose members have more general aptitudes and can collaborate on different tasks

Discussion 0
Questions 62

A project manager is establishing a project management office (PMO) for a

company-wide program to implement a software based on artificial intelligence (AI). As part of the PMO tasks, some stakeholders need help understanding how to deal with difficult situations.

Which activity should the project manager use to help train the stakeholders?

Options:

A.  

Contract negotiation

B.  

Team assessment

C.  

Mentoring and coaching

D.  

On-the-job training

Discussion 0
Questions 63

A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late. Digress into solutioning. or skip the meetings altogether.

How should the project manager improve this situation with the project team?

Options:

A.  

Engage the project team In implementing and Improving key aspects of the standup meetings.

B.  

Ask the product owner to remove team members who do not comply with standup meeting rules.

C.  

Send a daily retrospective report to all team members instead of holding standup meetings.

D.  

Include a daily brainstorming session In the standup meetings to resolve pending Issues.

Discussion 0
Questions 64

A project manager is assigned to a project related to taxes, which will be managed

using an agile approach. By reviewing lessons learned from a previous project, the project

manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

Options:

A.  

Recognize the stakeholder's skills are important for the project and evaluate thepossibility of the stakeholder supporting the project team.

B.  

Request the functional manager to assign the team from the lessons learned project tothe current project to avoid a learning curve.

C.  

Ask the project team to review the lessons learned and have the team contact thestakeholder directly if there are any questions.

D.  

Send a request to the project sponsor to hire the stakeholder and have them becomepart of the project team.

Discussion 0
Questions 65

A project stakeholder has expressed concern that the established success criteria for

the project are not being met. What should the project manager do next?

Options:

A.  

Review the established project benefits tracking metrics.

B.  

Update the project business case document.

C.  

Document the agreed-upon ownership of benefits realization.

D.  

Create a project benefits management plan.

Discussion 0
Questions 66

A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software.

What should the project manager do?

Options:

A.  

Include the new requirement in the next iteration of the software without informing the sponsor.

B.  

Inform the team that the sponsor decided to reject any changes and release the software as is.

C.  

Release the software as is and start a new project to deliver the new requirements.

D.  

Collect the requirements of the regulation and follow the change control process.

Discussion 0
Questions 67

During the setup of an agile project, the product owner expressed clear interest in

having features released during product development over having the product completed in

one year. What should the project manager do?

Options:

A.  

Promote a productive environment where everybody can work without interruptionsfrom the rest of the team members.

B.  

Create a reward system recognizing group contributions to get people motivated andimprove performance.

C.  

Facilitate sprint planning sessions with a focus on defining the minimum viable product(MVP).

D.  

Design a set of metrics including velocity, which is a good measure of value delivered.

Discussion 0
Questions 68

A new manufacturing line project is planned to be delivered in iterations tor the equipment installation phase. During one of the iterations the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates.

What should the project manager do next?

Options:

A.  

Replan the remaining iterations according to the new installation dates

B.  

Update the product backlog m order to address the delays

C.  

Review the procurement agreements to address the situation

D.  

Find another vendor who can fulfill the delivery dates

Discussion 0
Questions 69

During the execution of a construction project, the project sponsor asks to make

changes to the floor plan by adding a minimal storage room. The sponsor insists on making

this last-minute change, but they would like to avoid delays to the project.

Which document should the project manager refer to first?

Options:

A.  

Change management plan

B.  

Schedule management plan

C.  

Scope management plan

D.  

Cost management plan

Discussion 0
Questions 70

A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event What should the project manager do first?

Options:

A.  

Follow the risk response plan

B.  

Use the contingency fund

C.  

Prepare a change request

D.  

Update the risk register

Discussion 0
Questions 71

A project to implement a new process is still in development. When implemented,

the company will benefit by a reduction in utility costs. The project financial evaluation

indicates a payback of 3 years.

What should the project manager do to expedite the project delivery?

Options:

A.  

Increase resources on the technical design to enable a decision to proceed as this is aquick return project.

B.  

Increase the time spent on project development to improve the level of confidence tovalidate the financial evaluation.

C.  

Conduct a stakeholder survey with the plant operators to establish the probability ofthis project reducing the cost of utilities.

D.  

Stop any further project development and commence with the implementation as thereis no need to seek further approval.

Discussion 0
Questions 72

A project is on its fifth iteration out of six. One member of the team has left the company unexpectedly.

What should the project manager do next?

Options:

A.  

Detail the reason for the project delay in the status report.

B.  

Invite the stakeholders to discuss a mitigation plan.

C.  

Take on some of the necessary work to minimize the impact.

D.  

Register an issue and escalate it to the project sponsor.

Discussion 0
Questions 73

The project sponsor reports that a key stakeholder is complaining about performance differences in the metrics reported by the project manager,

which gives the impression that the project is out of control. The project manager has been providing the project's status according to the agreedupon communications management plan. This key stakeholder, however, seldom attends the status report meetings.

What should the project manager do first to address this situation?

Options:

A.  

Evaluate the communication needs to discover the gaps and adjust the original plan if needed.

B.  

Use the contingency reserves to implement fast tracking and improve the schedule key performance indicators (KPIs).

C.  

Review the resource breakdown structure (RBS) to request the main stakeholder's manager to replace the stakeholder.

D.  

Provide evidence to the project sponsor that the project is on track and the communications have been sent.

Discussion 0
Questions 74

A key project team member is out on sick leave in the middle of a critical project iteration. The project sponsor learns that any delay with the end-of-iteration release will displease the business stakeholders. Although all team members are cross-functional, they are also working close to full capacity.

What should the project manager do to address this situation?

Options:

A.  

Discuss the issues with the sponsor to fully convey the problem of the unavailable resource and the amount of work being done. shared.

B.  

Discuss this with the sponsor and hold a meeting with the stakeholders so all of the team challenges can be shared.

C.  

Discuss this with the team so they can complete the work of the unavailable team member and aim for the release deadline.

D.  

Discuss this with the team so they are able to reprioritize critical tasks and aim for the release deadline.

Discussion 0
Questions 75

A project team has two members with conflicting personalities. This is affecting the rest of the team's performance.

What should the project manager do?

Options:

A.  

Understand the viewpoint of each team member.

B.  

Organize a team-building activity for the team.

C.  

Conduct an analysis to measure missed targets.

D.  

Seek a solution during the daily coordination meeting.

Discussion 0
Questions 76

A project manager is beginning a new project with very diverse team members. The project manager chose to use consensus building so the team can agree on and be

engaged in how the project will be executed.

How should the project manager proceed?

Options:

A.  

Create an environment where the agreement is reached by a majority vote.

B.  

Create an environment where the agreement is reached through discussion.

C.  

Establish recurring brainstorming sessions to discuss project issues.

D.  

Allow team members to contribute ideas in a stream-of-consciousness mode.

Discussion 0
Questions 77

A project manager is leading a project that has a dependency on the client's vendor management system for critical requirements. The vendor

management team will not derive any benefits from the project. However, the project requires support from the vendor management head.

What should the project manager do next?

Options:

A.  

Get support from the sponsor to hire a subject matter expert (SME) from the vendor management team to work on the project.

B.  

Review the terms of reference of the steering committee to include the vendor management head.

C.  

Work with the sponsor on a communications management plan to obtain support from the vendor management head.

D.  

Obtain help from the sponsor to highlight any nonfinancial benefits for the vendor management team.

Discussion 0
Questions 78

Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?

Options:

A.  

Update the stakeholder register.

B.  

Refer to the resource management plan.

C.  

Consult the project sponsor.

D.  

Modify the statement of work (SOV).

Discussion 0
Questions 79

A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of

completion of the allocated tasks. After a conversation with the sponsor, the project manager realizes that they need to reassign a couple of tasks to meet the next

milestone. This change can be perceived as poor performance by the current assignees.

What should the project manager do?

Options:

A.  

Organize a team meeting and inform the team members that, as the person accountable for delivery, they decided to change the task allocation.

B.  

Ask the less experienced team member privately to stop working on the task and inform another team member that the work has been reassigned.

C.  

Ask the more experienced team member privately to take the task and inform the other team members that work has been reassigned.

D.  

Organize a team meeting to inform team members about a change in direction and work with them to change the task allocation.

Discussion 0
Questions 80

In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming milestone.

What should the project manager do?

Options:

A.  

Consult the risk response plan.

B.  

Assign the tasks to another team member.

C.  

Update the resource calendar.

D.  

Issue a request to the change control board (CCB).

Discussion 0
Questions 81

In a product development project, the project manager is constantly receiving complaints from stakeholders about functionalities being delivered, but not required by the business departments. The project sponsor wants to know if the project resources are being used effectively.

What should the project manager have done to avoid delivering work that is not adding value to the business?

Options:

A.  

Document the stakeholders' needs, review them during the retrospective, and create improvement plans.

B.  

Encourage the product owner to meet with the stakeholders and create a product backlog based on their needs.

C.  

Ask the stakeholders to document their complaints in change requests.

D.  

Define a product scope and ask the stakeholders to not deviate from it.

Discussion 0
Questions 82

A project manager has been assigned to a project that is in progress. The project

manager is looking for information regarding why the project is being completed.

What should the project manager do first?

Options:

A.  

Evaluate the project exit criteria in the project charter.

B.  

Reach out to the senior executive sponsor for the project.

C.  

Understand the project success criteria and objectives.

D.  

Review the project status reporting for the latest information.

Discussion 0
Questions 83

A project manager discovers that the project team is spending a large amount of time delivering several reporting formats for the same project updates to multiple stakeholders. What should the project manager do to reduce the time spent on these activities?

Options:

A.  

Segment the types of communications to be delivered to different stakeholders.

B.  

Update the communications management plan to remove less influential stakeholders.

C.  

Hold biweekly status meetings to deliver information to all stakeholders at once.

D.  

Delegate all of the stakeholder communications activities to a project team member.

Discussion 0
Questions 84

A subcontractor informs the project manager that they are unable to supply a key

component to the project. What should the project manager do?

Options:

A.  

Discuss the issue with the project sponsor and request extra time and budget to obtainthe component from a different supplier.

B.  

Raise a new risk in the risk register, perform a risk assessment, and convene SMEs and relevant stakeholders to plan a risk response

C.  

Submit a change request to the change control board (CCB) for changes to theperformance measurement baseline to obtain the component from a different supplier.

D.  

Raise a new issue in the issue log and convene subject matter experts (SMEs) andrelevant stakeholders to identify alternatives to address the problem.

Discussion 0
Questions 85

During a project's execution phase, two team members are having conflicts with other team members within the team on technical and interpersonal levels. Which two actions should the project manager take first to address this conflict? (Choose two)

Options:

A.  

Ask human resources (HR) to intervene before it escalates and affects the team's performance.

B.  

Arrange individual meetings with the team members who cannot work together effectively.

C.  

Address the conflict during team meetings for the entire team to participate and find solutions.

D.  

Discuss the conflict early among the affected team members using a direct, collaborative approach.

E.  

Plan to resolve the team members' conflicts after the sprint and focus on achieving the goal.

Discussion 0
Questions 86

A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule

What should the project manager do?

Options:

A.  

Advise the project management office (PMO) that there is a resource gap for sharing project artifacts effectively

B.  

Escalate the issue to the steering committee and ask them to deal with the stakeholders' lack of training

C.  

Make sure all stakeholders have access to the system and know where to find project artifacts

D.  

Send the project schedule via email to the stakeholders who need that information

Discussion 0
Questions 87

A project manager is leading a product feature rollout that will gain more subscribers for a video-streaming application. During the backlog grooming phase, the business stakeholders were unable to understand the feature integration with the product and raised concerns.

What can the project manager do to demonstrate the feature integration?

Options:

A.  

Involve business stakeholders in the iteration retrospective.

B.  

Include the business stakeholders in the iteration review.

C.  

Review the backlog in detail with the business stakeholders.

D.  

Create a task for the iteration review and add it to the backlog.

Discussion 0
Questions 88

A project manager is working with an agile team to enhance a product. Due to a

tight deadline, the team is trying to crash the schedule by engaging multiple resources to work

on the project simultaneously. However, the technical environment is configured to allow only

one resource to work on a feature at a time. The team plans to upgrade the technical

environment but is unable to agree on a way forward.

What should the project manager do first?

Options:

A.  

Conduct a consensus-building session to decide how to approach the next set of work.

B.  

Escalate the issue to the product owner for resolution.

C.  

Add this conflict to the agenda for discussion at the next daily standup meeting.

D.  

Conduct a planning session to decide how to approach the next set of work.

Discussion 0
Questions 89

During a final investment decision meeting, all of the stakeholders were aligned on the project benefits, proposed budget, and schedule. Before final approval was given, the executive requested an aspirational target for the project team to obtain an enhanced benefit from the project.

What should the project manager do in this situation?

Options:

A.  

Accept the request and commit to some benefit improvement opportunities for the project.

B.  

Investigate the request and express willingness to find ways to obtain higher project benefits.

C.  

Review the proposal and suggest optional benefit improvement opportunities for the project.

D.  

Explain the planning and budgeting process and demonstrate that the project proposal maximizes benefits.

Discussion 0
Questions 90

A project manager is performing the scrum master role for a project team of developers. At the daily standup, a couple of developers complain about the noise from a neighboring team, the performance of their laptops, and the difficulty in booking meeting rooms.

What should the project manager do?

Options:

A.  

Acknowledge the impediments and facilitate their resolutions.

B.  

Note the impediments and escalate them to the product owner.

C.  

Note the impediments and work on addressing them later.

D.  

Assign actions to all stakeholders and oversee their implementation.

Discussion 0
Questions 91

A project involves exporting 150 packages to the customer. However, only 30 packages have been cleared by the customer for shipment. The logistics manager provided

details to the customer 2 weeks ago and set up a weekly conference call to effectively

communicate with them, but the customer has not been participating in the calls.

How should the project manager handle this situation?

Options:

A.  

Request a change in the contract to include the shipment in the project managementplan.

B.  

Find the root cause of the issue and discuss the customer's current engagement.

C.  

Inform the customer that subsequent packages cannot be manufactured.

D.  

Request a delivery date extension from the customer

Discussion 0
Questions 92

A project manager is leading a hybrid project and is collaborating with the client to develop the project contract.

Some delays have been experienced due to unforeseen technical difficulties and new dependencies. However, the project manager is optimistic about recovering the delays in the upcoming sprints. A key stakeholder asked the project manager if the contract deadlines can be met.

What should the project manager do first?

Options:

A.  

Study the contract terms and deadlines to ensure they are not under risk and confirm them with the stakeholder.

B.  

Clarify the current work progress, causes for delays, existing risks, and planned corrective actions.

C.  

Submit a request for extra time and budget related to the dependencies and technical difficulties.

D.  

Ask the stakeholder to remain calm and confirm that they are participating in all team meetings.

Discussion 0
Questions 93

An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.

What tools should the agile project manager use to do these estimates?

Options:

A.  

Product backlog, budget, resource management plan

B.  

Budget, minimum viable product (MVP), retrospective notes

C.  

Resource management plan, retrospective notes, backlog grooming

D.  

Backlog grooming, product backlog, minimum viable product (MVP)

Discussion 0
Questions 94

A project sponsor has requested a trend analysis of all risks that the project has

monitored over the past 12 months. What should the agile project manager do?

Options:

A.  

Share the annual report with the sponsor.

B.  

Organize a stakeholder meeting to brainstorm on general project risks.

C.  

Extract this from the project risk register tracking tool and issues log.

D.  

Refer the sponsor to the contract document.

Discussion 0
Questions 95

When trying to track project benefits, a project manager realizes that some key performance indicators (KPIs) are not yet defined. What should the project manager do?

Options:

A.  

Work with the business analysts to track and collect the missing data and build the KPIs.

B.  

Coordinate with the benefit owner to track and collect the missing data and build the KPIs.

C.  

Forward the issue to the benefit owner and ask them to collect the missing data and build the KPIs.

D.  

Ask the program manager to track and collect the missing data and work to build the KPIs.

Discussion 0
Questions 96

A project's customer is furious. When the customer arrived at the project site, they discovered that one of their requirements was not met.

What should the project manager do?

Options:

A.  

Refer to the requirements traceability matrix and analyze the requirement.

B.  

Analyze the benefits management plan and implement the needed change.

C.  

Consult the scope management plan with the customer to understand the gap.

D.  

Discuss and agree with the customer to implement the missing requirement.

Discussion 0
Questions 97

A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project

How should the project manager report this cost?

Options:

A.  

Estimate user story points and forecast a budget for that deliverable

B.  

Determine the control accounts and use a top bottom estimate

C.  

Consider the cost performance index (CPl) based on earned value (EV) divided by costs

D.  

Calculate the budget at completion (BAC) based on the completed and planned features

Discussion 0
Questions 98

A company is transitioning projects from a predictive to an agile approach. The CFO is concerned that one of the agile projects has an important feature for the financial

department that is being delayed for a later iteration.

What should the project manager do to clarify the situation?

Options:

A.  

Create an executive board to review the product backlog and replan the next iterations.

B.  

Clarify with the CFO that the prioritization process is based on business value.

C.  

Request support from the CEO on how to deal with the situation.

D.  

Increase the size of the team in order to match any prior expectations of the CFO.

Discussion 0
Questions 99

A project team has been formed and the tasks have been assigned to each team member All team members have agreed to follow a hybrid protect approach. What should the project manager do to ensure the team performs as an organized unit?

Options:

A.  

Advise the team to adjust their work habits and behaviors to allow for better conflict resolution

B.  

Call a team meeting to discuss team members' strengths and weaknesses

C.  

Establish rules and regulations for team members with consequences if the goals are not reached

D.  

Establish team behavior and develop an understating of how to work together

Discussion 0
Questions 100

A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The

resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product.

What should the project manager do?

Options:

A.  

Use the remaining time and resources to add additional scope to the project without spending the project budget.

B.  

Ensure product quality by spending the remaining resources and time on additional quality checks for the product.

C.  

Acknowledge the project closure criteria has been met and release the remaining budget and resources.

D.  

Obtain approval from the sponsor to add additional functionality to the project deliverables with the leftover budget.

Discussion 0
Questions 101

A project manager is working with a team that is new to agile. One of the more

influential stakeholders struggles with the nature of agile. The project manager knows that this

stakeholder is needed as an advocate and wants to do everything possible to make the

stakeholder comfortable with the project.

What should the project manager include in the status report to illustrate the project's

performance?

Options:

A.  

Results of the MoSCoW assessment

B.  

Cost-benefit analysis

C.  

Return on investment (ROI) analysis

D.  

Earned value analysis (EVA)

Discussion 0
Questions 102

The team responsible for executing a work package asks the consultant to reconsider the initial project deliverables specified in the contract.

What should the project manager do in this situation?

Options:

A.  

Carry out corresponding negotiations in the adjustments of outcomes.

B.  

Agree with the consultant to continue without any adjustments.

C.  

Pause the project until a satisfactory agreement between both parties is reached.

D.  

Explain to the consultant that without adjustments, payment terms will be affected.

Discussion 0
Questions 103

A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.

What should the project manager do to address this issue?

Options:

A.  

Negotiate the payments with the supplier and remind them of their long-term association

B.  

Penalize the supplier according to the contract's service level agreement (SLA)

C.  

Hire another information security supplier and incentivize them for speedy delivery

D.  

inform the relevant stakeholders of this challenge and seek their support

Discussion 0
Questions 104

A protect manager has just finished planning for a project when the client adds a new project team member The project manager Knows that the new team member only works remotely and is not in the main office. In addition, the new team member engages with decisions quickly in a face-to-face environment, but is slow to respond otherwise.

How should the project manager reflect this in their planning?

Options:

A.  

Send out recurring onsite project meeting invites to ensure the team member's presence.

B.  

Update the project charter to include the new team member for this project.

C.  

Monitor the new team member's input to gauge their value to the project.

D.  

Include the team member in the stakeholder register and update the communications management plan.

Discussion 0
Questions 105

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?

Options:

A.  

Update the project management plan in order to get back on track.

B.  

Ensure the team receives continuous feedback from customers users.

C.  

Submit a change request to adjust the project scope.

D.  

Ensure the team understands all additional project requirements.

Discussion 0
Questions 106

A project manager is assigned to deliver an innovative solution that is part of a

brand new offering. The project manager reviews the request for proposal (RFP) and realizes that key terms are restricted to technical resource assignments. There is also a gap in addressing compliance.

How should the project manager bridge the gap and ensure the project delivers the expected

business value?

Options:

A.  

Determine the critical requirements.

B.  

Document the risks and mitigations.

C.  

Define the project schedule.

D.  

Create a project scope statement.

Discussion 0
Questions 107

A newly appointed product owner is working with a project team that is using agile

for the first time. The product owner is constantly disrupting various team members throughout

the day to discuss progress. This has resulted in the team feeling micromanaged and

frustrated because of the constant disruptions.

How should the project manager proceed?

Options:

A.  

Invite the product owner to attend daily standup meetings so they can assessprogress.

B.  

Set up a feedback session with the product owner once a week so they can assessprogress.

C.  

Instruct the team to refer the product owner to the project manager for information.

D.  

Invite the product owner's functional manager to a feedback session to escalate theissue.

Discussion 0
Questions 108

An agile project manager is evaluating the method that will be used to display the

value of the work performed to date. Which method will they select to display to the project stakeholder?

Options:

Discussion 0
Questions 109

A project manager is managing the opening of a new office overseas. At the beginning of the project, possible delays due to legal permits are raised by one stakeholder. Subject matter experts (SMEs)

reassessed the concern and suggested assigning more time for this permit, and the change control board (CCB) agrees.

Which document should the project manager update first to document this change?

Options:

A.  

Scope baseline

B.  

Cost baseline

C.  

Risk register

D.  

Schedule baseline

Discussion 0
Questions 110

During a project, the project manager finds an opportunity to reduce the project cost by completing a deliverable ahead of schedule with a minimal

impact on project resources. However, the client has only been focused on the next milestone.

How should the project manager approach this situation?

Options:

A.  

Apply additional resources to realize the early deliverable and ensure the next milestone is achieved.

B.  

Focus on the deliverable of the next project milestone as per the client's strict instructions.

C.  

Review the change management plan to discuss early benefits realization with the client.

D.  

Evaluate whether the client's request will add extra features to the project deliverable.

Discussion 0
Questions 111

While finalizing project management plans, a customer provides the project manager with a new set of quality standards to which the final product must adhere. What

should the project manager do to ensure a smooth delivery of the product?

Options:

A.  

Involve the client in risk identification.

B.  

Agree with the client on acceptance criteria.

C.  

Involve the client in a performance gap analysis.

D.  

Agree with the client on a new project charter.

Discussion 0
Questions 112

At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.

How should the project manager reply?

Options:

A.  

Recurrent team meetings are planned to control the budget against future uncertainties.

B.  

Probabilistic analysis was used to develop the budget to address future uncertainties.

C.  

The budget was developed by using the lessons learned from previous project data.

D.  

Feedback from stakeholders will be addressed at each board meeting to adapt the budget.

Discussion 0
Questions 113

During daily team standup meetings, team members constantly ask about which tasks they should focus on first. How should the project

manager ensure the team is fully productive?

Options:

A.  

Review the project backlog during the team's standup meeting.

B.  

Encourage project team members to prioritize the product backlog.

C.  

Ensure team members are working according to the project plan.

D.  

Work with the product owner to ensure the project backlog is prioritized.

Discussion 0
Questions 114

A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned

to work on the details and estimates as requested by the client.

What should the project manager do before sending the information to the client?

Options:

A.  

Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.

B.  

Sequence the tasks with estimates and add standard risk reserves to use for software development.

C.  

Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.

D.  

Work with the team to understand their views and add the appropriate dependencies and risks.

Discussion 0
Questions 115

During a project meeting, the project manager expressed the importance of delivering reports on time. These individual reports will be

consolidated into a single report. One of the team member's reports was not delivered on time and therefore the report could not be integrated

with the other reports. This demonstrates a lack of teamwork and impacts project success.

What should the project manager do to resolve this issue?

Options:

A.  

Assign the task to someone else on the team.

B.  

Discuss it with the team member in confidence.

C.  

Discuss this matter during the project meeting.

D.  

Include this item in the risk register.

Discussion 0
Questions 116

A project manager is part of a balanced matrix project organization. The project manager will receive all work performance updates directly from the new sourcing

department head who has no time to spare to give the project manager the information.

What should the project manager do?

Options:

A.  

Request information directly from the sourcing department team members.

B.  

Present the situation to the manager of the sourcing department head.

C.  

Discuss the situation with the company project sponsor for advice.

D.  

Work out a resolution in consultation with the sourcing department head.

Discussion 0
Questions 117

At a project meeting, a business analyst requires input from a marketing consultant to continue working on a task. The business analyst has tried

to contact the consultant but has been told that the consultant does not have the time to discuss the project.

What should the project manager do to move the project forward?

Options:

A.  

Escalate the issues about the consultant to the functional manager so the consultant dedicates the necessary time to the project.

B.  

Include a new project risk into the risk register and allocate the consultant as the risk owner as it is their responsibility to provide input.

C.  

Discuss the request with the consultant and set up time with the business analyst and consultant to discuss the project requirements.

D.  

Urge the business analyst to continue contacting the consultant to discuss the project since this is the responsibility of the business analyst.

Discussion 0
Questions 118

A multicultural team is working on a project. After a few months of observation, the project manager realizes that two team members are not responding to the construction manager properly. The project manager spoke to the team members individually and found that both had cultural differences with the construction manager.

What should the project manager do to improve the situation?

Options:

A.  

Ask the team members to tolerate the cultural differences as they have a different cultural background.

B.  

Ask the construction manager to meet with the two team members to resolve the situation.

C.  

Provide the construction manager with instructions on how to resolve the situation.

D.  

Discuss the team members' concern with the construction manager and seek solutions.

Discussion 0
Questions 119

While developing a new product, a key stakeholder expresses concern about

insufficient information on product feature requirements. The product team disagrees and

mentions that detailed requirements have been provided.

What should the project manager do to handle this situation?

Options:

A.  

Organize a discussion with the product team to clarify the missing information.

B.  

Redirect the stakeholder to discuss this request with the functional manager.

C.  

Record the new requirements and ask the product team to develop them.

D.  

Conduct new risk and scope analyses, identifying the missing information.

Discussion 0
Questions 120

An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.

What should the project manager do?

Options:

A.  

Provide feedback to the team and conduct a meeting to review the team rules.

B.  

Provide feedback to the team and conduct a retrospective meeting to find a root cause.

C.  

Provide feedback to the team and request agile training for the new member.

D.  

Provide feedback to the team and coach the new team member in agile methodology.

Discussion 0
Questions 121

A company is initiating a project to decommission inefficient sales channels. Several stakeholders argue that one channel that indicates a downturn in generating value is still more efficient than some of the channels that are planned to remain.

What should the project manager do?

Options:

A.  

Plan for incremental and iterative delivery based on feedback from the marketing and sales team.

B.  

Review and update the success criteria to ensure that the channel is not decommissioned.

C.  

Inform the stakeholders that the list of channels to be decommissioned was approved by the CEO.

D.  

Escalate the objection to the steering committee and human resources (HR) as a personal intimidation incident.

Discussion 0
Questions 122

A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets with the stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive.

What should the project manager have done to avoid this situation?

Options:

A.  

Initiated requirements planning to analyze, document, and manage requirements

B.  

Applied requirements elicitation to involve engaging stakeholders consistently in the requirements process

C.  

Implemented the change request process to harness change to the stakeholders’ advantage

D.  

Used progressive elaboration to enhance the scope management plan with additional details

Discussion 0
Questions 123

A project manager receives a call from the customer's account manager requesting support for a critical operational issue. Although the issue is unrelated to the project, the customer believes that one of the project team members has the technical expertise to recommend a solution.

What should the project manager do first?

Options:

A.  

Organize a conference call with the internal expert and the client to estimate the amount of effort required to fix it.

B.  

Decline the request politely since the issue, although critical, is not the responsibility of the project team.

C.  

Allocate a task to the team member as a high priority and inform the customer that the issue will be resolved the next day.

D.  

Inform the customer that they should contact the sales manager and submit a formal request for a quote.

Discussion 0
Questions 124

A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?

Options:

A.  

Check if the budget can cover the enhancement

B.  

Accept the request because it came from the project sponsor

C.  

Refuse the project sponsor's request because it is out of scope

D.  

Validate the proposed change's impact on the project.

Discussion 0
Questions 125

An agile project is starting and the assigned team is new to agile During the first daily meetings, the project manager observes that the team is having problems meeting goals What should the project manager do?

Options:

A.  

Plan an outdoor activity tor the team to get to know each other

B.  

Ask the team to review agile protect management approaches.

C.  

Ask the human resources department for an experienced agile team

D.  

Conduct a meeting to help the team define the team charter

Discussion 0
Questions 126

At the end of the last iteration, the customer rejects the deliverables since they did

not meet the customer's expectations. What should the project manager have been done

to prevent this situation?

Options:

A.  

Involved the customer more in the planning process for the project, and ensuredagreement on the proceedings.

B.  

Included all relevant criteria in the agreed upon definition of done (DoD), and crafted a shared product vision.

C.  

Provided the customer with the backlog and the specified user stories at the beginning of the iteration.

D.  

Developed the DoD in close cooperation with all stakeholders to ensure their expectations were included.

Discussion 0
Questions 127

After a project team has been working on a project for several months the project is cancelled. The project sponsor is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project

How should the project manager handle this situation?

Options:

A.  

Comply with the project sponsor's request to not archive the project artifacts.

B.  

Consult with the project management office (PMO) for guidance on project artifacts.

C.  

Archive the project artifacts on the project manager's local computer for future reference.

D.  

Document the project sponsor's instructions as the archived project artifacts.

Discussion 0
Questions 128

A team is assembled for a new project that will be using a predictive approach through requirements gathering and an agile approach for development and testing Not everyone on the team has experience working in agile. The schedule has started slipping due to the unclear structure of the agile development approach.

What should the project manager have done to avoid this situation?

Options:

A.  

Established daily standup meetings to track and report on team progress and escalated delays to stakeholders as they occurred

B.  

Set up weekly status meetings to review team progress, prepared weekly status reports to track progress and regularly escalated delays

C.  

Met with the team, allowed team members to make decisions about what to do and established performance goals

D.  

Conducted routine meetings and identified team members who are under performing

Discussion 0
Questions 129

During the execution phase, the project manager discovered that the deliverables

are not meeting the quality specifications requested by the main stakeholder. This has

caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost

performance index (CPI) from 1.5 to 1.1.

What action should the project manager take to mitigate the issue of the deliverables being

rejected during the next iteration?

Options:

A.  

Submit a change request to prioritize resolutions for the quality issue to minimize the impact on the rest of the deliverables.

B.  

Reinforce the definition of done (DoD) during sprint planning so that the team has a common understanding of expectations.

C.  

Assure that the product backlog is properly prioritized to avoid dependencies that cause rejection.

D.  

Create a dedicated sprint to complete all of the pending specifications from previous sprints.

Discussion 0
Questions 130

An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.

What should the project manager of the ongoing project do?

Options:

A.  

Submit new user stories to the product owner in order to put documentation in the product backlog.

B.  

Introduce a document management tool to support the agile teams in preparing the documentation.

C.  

Check with the agile teams to see if the project manager's understanding of the Agile Manifesto is correct.

D.  

Add an additional team member to take up the role of scribe for the required documentation.

Discussion 0
Questions 131

A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?

Options:

A.  

Accommodate the change request to serve the client's needs

B.  

Consult with team members and allow them to make a decision

C.  

Convince the client not to make changes to the project

D.  

Make transactional decisions focusing on the project goals

Discussion 0
Questions 132

A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.

What should the project manager do to address this situation?

Options:

A.  

Inform the steering committee of the situation and request additional resources.

B.  

Coordinate virtual and face-to-face meetings at each site to improve communication

C.  

Coordinate virtual meetings to assess the project team's communication needs

D.  

Inform the project sponsor of this situation and request cultural orientation training.

Discussion 0
Questions 133

A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects.

What else does the project manager need to do before determining the budget baseline?

Options:

A.  

Look at a previous project to ensure the budget totals match.

B.  

Require all stakeholders to review and approve the estimates.

C.  

Revise the project timeline and scope based on the WBS.

D.  

Add contingency into the budget for inflation and other changes.

Discussion 0
Questions 134

After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.

How should the project manager handle this situation?

Options:

A.  

Comply with the project sponsor's request to not archive the project artifacts.

B.  

Document the project sponsor's instructions as the archived project artifacts.

C.  

Archive the project artifacts on the project manager's local computer for future reference

D.  

Consult with the project management office (PMO) for guidance on project artifacts.

Discussion 0
Questions 135

A project manager is leading a council's project that aims to ensure full compliance with health, ecological, and environmental standards.

At the same time, the project's goal is to remain fully adherent to the council's values, policies, and procedures.

How should the project manager ensure project success?

Options:

A.  

Enforce the project manager's authority over the contracting partner delivering to the council. by

B.  

Engage a third-party consulting firm to oversee the project's implementation.

C.  

Develop the necessary implementation plan and ask the partners to adjust their plans to meet the project manager's objectives.

D.  

Meet with the stakeholders regularly to share project objectives and mutually agree on common goals and plans.

Discussion 0
Questions 136

A team has been consistently delivering outcomes. However, based on their current performance, it was discovered that their velocity has decreased by 30%.

What should the project manager do to ensure the velocity is under control?

Options:

A.  

Ask the product owner to look at a minimum of four to eight iterations and replan the velocity for the next iteration based on the team's current performance.

B.  

Ask the scrum master to plug gaps in the team's performance by adding a team member to compensate for the velocity decrease.

C.  

Request that the team improve their cycle time to compensate for the velocity decrease.

D.  

Request the team to improve the lead time, cycle time, and response time individually and track closure.

Discussion 0
Questions 137

A project manager receives feedback from the customer's leadership team regarding their annoyance about the frequency of email updates. What should the project manager have done first to prevent this?

Options:

A.  

Understood the customer's company culture

B.  

Updated the communications management plan

C.  

Analyzed customer interest and engagement

D.  

Scheduled weekly update meetings

Discussion 0
Questions 138

In the past, the project manager and the project team performed well using

predictive methodology. However, the organization recently decided to adopt agile

approaches, and the project sponsor wants to use an agile approach in an upcoming project.

Before initiating the project, what should the project manager do?

Options:

A.  

Prepare a risk report that captures the probability and impact of risks, and then shareit with the project sponsor.

B.  

Share the organization's decision with the team and make plans to adopt an agileapproach in the upcoming project.

C.  

Make a request to human resources for new team members who have agileexperience.

D.  

Ask the project sponsor to change the approach back to predictive as that is theteam’s strength.

Discussion 0
Questions 139

A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.

What should the project manager do to address the growing resistance?

Options:

A.  

Crash the project schedule and ask project team members to work overtime to meet the new timeline

B.  

Motivate project team members by offering incentives to complete the project on time

C.  

Describe to the team members how specific tools and techniques can be used to finish on time

D.  

Convince team members to use a specific methodology to complete the project on time

Discussion 0
Questions 140

In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate. How should the project manager address this issue?

Options:

A.  

Create a product backlog

B.  

Perform sprint reviews with the team

C.  

Assess the previous project velocity

D.  

Reduce the story size by splitting stories

Discussion 0
Questions 141

In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale.

What should the project manager do to handle this situation?

Options:

A.  

Give team members more authority to make decisions.

B.  

Perform team-building activities and enhance collaboration.

C.  

Identify the team members who are impacting low morale.

D.  

Coach the team members on agile processes and knowledge.

Discussion 0
Questions 142

A project learn member identified a defect in the initial solution design for a project The stakeholders are not sure whether to deploy the system or not. What should the project manager do?

Options:

A.  

Propose a solution redesign for the project

B.  

Perform risk analysis against the issue.

C.  

Revise the project's quality control measurements

D.  

Develop a mitigation based on the solution design

Discussion 0
Questions 143

A project team member complained to the project manager that they are not sure f on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past they worked on a document tor more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.

What should the project manager do to avoid this situation in the future?

Options:

A.  

Encourage better team communication by positioning team members closer together.

B.  

Implement a project management information system (PMIS)

C.  

Update the communications management plan to ensure correct delivery of the latest version

D.  

Restrict team members from sending the requirements documents via email

Discussion 0
Questions 144

A project manager brings in a new team member from an agile environment to work in a predictive environment The project manager expects to leverage the new team member's agile experience with the existing team members.

What should the project manager do to integrate the new team member effectively?

Options:

A.  

Train the new team member in the predictive project management approach.

B.  

Acknowledge that hiring this new employee is a risk to the existing team

C.  

Set expectations with the new team member and explain what is needed

D.  

Meet with all team members and explain the new employee's position.

Discussion 0
Questions 145

A year after implementing a policy change to improve diversity and inclusion within two teams, there is increasing conflict within the company What should have been done to prevent this conflict?

Options:

A.  

The organization should have introduced the concept of diversity broadly

B.  

The leadership team should have worked closely with the marketing team to get insight on diversity

C.  

Organization-wide diversity training should have been provided to the workforce

D.  

The critical departments in the organization should have been involved in this exercise

Discussion 0
Questions 146

During a sprint planning meeting, a stakeholder is told that their requirement is in progress and on track for the final product to be ready in the next two sprints. The stakeholder is very satisfied with the timeline and gives their full support to the agile team. After the meeting, the project sponsor calls the project manager about a large requirement they want the team to work on right away as it has significant

business value. What should the project manager do?

Options:

A.  

Call the stakeholder to tell them that the final product schedule must be extended due to this last minute, urgent request.

B.  

Perform an impact analysis and share the overall schedule impact before deciding on a new priority.

C.  

Reject the new requirement from the sponsor as this is going to impact the delivery of the stakeholder's final product.

D.  

Ask the product owner to prioritize the new request from the sponsor and ask the team to work on it immediately.

Discussion 0
Questions 147

A project manager is working to create a product that can be released to the market as soon as it passes rigorous quality standards.

Historically, the company has used a predictive methodology, but the company is exploring the implementation of agile methodologies.

The company asked the project manager to explain the value gained by using an agile process.

How should the project manager respond?

Options:

A.  

Early value cannot be achieved until the product is fully released.

B.  

Early value can be gained by testing the most important features in the initial stages to fix deviations.

C.  

Early value will be gained only if beta products can be released to the market.

D.  

Early value will be gained only if the speed can be increased to release the product to the market.

Discussion 0
Questions 148

An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this'?

Options:

A.  

Discuss the meeting delays with the director of operations and ask for support with the concerns.

B.  

Review the operations manager's concerns and ensure these concerns are addressed

C.  

Escalate the concerns to the project sponsor and discuss options to address them

D.  

Include the operations manager's concerns in the risk register and assign actions to mitigate the risks.

Discussion 0
Questions 149

The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.

What should the project manager do to resolve and prevent additional arguments?

Options:

A.  

Monitor the interactions between the vendor and infrastructure manager going forward.

B.  

Host a meeting with the vendor and infrastructure manager to help resolve their disagreement.

C.  

Escalate the issue to the sponsor so appropriate action can be taken.

D.  

Instruct the vendor to correct the problem without additional arguments.

Discussion 0
Questions 150

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

Options:

A.  

Continue with the sprint as the progress shows buffers for potential interruptions.

B.  

Ask the product owner if some low-priority stories could be cut from the sprint.

C.  

Continue with the sprint work as planned and keep monitoring.

D.  

Ask the project team to select any additional stories as they have additional capacity than planned.

Discussion 0
Questions 151

A project manager is working on a large project with a very difficult client. During

the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.

How should the project manager approach this?

Options:

A.  

Concentrate on the current project milestones.

B.  

Update the project management plan for this new work.

C.  

Develop a business case and submit it to the client.

D.  

Make all the changes and then show the client the results.

Discussion 0
Questions 152

In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.

What should the project manager do?

Options:

A.  

Consider cultural differences among stakeholders.

B.  

Conduct an integration meeting among all stakeholders.

C.  

Schedule communication training for management-level stakeholders.

D.  

Understand how political aspects can affect the project.

Discussion 0
Questions 153

Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not

delivered, the company could receive a fine from the government. What should the project manager do?

Options:

A.  

Discuss the issue with the project sponsor.

B.  

Review the resources required for the tasks on the critical path.

C.  

Review and update the risk management plan.

D.  

Allocate resources to develop the competencies of the other team members

Discussion 0
Questions 154

A new agile project manager is trying to determine how the team is performing against the schedule for a release. Which tool will provide a deeper look into the team's progress?

Options:

A.  

Release plan Sy

B.  

Product roadmap

C.  

Kanban board

D.  

Burndown chart

Discussion 0
Questions 155

Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.

How should the agile project leader resolve this situation?

Options:

A.  

Update the restriction log with the new team capacity.

B.  

Explain the new project requirements to the team.

C.  

Update the project budget with the released team members.

D.  

Explain the new team velocity to the customer.

Discussion 0
Questions 156

An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager

do with many tasks still open on the Kanban board?

Options:

A.  

Decompose the item immediately and begin work.

B.  

Discuss the impact of starting the item with the team.

C.  

Finish the small tasks in progress before decomposing the item.

D.  

Communicate the impact with the project sponsor.

Discussion 0
Questions 157

In a weak matrix environment, two key team members are falling behind with their tasks, which will affect the success of the project.

Further investigation by the project manager reveals that they have unresolved issues with each other. The project manager asks them to find a way to resolve the issues, but this is unsuccessful. The project manager then holds a meeting with them to work outa permanent solution to the issues, but this is also unsuccessful.

What should the project manager do next?

Options:

A.  

Escalate the issue to a higher authority.

B.  

Suspend the two key team members immediately.

C.  

Put the issue on the agenda for the next team meeting.

D.  

Reassign one of the key team members to a different task.

Discussion 0
Questions 158

A project manager is working with an agile team. A key stakeholder who does not

join the sprint planning session is very unhappy, as the delivery date for the final product has

been pushed back three times. What should the project manager do?

Options:

A.  

Meet with the stakeholder to understand the concern and business impact, reprioritize as necessary, and invite them to join the sprint planning session.

B.  

Direct the product owner to drop other work in progress and work on this stakeholder’s requirement as the top-priority item.

C.  

Share the prioritized items that the team is working on with the stakeholder and invite them to join the sprint planning session.

D.  

Secure some additional funding to recruit more resources to the project team to enable faster delivery.

Discussion 0
Questions 159

A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.

The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.

Match the stakeholders on the left with the appropriate frequency for updates.

Options:

Discussion 0
Questions 160

During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past

What should the project manager do next to improve this situation?

Options:

A.  

Call for a team meeting to identify the root cause for the declining performance

B.  

Estimate the baseline impacts and submit a change request.

C.  

Implement compression techniques to bring the project back on track.

D.  

Review the resource management plan and organizational assets

Discussion 0
Questions 161

A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.

What should the project manager do next?

Options:

A.  

Contact the human resource (HR) department for a solution.

B.  

Speak with the key team member to clarify the situation.

C.  

Conduct a meeting with the team to deliberate on a decision.

D.  

Suspend the team member until further notice.

Discussion 0
Questions 162

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.

What should the project manager do?

Options:

A.  

Adjust the original budget estimates with the current cost variance.

B.  

Negotiate the project changes and adjust stakeholder expectations.

C.  

Perform a root cause analysis of the project performance.

D.  

Review the activity duration to reforecast the project completion date.

Discussion 0
Questions 163

A project started 12 months ago and is currently on iteration 12 of 14. The team

has performed well and completed all deliverables on time. However, some team members

are starting to complain about the length of the project, creating a risk for lack of

performance at this critical stage.

What should the project manager do as a servant leader to mitigate this risk?

Options:

A.  

Meet with the team to reinforce their responsibilities and the consequences if theproject deliverables are not completed on time.

B.  

Apply additional controls to the project deliverables to ensure that all milestonesare achieved on time.

C.  

Contact the functional manager to ensure that team motivation remains high untilthe end of the project.

D.  

Schedule a team event with the project sponsor to highlight the importance of theproject and recognize the work of the team.

Discussion 0
Questions 164

A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule

Which two actions should the project manager take to manage Impediments and improve the team's velocity? (Choose two)

Options:

A.  

Look for processes that cause bottlenecks and slow down the team's agility

B.  

Assign the items with high complexity lo senior developers

C.  

Empower the learn to make decisions to remove impediments

D.  

Work with the team to remove impediments as quickly as possible

E.  

Move the items with high complexity to the last iterations

Discussion 0
Questions 165

A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?

Options:

A.  

Develop new procedures that are easy for the team to follow.

B.  

Escalate the issue to the CEO and the board members.

C.  

Instruct the team that the procedures should always be followed.

D.  

Initiate a review of the procedures with the CTO and the team.

Discussion 0
Questions 166

A contractor delivering construction services to a company is using agile principles

to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design

changes or performing rework.

What should the project manager do to minimize the cost?

Options:

A.  

Put the project on hold until all definitions are ready in order to avoid rework.

B.  

Review the backlog with the product owner and prioritize the tasks that are least likely to be affected by a change in legislation.

C.  

Capture the engineers' feedback at the daily meeting and communicate it to the product owner.

D.  

Cancel the project release resources, then start again when all the definitions are ready.

Discussion 0
Questions 167

For an ongoing project, match the key performance indicators (KPIs) on the left to the correct categories on the right.

Options:

Discussion 0
Questions 168

A company is planning a digitization project. Which action should the project

manager take first when defining the project scope?

Options:

A.  

Assess the current state process to define the scope of the digitization.

B.  

Digitize the current state process exactly as defined.

C.  

Redefine the current state process to scope the supporting software.

D.  

Develop the software that will support the current state process.

Discussion 0
Questions 169

A large company has agreed on a business case for an environmental project. The

project will cause some major changes in their operations, such as reduction in paper use,

which will obviously affect all of the users.

What is the first thing the appointed project manager should do?

Options:

A.  

Evaluate the impact to the users and create a plan to address it.

B.  

Inform users about the new changes and ask for their collaboration.

C.  

Ask all managers to collaborate implementing this change to users.

D.  

Start implementing the change so that users will eventually get used to it.

Discussion 0
Questions 170

A specialized team member has just received news that they must leave the office for several weeks They have approximately two workdays until they will leave and then they will become unavailable through any communication channels. There is a key deadline approaching

What should the agile project manager do?

Options:

A.  

Ask the team member to complete as much as they can now.

B.  

Ask the team member to work with their peers to knowledge share

C.  

Ask the team member to identify their specialist tasks

D.  

Ask the team member to host a special team meeting.

Discussion 0
Questions 171

A stakeholder is requesting that the project manager share project status updates

on a regular basis. This stakeholder is not included in the regular distribution list.

What should the project manager do?

Options:

A.  

Start sending status updates to this stakeholder based on the request.

B.  

Ask the stakeholder's manager if the stakeholder can be added to the list.

C.  

Review the stakeholder engagement and communications management plans.

D.  

Escalate the stakeholder’s request to the project sponsor.

Discussion 0
Questions 172

A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community.

How should the project manager handle this issue?

Options:

A.  

Disregard these stakeholders since the relevant documents have been secured to execute this project.

B.  

Update the stakeholder register and risk management plan.

C.  

Update the stakeholder register and revise the stakeholder engagement plan.

D.  

Explain to the community members why they were not included as stakeholders for the project.

Discussion 0
Questions 173

A project manager is managing a project which is approaching the end of the execution phase. A high-level stakeholder informs the project manager that a very important requirement was not included in the scope of the project, and that without that requirement the project will deliver no value.

What is the first thing the project manager should do"?

Options:

A.  

Include the requirement into the project and schedule it as soon as possible

B.  

Inform the project sponsor about the situation and request assistance

C.  

Evaluate the impact that the inclusion of this new requirement will have on project performance

D.  

Inform the stakeholder that it is impossible to add new requirements to an approved project scope

Discussion 0
Questions 174

A new project manager is assigned to a project in the execution stage. A few key stakeholders inform the new project manager that the project has some serious issues.

What should the newly assigned project manager do first to understand the issues?

Options:

A.  

Escalate the issues to the project sponsor.

B.  

Review the issues log to ensure the issues are captured.

C.  

Check the risk management plan to ensure there is a strategy to address the issues.

D.  

Ask the key stakeholders to discuss the issues with the project team.

Discussion 0
Questions 175

A company Is helping their client launch an Innovative product. During the sprint review, the product owner identifies that the product does not include key features that were previously prioritized as part of the product backlog.

What should the project manager do next?

Options:

A.  

Extend the sprint timeline so the learn can work on the missing feature.

B.  

Inform the product owner that this issue needs to be escalated to the executive level.

C.  

Collaborate with the product owner and the team to plan the following sprint

D.  

Initiate the change request process to include these missing features.

Discussion 0
Questions 176

A project manager for an agile project wants to have a highly engaged team. How should the project manager achieve this objective?

Options:

A.  

Be clear with directions and assignments so people stay focused and engaged with their work.

B.  

Promote an environment where everybody knows what their contribution means to the project as a whole.

C.  

Design a reward system to get people motivated by recognizing significant individual contributions from the last sprint

D.  

Encourage continuous rotation of roles among team members to keep people motivated throughout project delivery.

Discussion 0
Questions 177

An agile project team is building a new product. The stakeholders require ongoing

illustration of project business value.

How should the project manager proceed?

Options:

A.  

Prepare performance value reports for the business on an ongoing basis.

B.  

Include demonstrations of the built portion of the product at the end of every sprint.

C.  

Prepare a project report for the stakeholders and distribute it weekly.

D.  

Confirm the minimum viable product (MVP) and demonstrate it to the business when it is ready.

Discussion 0
Questions 178

An agile project has just started, and the backlog is being prioritized. The

customer wants to prioritize business value over identified risks.

How should the customer’s request be managed?

Options:

A.  

Accept risks as they decrease over a period of time.

B.  

Create a risk value profile to track the relative importance of risks.

C.  

Log and track risks separately as only business value is important.

D.  

Assess risks together with business value during prioritization.

Discussion 0
Questions 179

Match the project situation on the left to the meeting on the right where the situation could occur.

Options:

Discussion 0
Questions 180

A project manager is leading a new agile project. The requirements for the first sprint have been defined and the work is about to start.

What should the project manager do next?

Options:

A.  

Assign the tasks to the resources based on their expertise.

B.  

Ensure that the priority of each task is clear to the team.

C.  

Ask the team to self-organize and manage the work assigned.

D.  

Tell the team which task to focus on at the next daily standup.

Discussion 0
Questions 181

A project leader of an agile team realizes that one team member is unmotivated, which is affecting the whole team. What should the project leader do to improve the situation?

Options:

A.  

Invest in developing the team's emotional intelligence.

B.  

Ask the unmotivated team member to take a short leave.

C.  

Reduce the number of daily and retrospective meetings.

D.  

Send the unmotivated team member to another team.

Discussion 0
Questions 182

A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?

Options:

A.  

Ask stakeholders to communicate with the project manager and not directly with the team

B.  

Empower the team members to remove obstacles and blockers

C.  

Address and remove obstacles and blockers for the team

D.  

Add blockers to the issue log and risk management plan

Discussion 0
Questions 183

A project manager has noticed that the performance of a new team member has increased dramatically over the past few months The project manager has been measuring this team member's performance through the cost performance index (CPl) and schedule performance index (SPl) of work packages. The project manager has also assigned new. unrelated work packages to this team member The project manager wants to formally record the team member's success in the project documentation

What should the project manager do?

Options:

A.  

Attach a note to the project management plan about the team member

B.  

Hold a project team meeting about the team member's contribution and take minutes

C.  

Record the team member's contribution in the responsibility assignment matrix (RAM)

D.  

Send a communication to management recognizing the team member's contributions

Discussion 0
Questions 184

The project manager has recently received funding approval for a training program

for the entire project team but has not yet defined the most effective training course. One

team member submitted a request for specialized training that is required for the project.

How should the project manager handle this request?

Options:

A.  

Send this change request to the change control board (CCB) for approval.

B.  

Approve the request for the specialized training.

C.  

Reject the request as it does not impact the project deliverables.

D.  

Validate if the training is within scope and budget.

Discussion 0
Questions 185

At the end of planning a new project, the project manager needs to schedule the

kick-off meeting but is having difficulty finding a common time slot when all necessary

stakeholders can be available onsite. How should the project manager proceed to

schedule the kick-off meeting?

Options:

A.  

Email all stakeholders with the objectives of the project and ask for feedback.

B.  

Wait for a date when all required attendees can be available onsite.

C.  

Run separate meetings to accommodate everyone's schedule.

D.  

Schedule a virtual meeting so onsite and remote stakeholders can attend at the same time.

Discussion 0
Questions 186

During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.

What should the project manager do?

Options:

A.  

Schedule a meeting with the new sponsor in order to explain the agile approach and how teams are supposed to be self-organized.

B.  

Schedule an emergency meeting with the project team so they fulfill every request that comes from the sponsor.

C.  

Review the sponsor's request with the project team during the next daily review meeting in order to provide the requested control.

D.  

Review the sponsor's request with the project team during the next iteration review meeting in order to obtain a team decision.

Discussion 0
Questions 187

A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?

Options:

A.  

The team with the higher velocity is performing better and should be rewarded.

B.  

The issue should be addressed as part of a retrospective in the next iteration.

C.  

The velocity should not be compared as teams can size items differently.

D.  

The velocity of both teams should be compared at the end of every iteration.

Discussion 0
Questions 188

On a project to create the perfect paper airplane, the development of the airplane Is performed In iterations. The artwork to go on the wings and tail is done using a predictive approach. One of the stakeholders provides a requirement that conflicts with the product owner's requirements.

Who is responsible for analyzing the new requirement and making the final decision?

Options:

A.  

Project manager

B.  

Scrum master

C.  

Project sponsor

D.  

Product owner

Discussion 0
Questions 189

A supplier was supposed to mobilize a government-issued, licensed piece of

equipment two days ago, but did not. The procurement manager was informed that the

supplier failed to check the validity of the license, which expired last week. The supplier had

already submitted an application to the authorities, but it generally takes one to three weeks to process the application, which will affect the critical path.

Which action should the project manager take?

Options:

A.  

Update the project team on the delay so that resources can be utilized elsewhere.

B.  

Analyze the schedule and look for fast tracking and crashing alternatives.

C.  

Review the terms of the contract in order to determine next steps.

D.  

Update the lessons learned register to serve as an input for future material transactions.

Discussion 0
Questions 190

A project manager is leading a virtual team that is geographically dispersed. What

should the project manager do to avoid uncertainty in the project due to different cultures?

Options:

A.  

Start the project and add any uncertainty that arises to the risk register.

B.  

Dissolve the virtual team and build a colocated team.

C.  

Gather relevant cultural data and engage members in discussions covering their work ethics.

D.  

Build a culturally neutral team that will not be affected by cultural differences.

Discussion 0
Questions 191

Since the beginning of a project, the product owner keeps asking during ceremonies about the budget spent for each product iteration The product owner seems much more interested in the cost rather than the product itself.

What should the project manager have done earlier to change the product owner's behavior''

Options:

A.  

Worked on a fixed-price contract to switch the product owner's attention to value instead of money

B.  

Worked on a communications management plan with reports of budget spent in each iteration versus planned to avoid these discussions during ceremonies

C.  

Worked on different approaches of estimating to give confidence of the cost spent in each product increment.

D.  

Worked with the product owner to clarify their role in an agile project and the scope of the agile ceremonies

Discussion 0
Questions 192

The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?

Options:

A.  

Reschedule the project execution date.

B.  

Continue project execution using the current blueprints from the client.

C.  

Escalate this issue to the project sponsor

D.  

Consult with the client to determine if project execution should be continued.

Discussion 0
Questions 193

A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?

Options:

A.  

Request the team member to move to another team.

B.  

Delegate other team members to complete this team member's tasks.

C.  

Mentor the team member and provide the necessary training.

D.  

Include this team member in an improvement program through a human resources request.

Discussion 0
Questions 194

A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted However, a government agency has recently Introduced new standards that may significantly impact the project The deliverables must be changed to align with the new quality standards

What should the project manager do?

Options:

A.  

Set up a structured, independent processes to determine if project activities followed the standards.

B.  

Schedule training for the project team on the new regulations introduced by the government agency

C.  

Evaluate the impact the new regulations will have on the project and submit a change request

D.  

Update the lessons learned register and inform senior management of the new standards

Discussion 0
Questions 195

A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.

What should the project manager do?

Options:

A.  

Inform the stakeholder that the new requirement will be considered in the next release planning session.

B.  

Inform the sponsor of the latest changes and ask the sponsor to prioritize the features.

C.  

Ask the product owner to determine if this requirement needs to be treated as a top priority.

D.  

Direct the development team to work on this requirement right away.

Discussion 0
Questions 196

In an agile project, the project manager notices that one team member rarely reports blockers during daily check-ins. Additionally, the team member is too shy to participate in team activities and prefers to provide status updates individually to the project manager.

How should the project manager rectify this situation?

Options:

A.  

Review team culture and the personality traits of the individual to address status update gaps.

B.  

Create a safe space for status updates and encourage the team to approach the project manager.

C.  

Review the team status updates more thoroughly to address the gaps.

D.  

Support team inclusion and change the format of status updates to email.

Discussion 0
Questions 197

A project manager decided to incorporate the latest technological advancement with the client's devices at no additional cost to the project.

Upon completion and submission of the project deliverables, the client rejected the devices, despite having the latest features.

What should the project manager have done?

Options:

A.  

Incorporated the change within the scope of the project

B.  

Reviewed the quality inspections

C.  

Complied with the customer specifications

D.  

Documented the technical reviews with the new change

Discussion 0
Questions 198

At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.

What should the project manager do next?

Options:

A.  

Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.

B.  

Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.

C.  

Address this concern with the functional managers to ensure there will be no further delays.

D.  

Schedule a meeting with all of the functional managers to resolve the resource conflicts.

Discussion 0
Questions 199

An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable.

What should the project manager have done to avoid this situation?

Options:

A.  

Ensured the project repository is up to date.

B.  

Updated the job descriptions for all team roles.

C.  

Provided specialist training for all team members.

D.  

Made an effort to reemploy the senior project team member.

Discussion 0
Questions 200

A company is developing a new product. During project planning, a stakeholder from the legal department does not attend any of the project meetings and is not interested

in the product design.

How should the project manager deal with this situation?

Options:

A.  

Escalate the issue to the project sponsor and seek assistance.

B.  

Engage the project stakeholder and ensure all requirements are captured.

C.  

Review the stakeholder engagement plan and communication strategy.

D.  

Review the product requirements and update the stakeholder register.

Discussion 0
Questions 201

An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.

What should the project manager recommend?

Options:

A.  

Time-boxed iterations to allow the testing team to thoroughly test the product increments

B.  

Incremental delivery and frequent backlog refinement based on user feedback

C.  

Iterative development and collection of frequent feedback from project team members

D.  

Frequent retrospectives to ensure that lessons learned and improvement actions are implemented

Discussion 0
Questions 202

A contractor has been making small changes to the engineering specifications without submitting change requests. The contractor and the technical team did not discuss the changes with the project manager, and the modifications do not affect the budget and quality of the deliverable.

What should the project manager do?

Options:

A.  

Report the violation to the change control board (CCB) and seek comprehensiveapproval for these modifications.

B.  

Update the change management plan to define the level of control required forthese types of modifications.

C.  

Ask the quality control team to evaluate the modifications, but take no actionbecause the associated quality risks are insignificant.

D.  

Request the engineering team to update the specifications to reflect the modifications made by the contractor.

Discussion 0
Questions 203

A project manager is assigned to a global project with dispersed team members. Previously, when working with remote teams, the project manager observed that team members do not tend to produce quality work.

What should the project manager do to ensure the project is completed on time with quality?

Options:

A.  

Encourage the team to participate in a peer evaluation activity by the end of the project.

B.  

Introduce the use of time sheets and ask team members to review and submit them regularly.

C.  

Arrange regular team meetings for the team to update one another on the progress of their assigned tasks.

D.  

Meet with the team together and in one-on-one meetings to set clear, shared targets.

Discussion 0
Questions 204

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?

Options:

A.  

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team

B.  

Escalate the issue to the functional manager

C.  

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training

D.  

Perform the quantitative risk analysis for the team member.

Discussion 0
Questions 205

A project in aerospace design has run into a substantial technical issue, and the project team is uncertain on how to proceed. With whom should the project manager call a meeting to discuss the issue?

Options:

A.  

Project stakeholders and the team

B.  

External subject matter experts (SMEs) and the team

C.  

Project sponsor and the team

D.  

Project sponsor and the external SMEs

Discussion 0
Questions 206

On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?

Options:

A.  

Escalate the issue to the project sponsor.

B.  

Review the stakeholder engagement plan.

C.  

Update the issue log.

D.  

Neutralize the negative stakeholders.

Discussion 0
Questions 207

For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product

After collecting the new requirements, what should the project manager do?

Options:

A.  

Assess the impact of the new requirements and initiate the change request process.

B.  

Work with the product manager and the rest of the team to update the project backlog.

C.  

Assess the impact and communicate the updated product roadmap to the stakeholders.

D.  

Follow the change management plan to update the risk register so It accounts for the added scope.

Discussion 0
Questions 208

A product owner has indicated there is strong customer interest in adding a new set of functionalities to a product. Using agile approaches, the project manager evaluates the new functionalities of the product.

What should the project manager do?

Options:

A.  

Negotiate with the product owner to determine which functionality should be pushed out of the scope of the project.

B.  

Discuss with the team how this change in scope impacts development at the next retrospective to determine next steps.

C.  

Negotiate with the product owner to determine what might be removed from the backlog that is of similar size.

D.  

Add the functionality to the product backlog for inclusion once a change request is created and approved.

Discussion 0
Questions 209

A large and complex project is comprised of multiple regions. The estimate to complete (ETC) work is assumed to be performed at the same cumulative cost performance index (CPI) as that incurred by the project to date. As of now, the earned value (EV) is 145 person/day, the planned value (PV) is 145 person/day, the actual cost (AC) is 170 person/day, and budget at completion (BAC) is 285 person/day.

What is the estimate at completion (EAC)?

Options:

A.  

334 person/day

B.  

285 person/day

C.  

310 person/day

D.  

315 person/day

Discussion 0
Questions 210

A project manager works for an IT consulting firm that has submitted a bid during the request for proposal (RFP) process for a contract that focuses on data center migration and optimization. However, the consulting firm has little experience in data center optimization.

What should the project manager do?

Options:

A.  

Send the team to a data center optimization training workshop.

B.  

Partner with a company that is an expert in this area.

C.  

Outsource the data center optimization work to a vendor.

D.  

Request a budget to build this competency among project team members.

Discussion 0
Questions 211

A project team has experienced deliverable delays in the last few iterations. During the retrospective, the team realizes that the quality issues identified are because the quality process is outdated.

Who should the project manager ask to update the process?

Options:

A.  

Project team

B.  

Project management office (PMO)

C.  

Quality lead

D.  

Product owner

Discussion 0
Questions 212

An investment company is interested in unifying direction and control criteria in one of its principal projects. The project manager was advised to enforce the main framework of this initiative.

What should the project manager do first?

Options:

A.  

Document the direction and control framework into the project charter.

B.  

Develop an engagement plan to achieve consensus.

C.  

Identify and interview all of the relevant stakeholders.

D.  

Get direction and control framework requirements from stakeholders.

Discussion 0
Questions 213

During a planning session, the development team and the product owner are arguing about the effort needed to deliver a specific feature in a software development project. The product owner says that the feature can be developed in one week, whereas the team estimates that it will take at least two weeks. After several hours of discussion, they have not reached an agreement.

What should the project lead do?

Options:

A.  

Communicate to the stakeholders that the project has to be delayed for two weeks.

B.  

Ask the project team to accept the shorter estimate as it is important to keep a good relationship with the product owner.

C.  

Decide what should be the time estimate and proceed with the planning meeting.

D.  

Educate the product owner that the project team members are the most appropriate group for assessing the effort.

Discussion 0
Questions 214

A project team is struggling to meet the project deadline due to a recurring conflict between two team members. What should the project manager do?

Options:

A.  

Hold the team collectively responsible for their actions.

B.  

Explore the possibility of reshuffling the team.

C.  

Introduce training sessions to improve the team's performance.

D.  

Schedule team-building activities as required.

Discussion 0
Questions 215

A company in the manufacturing industry has started a new initiative to integrate project management and improve product innovation. What first step should the project manager take to increase transparency among the stakeholders?

Options:

A.  

Define a plan on how communication throughout the project will be handled among the stakeholders.

B.  

Set up a project dashboard to show day-to-day project status across the company.

C.  

Invite key stakeholders to retrospective and review sessions to receive feedback as often as possible.

D.  

Invite upper management to process workshops where current project statuses will be discussed.

Discussion 0
Questions 216

An IT team has reached out to the project manager for guidance on which communication method to use when system downtime will impact the resources working on the project.

Which two communication methods should the project manager recommend? (Choose 2)

Options:

A.  

Communicate via email to the project's email distribution group.

B.  

Communicate via instant messaging.

C.  

Communicate via the project team's document management site.

D.  

Communicate in the IT risk forum.

E.  

Communicate verbally to the key project stakeholders.

Discussion 0
Questions 217

To ensure effective team communication and processes, a standard set of software including video conferencing is defined for a virtual scrum team. Several team members are reporting problems with their access and cannot adhere to team processes.

How should these issues be resolved?

Options:

A.  

Individual team members should discuss solutions to resolve the issues after the Scrum is concluded.

B.  

The scrum master should ensure the appropriate escalation to resolve the issues.

C.  

The product owner owns the open issues until they are resolved.

D.  

Individual team members need to submit service desk tickets to resolve the issues.

Discussion 0
Questions 218

An experienced project manager is in a meeting with project key stakeholders when they are informed that a senior manager with extensive experience on similar projects will join the project steering committee. The project kick-off meeting is scheduled for the following week.

What should the project manager do next?

Options:

A.  

Have the kick-off meeting as scheduled and capture any new requirements raised in the meeting.

B.  

Have a one-on-one interview with the new senior manager before the kick-off meeting.

C.  

Ask the new senior manager to send any new requirements before the kick-off meeting.

D.  

Ask the project sponsor to hold the kick-off meeting after the new senior manager has onboarded.

Discussion 0
Questions 219

A project has obtained all of the necessary legal requirements and policies from the local government. During the execution phase, the product owner is informed that a new law impacting the project deliverables will be published within two weeks.

What should the project lead do?

Options:

A.  

Review the product backlog items to evaluate the impact on scope and prioritize accordingly.

B.  

Develop a change request for more resources and update the project budget and schedule.

C.  

Ask the internal legal department to evaluate if the regulatory law could be managed internally.

D.  

Work with the team to develop an alternative solution with no additional effect on the project's budget.

Discussion 0
Questions 220

A supplier that the company has used for years has trouble accepting the new terms of an agile contract. They do not understand the terms in the contract and feel they should not have to sign it because they have had a long relationship with the company.

Which action should the project manager take?

Options:

A.  

Ask the team if they can do the work until there is an available supplier.

B.  

Train the supplier in agile approaches to help them understand the contract.

C.  

Issue a request for proposal (RFP) to find new suppliers with agile experience.

D.  

Change contract terms and conditions to avoid losing the supplier.

Discussion 0
Questions 221

During a sprint, the team is experiencing conflict because the customer asks for additional features that increase the complexity. The scrum master is trying to resolve the conflict.

Which approach should the scrum master use?

Options:

A.  

Discuss the definition of done (DoD) with the customer.

B.  

Approach the product owner to determine the next course of action and update the backlog.

C.  

Discuss the acceptance criteria with customer.

D.  

Perform backlog prioritization to ensure that everyone is working on the highest value features.

Discussion 0
Questions 222

Multidisciplinary teams will be needed for a project. The project manager asks the project planner to create a consolidated schedule. The project manager determines from the consolidated schedule that the project's finish date exceeds the requested finish date.

What should the project manager suggest to the planner to analyze this issue?

Options:

A.  

Verify the total float of each activity of the consolidated project schedule.

B.  

Verify the critical path of the consolidated project schedule.

C.  

Verify successors and predecessors of each activity of the consolidated project schedule.

D.  

Verify the free float of each activity of the consolidated project schedule.

Discussion 0
Questions 223

Due to an anticipated expansion, a company procured new technology. The project team responsible for using this technology does not have experience with it.

What should the project manager do?

Options:

A.  

Assess the benefit of using new technology versus old technology.

B.  

Hire project resources with experience using the new technology.

C.  

Propose training for the project team in batches on the new technology.

D.  

Request incentives for the team to use the new technology.

Discussion 0
Questions 224

A project is using a Scrum team from a new vendor to deliver a component. Engaging a new vendor was identified as a delivery risk that, if eventuated, must be escalated to the board. The project manager and product owner work well with the Scrum team, but the vendor misses the first release by a couple of weeks.

What should the project manager do?

Options:

A.  

Escalate the issue to the board with opportunities to recover the delay as soon as possible.

B.  

Work with the product owner and the Scrum team to add 2 weeks to the release schedule.

C.  

Work with the product owner and the Scrum team to recover the delay before the last release.

D.  

Escalate the issue to the board and plan for the engagement to be terminated.

Discussion 0
Questions 225

A project is delayed considerably from its original completion date for various reasons. The client attributes the delays to the contractor and is going to impose liquidated damages. The project manager of the contracting company reviews the schedule and observes that, though some activities were delayed by the contractor, the critical activity was delayed by the client.

What should the project manager of the contracting company do?

Options:

A.  

Record that the delay is attributable to the client and request a meeting.

B.  

Check the contractual terms about liquidated damages and reject if not applicable.

C.  

Meet with the sponsor to analyze the delays and the associated liquidated damages.

D.  

Schedule a detailed analysis of the delays using cause and effect.

Discussion 0
Questions 226

In the execution phase of a project, the development team is informed by the IT security department that one of the external platforms that the team is using will be uninstalled for the whole organization.

What should the project manager do first?

Options:

A.  

Escalate the issue to the change control board (CCB).

B.  

Ask the project team to analyze the impact.

C.  

Register the risk and document the contingency plan.

D.  

Have the project team brainstorm alternatives.

Discussion 0
Questions 227

An organization is undergoing an agile transformation and migrating most of its projects from a predictive approach. The CFO expressed a concern that predictability on both costs and scope will be lost with the new agile approach.

What should the project manager do?

Options:

A.  

Provide mentoring to the CFO, who is a key stakeholder in the project, and clarify the benefits of an agile approach.

B.  

Ask the CEO to intervene by asking for support from the executive board to accelerate the company's transformation.

C.  

Apply influence with other key stakeholders on the board to mitigate any risks that may be generated by the CFO's position on the matter.

D.  

Submit a report to all key stakeholders on the cost-benefit analysis of the new approach and detail how the company will save money.

Discussion 0
Questions 228

Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed.

Which three actions should the project manager do? (Choose 3)

Options:

A.  

Stop the project and review the output.

B.  

Ask the testers to provide additional information.

C.  

Ask the sponsor for assistance and guidance.

D.  

Continue with testing according to the plan.

E.  

Brainstorm the issue with the project team.

Discussion 0
Questions 229

A project manager has been assigned to a new project. The project sponsor has requested a detailed time line, but the project includes some deliverables that are not yet clearly defined.

Which project management approach should the project manager advise using?

Options:

A.  

As the project includes elements that are not yet clearly defined, an agile approach is the best option.

B.  

As the project sponsor has requested a detailed time line up front, an agile approach is the best option.

C.  

As the project appears to have both agile and predictive elements, a hybrid approach is the best option.

D.  

As the project includes elements that are not yet clearly defined, a predictive approach is the best option.

Discussion 0
Questions 230

A project team member who was a top performer in the planning phase of a project was easily irritated during the fifth sprint of the software development phase. The team member's attitude and behavior made the other team members feel uncomfortable.

What should the project manager do?

Options:

A.  

Assess the workload of each team member and redistribute tasks.

B.  

Meet with the team member to offer any help that may be needed.

C.  

Reorganize the team to reduce the interactions causing the team discord.

D.  

Arrange an immediate agile training course for the team member.

Discussion 0
Questions 231

Project stakeholders have provided a team with requirements that will take at least one year to complete. The project sponsor advised that they need to see some return on investment (ROI) soon.

What should the project manager do?

Options:

A.  

Request additional funding from the project sponsor to accelerate delivery.

B.  

Discuss reducing the requirements with the project sponsor in order to release the product earlier.

C.  

Prioritize the work into incremental features that can be delivered iteratively.

D.  

Acknowledge that the benefits cannot be realized any sooner due to the nature of the requirements.

Discussion 0
Questions 232

A project manager is leading the construction of a branch office building for a national bank. The project manager is informed that the regulatory authority has closed the bank.

In closing this project midway, which activities should the project manager execute first?

Options:

A.  

Perform contract, financial, and administrative tasks.

B.  

Finalize the in-progress administrative tasks.

C.  

Evaluate contract and administrative tasks.

D.  

Execute financial and administrative tasks.

Discussion 0
Questions 233

A company is experiencing a high rate of rejected project deliverables. The project manager is requested to suggest a solution to improve quality.

What should the project manager suggest?

Options:

A.  

Request that all team members receive the newest quality standards training and review one another's work.

B.  

Request that a quality specialist be assigned to the project to check the final product at the end of the project.

C.  

Break down the project into several iterations and incorporate a quality check by a quality auditor in each iteration.

D.  

Break down the project into several iterations and incorporate automatic testing and quality improvement sessions.

Discussion 0
Questions 234

A project manager leads an agile development project. During the sprint planning meeting, the development team expresses concerns that the proposed scope of the next sprint is much larger than expected given the current resource allocation. The project manager believes the scope is essential to meet the project milestones.

How should the project manager approach negotiating an agreement with the team to ensure the project remains on track?

Options:

A.  

Allocate additional resources to the development team to ensure the original scope can be completed on time.

B.  

Suggest prioritizing the most critical features for the next sprint as well as reevaluating the remaining scope.

C.  

Agree on reducing the scope to match the team's resources and plan to add the removed items to future sprints.

D.  

Insist on keeping the original scope and explain the importance of meeting all the project milestones on time.

Discussion 0
Questions 235

The project team is conducting iteration planning and having difficulty evaluating a new technology that will be used in this iteration. What should the project lead do?

Options:

A.  

Hire an external subject matter expert (SME) to help with design and implementation.

B.  

Coach the team to determine a path forward to achieve an efficient solution.

C.  

Provide technical guidance on complexity assessment.

D.  

Guide the team with estimating the time required.

Discussion 0
Questions 236

While working with the project team on planning project resources, the project manager discovers that a critical resource will be assigned at the same time to another project in the organization. The project team explains to the project manager that this resource cannot be replaced by another resource.

What should the project manager do first?

Options:

A.  

Contact the human resources (HR) department to find new resources to replace this critical resource.

B.  

Meet with the project lead of the other project to evaluate how to best allocate the critical resource in both projects.

C.  

Ask the project team to reschedule the project tasks that will demand the use of this critical resource.

D.  

Discuss the resource management plan with the project team for effective utilization of critical resources.

Discussion 0
Questions 237

A project manager is leading the development and delivery of a strategic product that must be delivered on time. The project is facing technical issues that could significantly impact the budget and ability to deliver some of the product features.

What should the project manager do first to resolve the issue?

Options:

A.  

Record the situation in the risk register and communicate it to stakeholders.

B.  

Assess the impact of the feature on the project and ask for a contingency.

C.  

Schedule a meeting with the team and management to discuss options.

D.  

Develop a quality management plan to clearly identify how features should be classified.

Discussion 0
Questions 238

During a sprint, the product owner requested a change in the features to be delivered in the same sprint. According to the product owner, the request from the customer is due to regulatory reasons and they have a deadline to meet.

What should the project manager do?

Options:

A.  

Perform the change only if it has a higher or equivalent priority of the current remaining features.

B.  

Submit the feature changes to the change control board (CCB) so they can evaluate and approve.

C.  

Follow the plan by delivering the features and handle the change later in the project.

D.  

Discuss with the stakeholders about the possibility of accommodating the feature changes.

Discussion 0
Questions 239

A team member has escalated an issue to the project manager, stating that they have done their part of the job. Their concern is that there is still no response from the other party in the service level agreement (SLA). The team member is eager to find a resolution for the reported issue.

What should the project manager advise the team member to do to ensure that the project escalation mechanism is effective?

Options:

A.  

Involve all of the stakeholders in the escalation by setting up a conference call.

B.  

Escalate to the other party's management and inform the steering committee.

C.  

Reach out to peer managers for similar escalation situations and follow past experiences.

D.  

Review the established project escalation process and take the appropriate action.

Discussion 0
Questions 240

A customer complains that a software update project is failing to deliver value according to the original scope. What should the project manager do to resolve the problem?

Options:

A.  

Ensure that the project issue log is up-to-date with the customer's issues related to the missed stories.

B.  

Ensure that the project change log is up-to-date with the stories based on the missed requirements.

C.  

Ensure that the project backlog has the features and stories prioritized correctly.

D.  

Ensure that the project risk register is current and reflects the impacts posed by stories not delivered.

Discussion 0
Questions 241

A project manager is developing the project schedule with the project team. The team members estimate that an optimistic duration is 5 days, the pessimistic duration is 20 days, and the most likely duration is 11 days.

What duration should the project manager use?

Options:

A.  

11 days

B.  

12.5 days

C.  

12 days

D.  

11.5 days

Discussion 0
Questions 242

A project manager notices that an extroverted project team member appears to be increasingly controlling the direction of the entire team. The other team members are not complaining but seem to be more passive.

What should the project manager do?

Options:

A.  

Meet with each team member to better understand the situation.

B.  

Meet with the extroverted team member and ask them to be more sensitive to others.

C.  

Address the situation in a team meeting and ask everyone to be more active.

D.  

Observe the team dynamics closely and step in if a team member complains.

Discussion 0
Questions 243

A steering committee has asked the project manager to assist with the decision-making process between build versus buy delivery options. Which value metric should the project manager evaluate to respond to the steering committee's request?

Options:

A.  

Impact value

B.  

Expected monetary value (EMV)

C.  

Net present value (NPV)

D.  

Earned value (EV)

Discussion 0
Questions 244

A team member mentions to the scrum master that the user stories are too long. The team member believes this may be the cause of the team's inability to deliver value for stakeholders.

What should the scrum master do?

Options:

A.  

Review the user stories with the team and ask the product owner to break them down into more manageable units.

B.  

Review the user stories with the stakeholders and ask the product owner to break them down into more manageable units.

C.  

Ask the team member to suggest using shorter user stories to the product owner so that the next sprint can move faster.

D.  

Ask all the team members for their views about using shorter user stories so that value can be created for stakeholders.

Discussion 0
Questions 245

A project manager was just assigned to an ongoing project. According to the project's status, all the increments produced passed the acceptance criteria. During the last meeting with the project sponsor, the prototype is far from the sponsor's original expectations.

What should the project manager do first?

Options:

A.  

Cancel the ongoing project and start a new one.

B.  

Invite the sponsor to the retrospective meeting so they can clarify expectations.

C.  

Add additional sprints to modify the deliverables with the new information.

D.  

Complete the project and start a new one for the updated scope.

Discussion 0
Questions 246

A scrum master noticed that one of the team members is afraid to ask questions, does not like to collaborate with other team members, and avoids taking responsibility for their actions. What is the likely reason that would cause a team member to behave that way?

Options:

A.  

Lack of technical skills

B.  

Fear of conflict

C.  

Lack of experience

D.  

Company culture

Discussion 0
Questions 247

A project team is using an iterative and incremental delivery approach. The sprint's duration is 1 month with a production release every 3 months. In the last sprint review, the users communicated that they want the functionality presented and deployed in 5 weeks. The project lead is working on the next release plan.

When should the project lead have their team deploy the functionality?

Options:

A.  

In 1 month

B.  

In 5 weeks

C.  

In 12 weeks

D.  

In 2 months

Discussion 0
Questions 248

A project manager is managing a project with a cost performance index (CPI) of 1.05 that is trending downward. To maintain on-time completion, the scrum master needs to add 30 additional team members in the next month to enable more sprints. The project manager is concerned because the schedule performance index (SPI) is 1.0.

What is the first step the project manager should take?

Options:

A.  

Meet with the project team to forecast the SPI trend to determine if there are funds available to pay the 30 team members.

B.  

Quantify the cost for the 30 team members and determine if there is budget available to fund the expanded team.

C.  

Inform the project team that since the CPI is trending downward, there are funds available to expand the team.

D.  

Engage with the human resources (HR) representative to begin selecting candidates for the 30 open positions.

Discussion 0
Questions 249

A global and complex project is in the execution phase. Recently, there were executive board changes, and the executive sponsor is transitioning to a new role. The outgoing sponsor asked the project manager to speed up project completion of the current phase to ensure successful onboarding of the new sponsor.

What should the project manager do?

Options:

A.  

Use the contingency budget to implement compression techniques to finish the current project phase early.

B.  

Review the stakeholder engagement plan and determine the best course of action to take.

C.  

Notify the outgoing sponsor that the project needs to be put on hold until the new sponsor is onboarded.

D.  

Submit a change request to the change control board (CCB) to modify the end date of the current phase.

Discussion 0
Questions 250

A team is performing above expectations, and the sponsor wants to expand the project scope to benefit the organization. However, there are only a few team members with the needed leadership experience.

What should the project manager do?

Options:

A.  

Communicate the risks and propose hiring members with leadership experience before continuing with the request.

B.  

Decline the scope expansion until the team members get appropriate leadership opportunities within the project.

C.  

Implement the scope expansion and suggest the team members get a mentor due to their lack of leadership experience.

D.  

Recognize each team member for their contributions and recommend them to the leadership development program.

Discussion 0
Questions 251

A new offshore call center project is vital for a company's branch offices. The project is at the end of the planning phase when the project manager is informed by the sponsor that the project will be delayed due to reprioritization.

What should the project manager do?

Options:

A.  

Create a messaging group chat with the branch office stakeholders to inform them about the project delay.

B.  

Schedule a video conference to inform the branch office stakeholders about the project delay.

C.  

Send an official project memo to inform the branch office stakeholders about the project delay.

D.  

Include the project delay in the monthly progress report for the branch office stakeholders.

Discussion 0
Questions 252

A project manager has been assigned a project team with members in two different locations. The project manager noticed that the productivity of a senior team member in the other location is much lower than the local junior team members.

What should the project manager do to address the issue?

Options:

A.  

Share a work performance report with the team member's supervisor.

B.  

Assign a mentor to work with the senior team member.

C.  

Speak with the senior team member to identify the difficulties.

D.  

Collect feedback from all team members about team performance.

Discussion 0
Questions 253

A project manager regularly sends out project progress reports. However, there have been a few complaints from stakeholders who expressed that the communication does not meet their needs.

What should the project manager do?

Options:

A.  

Analyze the communication needs of the stakeholders.

B.  

Communicate the project details to the stakeholders.

C.  

Communicate progress more frequently to the stakeholders.

D.  

Introduce a separate stakeholder engagement meeting.

Discussion 0
Questions 254

Two experienced team members in a hybrid project are having a conflict about a technical solution. The project manager has already spoken individually to the two team members without successfully resolving the conflict.

What should the project manager do next?

Options:

A.  

Discuss the topic with the team members in a team meeting.

B.  

Replace the two team members with other resources.

C.  

Contact the functional managers of each team member.

D.  

Schedule a meeting with both team members.

Discussion 0
Questions 255

A project team used agile approaches to create a minimum viable product (MVP). Currently, the team is discussing the possible next steps.

What should be the next step?

Options:

A.  

Break down the user stories into the smallest size possible.

B.  

Ensure user stories provide the steps necessary for implementation.

C.  

Prioritize the work at the user-story level.

D.  

Use scope cards in conjunction with story points.

Discussion 0
Questions 256

A project manager is approached by two new product owners who were instructed by their managers to join a new agile team. Both product owners were told they could start working with the new agile team immediately.

What should the project manager do to advise both product owners?

Options:

A.  

Modify the communications management plan to integrate the new product owners into the teams effectively.

B.  

Reiterate that having one product owner will improve clarity and accountability.

C.  

Present the product owners' product backlogs and prioritize the team's assigned requirements.

D.  

Confirm that two product owners are necessary and that both will report to an overarching chief product owner.

Discussion 0
Questions 257

During a daily meeting of a challenging project, two team members started to argue on the preferred solution based on their assumptions. The situation prevented the progress to the next phase of development, which could impact the finish date of the project.

What should the project manager do next?

Options:

A.  

Divide the team into small groups to avoid future arguments and delays.

B.  

Ask the human resources (HR) department to replace the team members.

C.  

Make a decision based upon the project manager's knowledge and expertise.

D.  

Meet with the team members to discuss the priority of the project schedule.

Discussion 0
Questions 258

A project manager has recently been assigned to a new project. When the project manager first meets the project team, the team tells the project manager that all of the management plans and documents for the project are missing.

What should the project manager do?

Options:

A.  

Ask the stakeholders to develop all of the project artifacts so the project team can continue their scheduled activities.

B.  

Create the project management plans with the project team and share the documents with the stakeholders.

C.  

Continue working on scheduled tasks to avoid delaying the project and leave the development of project artifacts for later.

D.  

Adapt the project management plans and documents from previous executed projects in order to save time.

Discussion 0
Questions 259

During the execution of a project, a project manager is informed that a team member is leaving the company. What should the project manager do next?

Options:

A.  

Wait for the next project status meeting to evaluate the impact of one less resource.

B.  

Ask the project sponsor to replace the resource immediately.

C.  

Record the situation in the issue log immediately and evaluate the impact of losing the resource.

D.  

Freeze the activities of the lost resource until they are replaced.

Discussion 0
Questions 260

A project manager has just been designated to lead an approved project with a virtual team. The team members are from several countries and have never met before.

In order to promote team engagement and introduce the project team, what should the project manager do?

Options:

A.  

Share a presentation with information about each project team member.

B.  

Share all members' resumes and photographs in a sharing digital platform.

C.  

Schedule multiple one-on-one meetings between team members.

D.  

Schedule a kickoff meeting to present the whole project team.

Discussion 0
Questions 261

A project manager is trying to define a project time line despite having incomplete and ambiguous information on requirements and regulations. What should the project

manager do to finish planning?

Options:

A.  

Review project documents to identify and eliminate uncertainties and inconsistencies.

B.  

Execute a root cause analysis to discover the underlying factors that might lead to risks and issues.

C.  

Perform an assumption and constraint analysis to provide more opportunities and remove limiting factors.

D.  

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

Discussion 0
Questions 262

A project is nearing finalization and just released the final product to the customer. The assigned project manager left the company without notice and without sharing any information or documents for the remaining activities. A new project manager has just been assigned to the project.

What should the new project manager do next?

Options:

A.  

Schedule a lessons learned meeting with the project team and close out the project.

B.  

Use the contingency fund to extend the timeline and conduct a detailed review of past deliverables.

C.  

Prepare a transition plan to hand over the operations and other closing documentation.

D.  

Document the project manager's departure and the missing documents in the risk log.

Discussion 0
Questions 263

During a contract renewal meeting, an organization's commercial team and the customer are disagreeing and negotiations are failing. What should the project manager do to reach an agreement that will satisfy all parties?

Options:

A.  

Reinforce the initial rules of the negotiations.

B.  

Engage a facilitator to support the negotiations.

C.  

Concentrate on meeting the customer's requests.

D.  

Set clear expectations among the participants.

Discussion 0
Questions 264

A company is transitioning from using a predictive approach to using an agile framework on a project. The project sponsor is concerned about the level of uncertainty and how to determine the time and budget required to complete the scope.

What should the project manager do to address this situation?

Options:

A.  

Communicate to the key stakeholders that the project baseline could not be estimated due to the new framework being used.

B.  

Ask the project team to create a high-level budget baseline for the project and provide more detail only for the first project stages.

C.  

Review organizational process assets (OPAs) for similar projects to determine the schedule, costs, and resources required to execute them.

D.  

Refine the amount of work required for the project with the project team and perform a detailed project baseline accordingly.

Discussion 0
Questions 265

A project lead was recently elected to complete the execution of a legacy project for a water filtration plant due to the project director's reassignment. The project lead has been on five similar projects in the recent past. The client has challenged the completion status due to a lack of construction evidence. The client has also indicated their intention to apply performance-associated penalties that are detailed in the contract.

What should the project lead do?

Options:

A.  

Accept the client's observations and pay the penalties as per the project contract details.

B.  

Investigate the client's project reports and proceed to negotiate the levying of any penalties.

C.  

Inform the project director of the change and complete the project so as to not incur any penalties.

D.  

Request for the recall of the project director to investigate the situation and negotiate potential penalties.

Discussion 0
Questions 266

A key stakeholder of a project wants to include additional work before completion.

What should the project manager do?

Options:

A.  

Request the additional work through governance.

B.  

Meet with the stakeholder and explain that additional work cannot be added.

C.  

Prioritize the additional work in the backlog.

D.  

Collaborate immediately with the stakeholder to complete the additional work.

Discussion 0
Questions 267

A project manager was assigned to lead a global project with a virtual team that is globally dispersed. The project manager has difficulties communicating with the team members and there seems to be frequent misunderstandings and conflicts.

What should the project manager do?

Options:

A.  

Ask the team members to refamiliarize themselves with the communications management plan.

B.  

Organize effective communication training for team members.

C.  

Listen to team members actively and change the communication practices accordingly.

D.  

Model servant leadership by adapting to team requirements.

Discussion 0
Questions 268

The project team completed a demonstration of the main deliverable of the project. Although the project sponsor is happy with the outcome and is ready to sign the release to production, one of the business unit managers who attended the demo believes that the deliverable is not complete.

Which document should the project manager use to resolve this situation?

Options:

A.  

Requirements traceability matrix

B.  

Risk management plan

C.  

Project scope statement

D.  

Requirements management plan

Discussion 0
Questions 269

A project steering committee meeting was arranged to approve a milestone of a project within two weeks. The project manager is informed that a new project executive will take over the project.

What should the project manager do first?

Options:

A.  

Assess the risks with the team members.

B.  

Submit a change request to the change control board (CCB).

C.  

Evaluate the project impact and seek additional funding if necessary.

D.  

Brief the new stakeholders on the current project status.

Discussion 0
Questions 270

An agile team is struggling to successfully deliver what they have committed. During the daily status meetings, the project manager notices that the most senior engineer is doing all of the talking, leaving little time for the other members to share their status. The team's performance is not good, and some team members want to leave the team.

How should the project manager approach this situation?

Options:

A.  

Measure the team's psychological safety.

B.  

Reschedule the team's retrospective meeting.

C.  

Coach the team to be more inclusive.

D.  

Rotate the team's daily meeting roles frequently.

Discussion 0
Questions 271

A project manager received several complaints from different project team members related to an unnecessary additional step the functional lead implemented as a preference. The project team members' work has been affected by this and they have missed a few deadlines.

What should the project manager do to address this concern?

Options:

A.  

Recommend the functional lead meet with the project team members to convince them to accept the change.

B.  

Document the additional step from the functional lead and adjust the timelines to accommodate the change.

C.  

Ask the functional lead to remove this additional step as it is not vital to the project.

D.  

Advise the team that the functional lead's preference should be taken into consideration.

Discussion 0
Questions 272

During execution of the third sprint in a project, a project team is uncertain about the frequent updates on the vendor's platform. The team is concerned about how the updates will impact the rest of the backlog.

What should the project manager do to minimize the uncertainty?

Options:

A.  

Speak with the vendor and explain that constant updates are impacting the project and request an action plan to minimize the changes.

B.  

Schedule a spike meeting, conduct risk assessments, and incorporate them into the backlog to help with risk mitigation.

C.  

Explain to the project team that the vendor's updates are something unpredictable, and the team must continue working on the project.

D.  

Schedule a retrospective meeting and conduct a risk assessment with the team, implementing mitigation tasks before the next sprint.

Discussion 0
Questions 273

A project manager's project relies on services from a department that has a new leader. Since the new leader was appointed, the services from their department have been slow which threatens the project's delivery deadline.

What should the project manager do?

Options:

A.  

Add the issue to the issue log and communicate the issue in the next regular report to project stakeholders.

B.  

Escalate the issue to the project sponsor notifying them of the slow services from the department.

C.  

Send all service requests to the department earlier in the project to lessen the impact on the delivery date.

D.  

Arrange a meeting with the leader to explain the project's needs and understand the leader's perspective.

Discussion 0
Questions 274

A project is continuously overlapping phases. Due to a recent human error, the team, which is made up of senior members, is experiencing distrust issues from other departments and lacking initiative. This is impacting overall performance and putting the project objectives at risk.

What should the project manager do when executing the next sprint?

Options:

A.  

Coach those responsible for the error so that the whole team understands they are not responsible for it.

B.  

Explain high-level objectives and ask team members to self-organize around their tasks to meet the objectives.

C.  

Request offsite team-building activities and deploy incentive plans around their tasks.

D.  

Identify the poor performers and ask their functional managers to assign them a mentor.

Discussion 0
Questions 275

A project manager is working on a hybrid project and is responsible for ensuring the design, build, and delivery of the software is completed in an agile way. How should the project manager plan the iteration?

Options:

A.  

Use a work breakdown structure (WBS) with firm start and end dates for all phases to ensure nothing is missed.

B.  

Use a kanban board as an information radiator to manage work in progress (WIP) at the individual and organizational levels.

C.  

Use a minimum viable product (MVP) to test and discover which features to schedule when and what to fail early.

D.  

Use a product backlog of the functionalities and features required to provide the expected business benefit.

Discussion 0
Questions 276

A project manager is planning the fifth sprint of a project when the sponsor requests a report on the business value gained to date. What should the project manager show to the sponsor?

Options:

A.  

The cumulative flow diagram

B.  

The data of the metrics defined to track benefits

C.  

The metrics plan to track benefits

D.  

The fifth sprint retrospective report

Discussion 0
Questions 277

A project manager has an engineering team mostly comprised of new hires. The project manager has to carefully predict in which stage of the project they will need to spend most of their time to ensure the team is properly integrated and performing well.

In which stage of the project would the project manager need a greater effort to lead them?

Options:

A.  

Performing

B.  

Storming

C.  

Norming

D.  

Forming

Discussion 0
Questions 278

A project manager is working on a software development project. Software development will be carried out through a partnership with a vendor based on a list of initial requirements not yet completely defined.

What type of contract and project approach should the project manager consider?

Options:

A.  

Time and materials (T&M) with an agile approach

B.  

Cost reimbursable contract with a predictive approach

C.  

Fixed-price contract with a predictive approach

D.  

Memorandum of understanding (MOU) with an agile approach

Discussion 0
Questions 279

Four new teams have been formed to develop a new product. Several team members ask the project manager who will integrate the different work streams into one backlog.

What should the project manager do?

Options:

A.  

Create integration tasks and schedule an additional team meeting following the standup meeting to plan the integration.

B.  

Advise the teams to work individually and organize an integration iteration every four development sprints.

C.  

Instruct the team to use the kanban board daily to facilitate alignment of their work item list, allowing them to do their best work.

D.  

Advise the teams to collaborate with the product owner in prioritizing the stories, considering dependencies and preventing overlap.

Discussion 0
Questions 280

Due to scope changes, some of the risks identified during the initiation phase have materialized into issues. What should the project manager do next?

Options:

A.  

Submit a request to access contingency reserves and accept the changes.

B.  

Submit a change request for additional resources and accept the changes.

C.  

Ask the project sponsor to reject high-risk scope changes.

D.  

Closely monitor scope changes and implement corrective actions.

Discussion 0
Questions 281

A project manager is creating the quality management plan for deliverables with very precise requirements. The project manager is uncertain about how to create quality standards so the suppliers can show conformity when delivering the product.

Which two actions should the project manager take first? (Choose 2)

Options:

A.  

Review the conformity management plan to ensure the requirements are clearly defined.

B.  

Reference the quality management plans from old projects to determine if they apply to these deliverables.

C.  

Add a conformity team member to inspect each deliverable upon receipt from the supplier.

D.  

Evaluate industry standards of similar products to determine which apply to this project.

E.  

Ask the suppliers to create a statement of conformity when the product is delivered.

Discussion 0
Questions 282

A project manager has been asked by the human resources (HR) review team to share information about how the project team members interact, communicate, and conduct themselves to reduce the risk of conflicts and improve overall team performance.

What should the project manager do next?

Options:

A.  

Provide the HR review team with the team norms document.

B.  

Invite the HR review team to attend one of the daily standup meetings.

C.  

Discuss the resource management plan with the HR review team.

D.  

Direct the HR review team to the communications management plan.

Discussion 0
Questions 283

A project management office (PMO) is following the execution of an organization's critical project. Some of the project phases are experiencing serious delays due to an international supply chain crisis. Project team members suggested revisiting the planned project phases to maintain the project's value delivery.

What should the project manager do?

Options:

A.  

Schedule a meeting with the project sponsor to report and discuss the issue.

B.  

Update the project schedule in response to the external crisis.

C.  

Develop a contingency plan and seek alternative suppliers.

D.  

Assess and consolidate projects phases and update the project management plan.

Discussion 0
Questions 284

A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.

What should the project manager do first to get the team energized and performing efficiently?

Options:

A.  

Seek to understand the sentiments of each team member and then work with them to address their concerns.

B.  

Bring the team together on a phone call to explain the criticality of the project and the impact of schedule delays.

C.  

Contact the functional manager to request a replacement for team members who are not able to meet the schedule.

D.  

Begin holding daily meetings and ask each team member to share their status and demand that they remain on schedule.

Discussion 0
Questions 285

A project team has difficulty understanding the relationship between functional requirements and their associated benefit to the business stakeholders.

How should the project manager improve the team's understanding?

Options:

A.  

Involve team members in stakeholder analysis and engagement.

B.  

Invite all stakeholders to progress meetings to avoid ambiguity.

C.  

Ensure team members have access to a well-written requirements traceability matrix.

D.  

Engage with the project sponsor and ensure the product backlog is correct and up to date.

Discussion 0
Questions 286

At the first retrospective meeting, a developer in a newly formed team points out that frequent delays in documenting the requirement solution are impacting the workflow. The developer wants to know why the analyst is not doing their job on time. Confronting the analyst causes a conflict that quickly escalates. The analyst is certain that the documentation process is not solely their function.

What should the project manager do to resolve the conflict and prevent future conflicts as the team matures?

Options:

A.  

Facilitate a conflict discussion and find a win-win situation for both parties so that they can continue to work together.

B.  

Allocate additional key resources and document who will be held accountable for the various aspects of the team's workflow.

C.  

Clarify the role ambiguity and define resource responsibilities with the team using a responsibility assignment matrix (RAM).

D.  

Set up a group discussion after each requirement is discussed to understand the dependencies that can impact workflow.

Discussion 0
Questions 287

A company is going through a large cost-cutting initiative. Senior management requests a report on the work remaining for outstanding projects.

Which tool should the project manager use for this purpose?

Options:

A.  

Cumulative flow diagram

B.  

Earned value (EV)

C.  

Burndown chart

D.  

Forecast estimation

Discussion 0
Questions 288

During a progress review meeting, the project sponsor requests a complete revamp of the product roadmap to meet the strategic objectives based on market conditions. This change will result in a completely new product.

What should the project manager do first?

Options:

A.  

Put the current project work on hold and revisit the scope based on the impacts.

B.  

Perform a root cause analysis to assess which deliverables can be reused by the team.

C.  

Discuss with the team and implement the revisions that were requested by the sponsor.

D.  

Update the business case and seek sponsor approval on the modified project scope.

Discussion 0
Questions 289

Before kicking off a high-priority and complex project, what should the project manager do to ensure all project stakeholders are aware of their role scope as it relates to project activities?

Options:

A.  

Create a communications management plan.

B.  

Create a responsible, accountable, consulted, informed (RACI) chart.

C.  

Develop a kanban board.

D.  

Send a copy of the project charter to all project stakeholders.

Discussion 0
Questions 290

Negotiations are underway to secure an agreement with a critical supplier for the project. The negotiation situation has become contentious as it is becoming apparent that both parties will not receive everything they want and that a compromise might be necessary to avoid project delays, cost overruns, and damage to reputations.

What should the project manager do to help ensure a successful outcome for the project?

Options:

A.  

Collaborate with stakeholders to complete an analysis of priorities with ranked objectives.

B.  

Withhold from revealing the priorities and objectives until midway through negotiations.

C.  

Begin the negotiation process with predetermined objectives to guide the discussions.

D.  

Adjust priorities and objectives based on real-time developments during the negotiation process.

Discussion 0
Questions 291

A project is late due to a large number of scope changes. This was raised as a risk in the risk register during the initiation phase. The team is afraid that they will be blamed in case of failure and recommends that the project manager ask for an extension.

What should the project manager do first?

Options:

A.  

Ask the sponsor for their advice on the way forward.

B.  

Ask the team to document the impact of the risk in detail.

C.  

Refer to the risk register and follow the mitigation plan.

D.  

Refer to the change log and ensure that changes are documented.

Discussion 0
Questions 292

A project manager is leading a team and wants each team member to produce their deliverables and be held accountable for the work product. What should the project manager do first?

Options:

A.  

Engage with each project team member to explain the individual consequences of late delivery.

B.  

Establish a daily standup meeting where each project team member reports their progress.

C.  

Create a plan of action and milestones (POAM) to detail the deliverables for each project team member.

D.  

Empower each project team member with ownership of a particular aspect of the project.

Discussion 0
Questions 293

As part of planning activities for a new project, the project manager must develop a budget that encompasses the full project scope. What should the project manager do to build the project budget?

Options:

A.  

Reference the work breakdown structure (WBS) and project schedule to estimate costs associated with each WBS element.

B.  

Schedule a working session with the project sponsor to review the project charter and estimate the cost per project phase.

C.  

Review historical project files and lessons learned to identify a similar project and adapt the budget used in the historical project.

D.  

Ask key project stakeholders to estimate the cost of delivering the project, then calculate an average that can be used for the budget.

Discussion 0
Questions 294

A project manager coordinates several projects in one program. Each project concerns a different country, has a different sponsor, and has specific business priorities. The resources are shared among the projects. The project manager anticipates this could result in delays and/or conflicts that will affect the program outcomes.

What should the project manager do to prevent such a situation?

Options:

A.  

Review all project schedules and add a 3-month time period to each to cover such a risk and ensure there will be no delay that could affect the program.

B.  

Organize regular meetings to identify risks related to the projects and program, assess them, and define action plans when needed to mitigate the risks.

C.  

Ask each project manager to write a detailed weekly report listing all the activities, what was achieved, what needs to be done, and the identified risks.

D.  

Ask the project managers to work on their own schedules independently of one another and aggregate these schedules to present at the monthly steering committee meeting.

Discussion 0
Questions 295

A project manager with global teams is managing a project that is progressing as expected. However, recently the project manager has learned of some team members missing the daily meetings. After investigating the issue, the project manager realizes different time zones is the main cause of the issue.

What should the project manager do next?

Options:

A.  

Schedule a team-building workshop involving all teams to support better communication.

B.  

Schedule a meeting and ask all teams to sort the issues and move ahead with full participation.

C.  

Ask everyone to only invite team members in different parts of the world as necessary.

D.  

Share the time-overlap schedule with the team to make meeting scheduling convenient.

Discussion 0
Questions 296

A project manager is working on a project that is using a hybrid approach. One key input for the deliverable will be from the outcome of another project that is using an agile approach.

What should the project manager do next?

Options:

A.  

Ask the other project manager to change the delivery methodology.

B.  

Request that the other project manager develop a work breakdown structure (WBS).

C.  

Participate in the other project's daily standup meetings.

D.  

Align with the other project manager's high-level project time lines.

Discussion 0
Questions 297

A multinational company is launching a company-wide digital transformation project that covers all of its regions and business lines. The project is expected to go through five phases and finish in 2 years. The project manager schedules a kick-off meeting.

What should the project manager do next?

Options:

A.  

Ensure there is enough budget to mandate all team members to fly to corporate headquarters for the kick-off meeting.

B.  

Consider using digital or virtual tools to conduct the kick-off meeting to minimize geographic boundaries.

C.  

Document the kick-off meeting and close out the planning phase after the meeting is held.

D.  

Limit to one kick-off meeting in the project's first phase in order to control the budget.

Discussion 0
Questions 298

A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.

What should the project manager do?

Options:

A.  

Send out daily emails with the project status and task lists to all team members.

B.  

Meet daily with the project team and include a monthly report on the risks and issues.

C.  

Distribute a project newsletter that includes any project changes and required project information.

D.  

Encourage collaboration on a daily basis, facilitating different communication channels.

Discussion 0
Questions 299

An IT project manager for a project that is 50% complete teams that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.

How should the project manager improve team dynamics?

Options:

A.  

Require that all team members be physically present for the weekly project review.

B.  

Offer the team member an incentive to stay until the end of the project.

C.  

Replace the team member with someone who has similar qualifications and is located closer.

D.  

Set up a weekly video conference to monitor the progress of the team member's work.

Discussion 0
Questions 300

A project manager wants to ensure that the project acceptance criteria are met for all project deliverables. What should the project manager do to accomplish this?

Options:

A.  

Schedule regular meetings with project stakeholders to make sure they are satisfied.

B.  

Include project stakeholder expectations and needs while creating project acceptance criteria.

C.  

Create a statement of work (SOW) and ensure it remains unchanged during the project life cycle.

D.  

Discuss project acceptance criteria with the project sponsor before the execution phase.

Discussion 0
Questions 301

A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.

When will the project manager be able to provide the requested information?

Options:

A.  

During the planning phase, when processes for scope definition and activity duration and sequencing will be performed

B.  

As soon as possible, as project delays can be significantly avoided when a schedule is developed early

C.  

Close to the end of the project, as the forecasts will be more accurate and most risks will already be mitigated

D.  

In the initiation process, as it happens concurrently with the project contract and project charter creation

Discussion 0
Questions 302

A project manager is assigned to an organizational transformation project. The company typically defines individual performance plans at the beginning of the year, and functional managers conduct feedback reviews at the end of the year. The transformation project team members are concerned that the work they are doing for this project is not aligned with the work included in their individual performance plan for the year.

What should the project manager do?

Options:

A.  

Meet with the functional managers to align the expected frequency and results reporting for the team members.

B.  

Provide performance feedback to the learn members' functional managers at the end of the year.

C.  

Assure team members that this project is a high priority for the company and they will be evaluated accordingly.

D.  

Request to be made responsible for the performance plans of those on this project team

Discussion 0
Questions 303

A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically

last 45 minutes with many misunderstandings due to language barriers.

How should the project manager resolve this issue for the next iteration?

Options:

A.  

Transfer half of the backlog items to the next iteration to allow more time to complete the meetings.

B.  

Extend the meeting to 1 hour and request that all of the participants bring up all of the issues.

C.  

Instruct the meeting participants to speak only about blockers during the meeting.

D.  

Train the three team leads to conduct a local meeting, then run an overall status meeting.

Discussion 0
Questions 304

A project manager is leading a multiyear project that involves internal and external stakeholders. As the project manager begins to gather requirements, additional business stakeholders express interest in being involved.

Which three actions should the project manager take to ensure proper stakeholder involvement? (Choose three)

Options:

A.  

Prioritize stakeholders based on the project phase and need.

B.  

Develop a stakeholder impact influence matrix to determine the level of engagement

C.  

Perform a stakeholder assessment to align with the project objectives.

D.  

Include all stakeholders in the stakeholder engagement plan and provide the same level of communication.

E.  

Classify and rank stakeholders based on their positions in the organization.

Discussion 0
Questions 305

In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product ft quality. What should the project

manager do?

Options:

A.  

Request the team to work more for on-time delivery.

B.  

Request the team to focus on doing better planning.

C.  

Request the replacement of certain team members.

D.  

Request management for a high-performing team.

Discussion 0
Questions 306

A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.

What should the project manager do?

Options:

A.  

Adopt the same timeframe as the closed project for the current project.

B.  

inform the sponsor that the activity list is not adequate for creating a schedule baseline.

C.  

Create a draft schedule based on the activity list and the historical data from the closed project.

D.  

Evaluate each activity duration and build a new project schedule.

Discussion 0
Questions 307

A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concemed about the team not receiving direct communications from this stakeholder.

Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two)

Options:

A.  

Schedule regular meetings with the key stakeholder to provide updates and receive feedback,

B.  

Share weekly status reports with detailed information about the project and team performance.

C.  

Submit performance reports and task assignments to keep the stakeholder informed.

D.  

Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders.

E.  

Provide training to the team on emotional intelligence and status reporting techniques.

Discussion 0
Questions 308

A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk

materialized and the project time line had to be extended by 2 months.

Which two actions should the project manager take? (Choose two)

Options:

A.  

Ask the team member to work overtime to make up the time lost so that the project schedule is not impacted.

B.  

Analyze the impact of the issue and submit a change request to update the project schedule.

C.  

Inform the project sponsor that the risk has materialized and request that the project budget be increased.

D.  

Extend the project deadline and update the project schedule to reflect the delay.

E.  

Log it in the risk register and work with the relevant owner to implement the mitigation action plan.

Discussion 0
Questions 309

An organization initiated a project in a complex program. The project lead notices that the team is demotivated because the current project framework implemented by the project management office (PMO) is not compatible with agile delivery

What should the project lead do?

Options:

A.  

Escalate the problem to the product owner.

B.  

Ask the PMO to review the framework

C.  

Request the PMO to define a new framework.

D.  

Plan a brainstorming session with the project team

Discussion 0
Questions 310

Midway into a project, the project manager is concerned with the lack of responsiveness from a vendor. What should the project manager do to

ensure the project is delivered successfully?

Options:

A.  

Ask the vendor to communicate via the established channels.

B.  

Invite the vendor to a meeting to discuss the concerns.

C.  

Escalate the vendor's lack of responsiveness to the project sponsor.

D.  

Proceed with other tasks while awaiting a response from the vendor.

Discussion 0
Questions 311

A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule.

What should be me project manager's response?

Options:

A.  

Sprint plan and product roadmap

B.  

Product roadmap and sprint backlog

C.  

Product backlog and scrum board

D.  

Sprint backlog and scrum board

Discussion 0
Questions 312

In an agile project, the learn planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?

Options:

A.  

30/40

B.  

40/70

C.  

30/70

D.  

40/30

Discussion 0
Questions 313

An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience

performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.

How should this situation be handled?

Options:

A.  

Use a robotics vendor company to develop the interfaces so the team will not be held back by a lack of expertise in this type of work,

B.  

Add an experienced professional to the team to reinforce knowledge sharing and help grow team expertise in the new product

C.  

Create a separate team with experienced members who understand the technology and split the product backlog according to team specialization.

D.  

Hire a consulting company to address the robotic interface questions, when necessary, and to help avoid delays and quality issues.

Discussion 0
Questions 314

A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday

morning. Due to an unexpected issue, 50% of the team has to work from home. The bank's management directed the team not to have in-person daily standups. Various team members are complaining about this, stating that there is a lack of information sharing among the team

What should the project manager do?

Options:

A.  

Postpone the daily standups and ask the team members to update the project manager daily via messaging.

B.  

Hold virtual daily standups each workday morning and use collaboration tools to manage project updates.

C.  

Delegate authority to the team members and ask them to submit weekly status reports instead.

D.  

Ask senior management for permission to hold in-person team meetings once each week.

Discussion 0
Questions 315

A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.

What should the project manager do?

Options:

A.  

Review the requirements on a weekly basis.

B.  

Implement a requirements traceability matrix.

C.  

Add the requirements to the project charter.

D.  

Understand the project management plan.

Discussion 0
Questions 316

A technology project is delivering new functionality on a new platform. Several team resources are starting to train their teams, but they are asking questions about the training that the project will provide.

What should the project manager's first action be?

Options:

A.  

Indicate that on the new technology is the functional manager's responsibility.

B.  

Review the project charter to determine if the training is in scope and, if not, put in a change request.

C.  

Consult with the organizational change management specialist as to what the training plan includes.

D.  

Document the skill requirements for the product to determine what training is needed.

Discussion 0
Questions 317

A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.

How should the project manager establish the delivery model for this project?

Options:

A.  

Organize the project into multiple subsets based on business functions and deliver each subset as a component of the final product.

B.  

Reestablish the project as a program with multiple small projects, as each project will be delivered as a product of its own.

C.  

Communicate the latest status to the steering committee and provide a demo of the features completed.

D.  

Schedule routine demos on features completed and deliver a single product once all features are completed.

Discussion 0
Questions 318

The project manager is reviewing a project's progress and notices that one of the risks has become an issue. What should the project manager do to address the situation?

Options:

A.  

Schedule a high-priority meeting with the project stakeholders to discuss the issue.

B.  

Initiate a change request to obtain additional funds from the management reserve.

C.  

Meet with the project team and customer to brainstorm about potential solutions.

D.  

Collaborate with the relevant stakeholders on implementing the risk response plan.

Discussion 0
Questions 319

While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.

How should the project manager handle this situation?

Options:

A.  

Suggest that the team member ignore the disruptive team member and focus only on the work.

B.  

Encourage both team members to meet as soon as possible and resolve the problem

C.  

Monitor the situation for a few weeks to determine if the disruptive team member's attitude changes.

D.  

Report the disruptive team member to the human resource (HR) department.

Discussion 0
Questions 320

A project manager is working on a time and materials (T&M) project using a hybrid approach. The milestones and outcomes are defined for the first 6 months with

incremental releases every month. After the first 2 months, the client communicates their dissatisfaction with the results and asks to change the course of the project. The project manager held a face-to-face meeting with the client and now has a better understanding of the newly desired milestones and outcomes.

What should the project manager do first?

Options:

A.  

Forward the client's request to management as a change request to get formal approval.

B.  

Document the information in the meeting minutes and share it with the project stakeholders.

C.  

Draft a contract change with the desired scope changes and send it to the client for approval.

D.  

Finish the current monthly release as it was planned and replan for the future months.

Discussion 0
Questions 321

A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional

managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.

What should the project manager do?

Options:

A.  

Discuss the testing requirements with a test engineer and negotiate the best approach to test the newly developed software.

B.  

Meet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained.

C.  

Request a meeting with the sponsor to change the scope to allow the development team to conduct testing.

D.  

Meet with a procurement specialist to negotiate with a company that specializes in software testing to test the software.

Discussion 0
Questions 322

A project manager is managing an internal project with a tight budget and schedule. While executing the project, the project manager realizes that

some stakeholders are working against the success targets of the project.

What should the project manager do to ensure successful project delivery? (Choose two)

Options:

A.  

Update the project stakeholder analysis and methods to satisfy the stakeholders’ requirements.

B.  

Escalate the issue to the functional manager and ask for support.

C.  

Involve all stakeholders in the project by distributing status reports.

D.  

Focus on the supportive stakeholders and minimize involvement of unsupportive stakeholders.

E.  

Engage all stakeholders in the project including the unsupportive stakeholders.

Discussion 0
Questions 323

In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in

conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?

Options:

A.  

Anticipate, alert, and follow the risk management process.

B.  

Detect, track, and follow the issue management process.

C.  

Promote, inspire, and follow the stakeholder engagement process.

D.  

Discuss, educate, and follow the communications management process.

Discussion 0
Questions 324

A project manager is closing a project and preparing to hand it over to the operations team. During handover, a delayed invoice was submitted with a higher-than-planned

cost against the project work. Consequently, project handover was delayed and the project's reported completion costs were increased.

What should the project manager have done to avoid this situation?

Options:

A.  

Captured and reviewed all of the project work and related costs regularly

B.  

Notified all vendors about the invoicing and nonpayment deadlines

C.  

Reviewed the total committed cost against the cost invoiced at project closing

D.  

Involved the finance team and discussed the issue with the vendor

Discussion 0
Questions 325

A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce

the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on 20 December

might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays.

What should the project manager do about this risk?

Options:

A.  

Update the risk register and take advantage of the opportunity.

B.  

Review the supplier's contract to understand the terms of sale.

C.  

Accept the risk and update the risk register.

D.  

Insist that the supplier deliver the goods on the agreed date.

Discussion 0
Questions 326

A team needs to follow defined cybersecurity compliance that is mandatory for a customer project. What should the project manager do to monitor compliance in the

project?

Options:

A.  

Confer with team members.

B.  

Review with security experts.

C.  

Schedule regular project audits.

D.  

Discuss with the customer.

Discussion 0
Questions 327

An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?

Options:

A.  

Meet with the project team to develop a proper resolution to the issue.

B.  

Update the project artifacts to reflect the new deadlines reported.

C.  

Request approval from the project sponsor to add more resources,

D.  

Prepare documentation to explain the issue and communicate accordingly.

Discussion 0
Questions 328

During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager

react to ensure the project remains successful?

Options:

A.  

Focus the discussion on recovery and ways to get back on track.

B.  

Act in a way to highlight the criticality of the situation.

C.  

Punish the team member for providing negative data that will affect the team's morale.

D.  

Thank the team member for raising this issue, log it, and move on to the next topic.

Discussion 0
Questions 329

A new team member joins an agile team. In a previous role, this team member was a subject matter expert (SME). This team member often directs the team on how to solve problems based on previous experience.

What should the project manager do first?

Options:

A.  

Update the definition of done (DoD) to include a review by the new team member to ensure the best outcome of each deliverable.

B.  

Ask the new team member to create a wiki that the rest of the team can reference in the future for all questions.

C.  

Ask the new team member to size all the stories in the backlog so that the rest of the team can focus on delivery.

D.  

Let the new team member know that even if they know the answer, it is better to give the team a chance to solve their own problems

Discussion 0
Questions 330

During project planning, a development team is assigned an agreed-upon work package to determine the appropriate pattern for integrating a new service with a legacy system. The lead developer has requested a meeting with the project manager and Is looking for direction as to which technology to select.

How should the project manager help guide the lead developer?

Options:

A.  

Advise the lead developer and team to consult with the project architect and for their development team leader.

B.  

Reassign this work package to another area given the lead developer's concerns,

C.  

Direct the lead developer to conduct a weighted evaluation of all products and solutions.

D.  

Listen to the concerns and suggest that the lead developer and the team be empowered to recommend the best approach.

Discussion 0
Questions 331

A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager

expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project

manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.

What engagement model should the project manager use for the technical architect role to ensure project success?

Options:

A.  

Hire a new technical architect who would be solely dedicated to the current project.

B.  

Share the existing technical architect so they can be allocated to the current project and other projects.

C.  

Hire a new technical architect who would be shared between the current project and other projects.

D.  

Assign the existing technical architect to solely be dedicated to the current project.

Discussion 0
Questions 332

A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.

Which action should the project manager take to address the sponsor's request?

Options:

A.  

Work with the organization's real estate department and reach out to the local government to identify the best location for the store.

B.  

Work with the local government to build the profiles of employees that will be working in the store.

C.  

Work with the organization's legal department to identify local regulations to ensure project compliance.

D.  

Work with the organization's project management office (PMO) to build a project team of residents located in the city.

Discussion 0
Questions 333

During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.

What should the project manager do next?

Options:

A.  

Escalate the situation again to the project sponsor.

B.  

Review this obstacle during the daily standup meeting.

C.  

Request a new resource to execute the activities.

D.  

Provide feedback to the resource at the sprint review.

Discussion 0
Questions 334

A project manager receives an email from a customer saying that they do not want to keep working with one of the project team members. The customer does not provide

any reasons for this sentiment. The project manager is concerned because this project team member is highly skilled and experienced and is key in one of the main project deliverables.

What should the project manager do to ease the situation?

Options:

A.  

Talk to the customer and project team member separately to assess the issue and decide on the next steps.

B.  

Remove the project team member immediately and assign the pending activities to other team members.

C.  

Tell the customer that they do not have the authority to remove project team members.

D.  

Ask the project team member to call the customer to apologize for their behavior.

Discussion 0
Questions 335

During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project

manager is not sure if some of the project deliverables will be fully compliant with the new requirements.

What should the project manager do?

Options:

A.  

Stop the project until someone in the organization can identify all the new requirements and how they impact the project.

B.  

Request the project management office (PMO) to assign a dedicated resource to monitor the external environment to enable more reactiontime.

C.  

Agree with the project team that the new requirements will be applied to the next project, not the one already under development.

D.  

Evaluate the consequences of noncompliance with relevant stakeholders and update the risk register with agreed actions.

Discussion 0
Questions 336

A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.

What should the project manager do?

Options:

A.  

Update the project management plan and adjust the project budget with this change request.

B.  

Raise a change request to the change control board (CCB) and inform the project sponsor about the change.

C.  

Ask the key stakeholder to take the lead in handling the request since they are more knowledgeable.

D.  

Request a meeting with the stakeholders and their team members to inform them about this change.

Discussion 0
Questions 337

A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the opinions of the product owner seriously and mostly relies on the project manager's opinion.

What should the project manager do?

Options:

A.  

Assume the role of the product owner while the product owner gets familiar with the product.

B.  

Schedule time to share insights with the new product owner about the product and project information.

C.  

Work with the project management office (PMO) manager to generate an onboarding plan for the new product owner.

D.  

Organize a team-building activity and ask the team to respect the opinions of the new product owner.

Discussion 0
Questions 338

Two teams are engaged on a global project which uses a follow-the-sun approach in order to speed up delivery. After the first release, many issues were identified on the product, which could easily have been avoided with better communication.

What should the project manager do?

Options:

A.  

Improve the videoconferencing system to provide better availability and quality in order to increase communication.

B.  

Have team ambassadors from each location travel to the other in order to facilitate communication and minimize issues.

C.  

Facilitate a meeting with both teams so that they can agree on the issues and propose solutions that work for both teams.

D.  

Move working windows so that team members can have increased overlap for the handover of status and issues to their counterparts.

Discussion 0
Questions 339

An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.

What should the project manager do to manage business concerns and expectations before starting the project?

Options:

A.  

Meet with the project finance team to measure market variations and product impact.

B.  

Direct the project team to estimate user stories in greater detail.

C.  

Ask the product owner to prioritize the backlog items based on the return on investment (ROI).

D.  

Request that the project team develop a release plan and roadmap for the project.

Discussion 0
Questions 340

A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is

seeking the project manager's recommendation on how to approach this request.

What should the project manager do to help the product owner?

Options:

A.  

Provide an overview of the completed functionalities and release plan, and capture expectations for future stakeholder involvement.

B.  

Invite the product owner to future demonstrations where they can provide feedback.

C.  

Provide access to the latest user acceptance test (UAT) environment so they can see the solution.

D.  

Remind the product owner of stakeholder accountability, and ask the product owner to determine the appropriate next steps.

Discussion 0
Questions 341

A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?

Options:

A.  

Retrieve the documentation that shows the resource allocation.

B.  

Examine ways of modifying the scope of the project.

C.  

Adopt a resource leveling procedure to level the resources.

D.  

Perform an impact analysis to see the effect on the project.

Discussion 0
Questions 342

A project manager is leading a project that has been in execution for 1 year. An experienced team member is performing well, but often disagrees with the project manager and refuses to implement their decisions. Part of the team supports the team member's defiance, while the other team members do not.

What should the project manager do?

Options:

A.  

Conduct a performance review and define and document the goals for the team member.

B.  

Clarify decisions and request that the project team follows the project manager's decisions.

C.  

Understand what the team member wants and find possible opportunities to address it.

D.  

Remove existing ground rules and create new ground rules that support the project manager.

Discussion 0
Questions 343

A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist

from the team was average.

What should the project manager do to help the new compliance specialist improve?

Options:

A.  

Escalate this situation to the manager of the area for a possible solution.

B.  

Provide time for the specialist to adjust to the pace of the project.

C.  

Coordinate a one-to-one meeting with the specialist to assess the situation.

D.  

Contact the human resources (HR) manager about the team's feedback.

Discussion 0
Questions 344

After assigning tasks to a project team, a project manager discovers that some team members are uncomfortable. Same team members are having 4 difficult time understanding their assigned tasks, whereas other team members are challenging the schedule based on that allocation to the project.

Which phase of the Tuckman ladder of team formation is occurring?

Options:

A.  

Forming

B.  

Mourning

C.  

Storming

D.  

Norming

Discussion 0
Questions 345

A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team

to collaborate effectively.

Which three actions should the project manager take to accomplish this goal? (Choose three)

Options:

A.  

Require the team to have daily mandatory meetings with the project management office (PMO).

B.  

Recommend the use of formal written documentation in all project communications.

C.  

Review the communications strategy with the team regularly with a view for continuous improvement.

D.  

Send out a survey to review the preferred method, time frequency for communications.

E.  

Compile a communications management plan with input from all stakeholders and distribute for review and approval.

Discussion 0
Questions 346

A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.

What should the project manager do?

Options:

A.  

Assign a development team member to have the responsibility of managing dependencies.

B.  

Suggest that each project develops a high-level plan to monitor the dependencies

C.  

Recommend switching to a predictive approach to have detailed plans to manage the dependencies

D.  

Continue the project with 2-week iterations as dependencies will be managed individually

Discussion 0
Questions 347

A project stakeholder has left the company. The new stakeholder is a family member of one of the team members. This stakeholder does not attend meetings. The project manager finds out that the stakeholder has been asking the family member for project updates.

What should the project manager do?

Options:

A.  

Design an updated status report.

B.  

Request a meeting with the stakeholder.

C.  

Escalate this to the project sponsor.

D.  

Forward the project status reports.

Discussion 0
Questions 348

During a retrospective, one of the team members reports that a functional manager wants to be involved in task allocation. What should the project manager do?

Options:

A.  

Inform the functional manager that self-organization includes task allocation.

B.  

Confirm with the team members that the functional manager is responsible for the delivery.

C.  

Ask the product owner to clarify the roles and responsibilities of the project team.

D.  

Inform the functional manager that task allocation is the responsibility of the product owner.

Discussion 0
Questions 349

A project team is executing a large regulatory project comprised of a multitude of internal and external stakeholders. An initial impact analysis revealed several systems, including an enhancement to existing modules as well as new builds. After completion of the initial design workshop, the team conducted a brainstorming session to better understand the types of likely users.

Which technique will best serve this purpose?

Options:

A.  

Personas

B.  

Power influence grid

C.  

Power user grid

D.  

Salience model

Discussion 0
Questions 350

A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee,

* Actual progress = 2 units

* Planned progress = 3 units

* Actual cost (AC) = 2 units

* Budgeted cost = 3 units

What statement should the project manager make to the project steering committee?

Options:

A.  

The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities.

B.  

The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken.

C.  

The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted.

D.  

The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings,

Discussion 0
Questions 351

Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information

should the project manager provide so that senior management can get a broader view of the project?

Options:

A.  

Risk register information

B.  

Higher-level activities completed

C.  

Milestones status report

D.  

Resource breakdown structure (RBS)

Discussion 0
Questions 352

A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed

for the product.

What should the project manager do to continue with the delivery plan and return to the expected velocity?

Options:

A.  

Use retrospectives to better understand the new technology's impact on the schedule, map the skill gaps, and adjust the team accordingly.

B.  

Reevaluate the backlog by looking for high-value/low-effort items, and negotiate a new minimum viable product (MVP) strategy with key stakeholders.

C.  

Seek sponsor approval for additional funding to hire new team members, increasing the capacity of the team and compensating for the productivity lost with the new technology.

D.  

Replace poorly performing team members with more experienced members, setting an example of accountability for the team.

Discussion 0
Questions 353

A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time.

Match the roles for the team on the left to their corresponding responsibilities on the right.

Options:

Discussion 0
Questions 354

A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved.

How should the project manager proceed?

Options:

A.  

Proceed with both the prefeasibility and feasibility studies in parallel while waiting for (he final approvals

B.  

Include the feasibility activities in the prefeasibility study and apply for a change of scope and budget.

C.  

Obtain approval to proceed with the feasibility study as a parallel activity while the prefeasibility study is approved

D.  

Secure approval of the prefeasibility study before proceeding with the feasibility activities.

Discussion 0
Questions 355

A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.

Options:

Discussion 0
Questions 356

A project manager is assigned to a project that is in the execution phase that has different types of stakeholders. Some of the stakeholders are very interested in the project, whereas other do not show the same level of interest.

What should the project manager do to assure the project finishes correctly?

Options:

A.  

Look at the stakeholder assessment matrix to find stakeholders' interests and make updates if necessary.

B.  

Invite the most interested stakeholders to risk assessment sessions and assure the less interested stakeholders agree with the requirements.

C.  

Review the user person definitions to find the interests of the stakeholders and make updates if necessary.

D.  

Create a stakeholder assessment plan to manage stakeholder engagement and took at stakeholders' approvals.

Discussion 0
Questions 357

A project manager's new employer decided to use an agile delivery approach to implement a new accounting system. The chief financial officer (CFO), who is also the

project sponsor, is committed to a new way of working but does not have experience as a product owner. The project manager's background includes a couple of years’

experience as an agile practitioner working as a scrum master.

What should the project manager do at the start of the project?

Options:

A.  

Collaborate with the development team to help the project sponsor acquire the relevant skills.

B.  

Assume the product owner role until the project sponsor is ready to take over the product owner role.

C.  

Delay the build of the system until the project sponsor is ready to take over the product owner role.

D.  

Work with and assist the project sponsor in building and prioritizing the product backlog.

Discussion 0
Questions 358

A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses to approve the proposed project plan.

What should the project manager do to gain an understanding of the cause for the resource's refusal?

Options:

A.  

Speak directly with the resource.

B.  

Communicate with their supervisor.

C.  

Organize a team meeting.

D.  

Speak with their colleague.

Discussion 0
Questions 359

A CEO of a general contracting company urgently asks the project manager to sign up two project team members to participate in a specific training course. Halfway

through the training, both team members complain that the training is too difficult, above their experience level, and that the material does not align with their tasks.

What should the project manager have done to prevent this situation?

Options:

A.  

Communicated with the two team members that the purpose of the training is to provide material that might be useful to them in the future

B.  

Sent an immediate request to the human resources (HR) department to replace the current team members with higher skilled candidates

C.  

Observed and assessed the competencies and skills of the team members and analyzed the training material beforehand

D.  

Planned a training to follow the specific course to bring the two team members to the required experience level

Discussion 0
Questions 360

An agile project to provide a material information system has started. During the kick-off meeting, the team realizes that the stakeholders require a solution in 2 months, but it will take at least 4 months to deliver the entire project.

Who should the project manager contact to help the team accelerate the delivery?

Options:

A.  

The human resources (HR) department—to ask for more resources to add to the project team.

B.  

The product owner and the stakeholders—to prioritize the requirements in the product backlog.

C.  

The team—to have them increase their velocity to accomplish the stakeholders requirements.

D.  

The stakeholders—to have them prioritize the requirements in the product backlog.

Discussion 0
Questions 361

A project manager is leading a hybrid project for the development of denial equipment with live team members A dentist, who is also one of the major investors attends a sprint review meeting and raises questions and doubt about the concept and expected performance of the equipment

What should the project manager do?

Options:

A.  

invite the investor to a sprint retrospective meeting to discuss the improvements of the concept and expected performance of the equipment with the team

B.  

invite the protect sponsor to the sprint review meeting and nave a QSA session about the concept and expected performance of the equipment

C.  

invite the product owner and the team to a discussion about the concept and expected performance of the equipment

D.  

invite the investor to the design review meeting to present the concept and expected performance of the equipment and include a QSA session m the meeting

Discussion 0
Questions 362

A project manager is managing a project that has a new sponsor who is cutting the budget As a servant leader how should the project manager handle the budget cuts with the team?

Options:

A.  

Notify the project sponsor that the budget reduction will require a schedule slip and scope reduction.

B.  

Inform each team member that they must release a portion of their budget but must remain on schedule with no change to the scope

C.  

Meet with the schedule coordinator and financial analyst to tell them which budget lines to reduce and where to release slack

D.  

Collaborate with the team to assess the impact of the change on the project and recommend an updated project plan

Discussion 0
Questions 363

A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety

approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.

What is the appropriate flow for product development?

Options:

A.  

Complete development with all functionalities in perfect condition prior to demonstrating to stakeholders to ensure a great first impression.

B.  

Complete development for each sprint and demonstrate the product increment to internal stakeholders and the government, without engaging other externalstakeholders.

C.  

Complete development for the must-have functionalities only prior to demonstration in order to fail fast and get early feedback.

D.  

Complete development for must-have functionalities only and demonstrate it to a focus group, but wait until all development is complete to demonstrate it to thegovernment.

Discussion 0
Questions 364

In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The

discussion has intensified and the team members are not able to agree.

What should the project manager do next?

Options:

A.  

Remove one of the team members from the project to improve team dynamics.

B.  

Make a decision based on expert judgment as a project manager.

C.  

Consider the view of each team member about the issue in order to reach consensus.

D.  

Remove both team members since they are not productively adding to the team.

Discussion 0
Questions 365

A project manager is assigned to a new project team that has several stakeholders who can have significant influence over the project outcomes.

The project manager categorized the stakeholders into four different groups and wants to define the communication strategy.

How should the project manager handle communication?

Options:

A.  

Utilize a uniform communication structure across all groups.

B.  

Define and direct communication to influential stakeholders.

C.  

Describe the four groups in the project stakeholder matrix.

D.  

Develop and define a communication strategy for stakeholders.

Discussion 0
Questions 366

A project team member is struggling to deliver an assigned task. In a team meeting, the project manager determines that there are other members

on the team who have more experience with similar tasks.

What should the project manager do?

Options:

A.  

Ask one of the more experienced team members to support the team member with the task.

B.  

Reassign the task to one of the more experienced project team members for a faster completion of the assigned task.

C.  

Ask the experienced team members to produce a manual on how to complete the task.

D.  

Inform the project management office (PMO) of the issue and request a replacement for the less experienced team member.

Discussion 0
Questions 367

During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.

A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.

How should the new project manager address these concerns?

Options:

A.  

Allow the agile team to decide what they are able to deliver in each iteration

B.  

Ask the team for additional feedback and add tasks to the task board,

C.  

Hold a brainstorming session to identify the root cause of the complaints.

D.  

Document the customer's complaints and critical issues in the issue log.

Discussion 0
Questions 368

A technical team for a project is managed by the lead who was recently promoted to this role. Inside the team, a mature and experienced engineer is constantly questioning the actions of the team lead and is currently ignoring part of the team lead's decisions. The team lead asks the project manager for help.

What should the project manager do?

Options:

A.  

Suggest to the team lead how to deal with this team member and discuss the situation with the engineer.

B.  

Organize a meeting with all of the project stakeholders and inform them about the new risk and its impact on the project.

C.  

Organize a meeting with the project team and discuss the situation and its impact on project delivery.

D.  

Suggest to the engineer how to work efficiently with the lead and discuss the situation with the lead's functional manager.

Discussion 0
Questions 369

A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the

project manager ensure that the needs of stakeholders are consistently met?

Options:

A.  

Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.

B.  

Add more iterative techniques to improve stakeholder learning.

C.  

Identify all the critical stakeholders during the project initiation.

D.  

Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.

Discussion 0
Questions 370

A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing.

What should the project manager do to create a positive environment?

Options:

A.  

Establish the team ground rules and share them with the team for strict adherence.

B.  

Copy the ground rules established by another project and provide them to the teams.

C.  

Extract the organization's policies and processes, customize them, and give them to the teams to adhere to.

D.  

Help the teams in establishing and adhering to their ground rules and revisit after regular intervals.

Discussion 0
Questions 371

A project manager is overseeing a project as part of a program geared toward a major technology disruption. The team is comprised of brilliant young professionals who have worked on different projects for the organization in the past. However, the team complained that they previously experienced a lack of direction during project execution and are a traid of the same issue in this project.

Which two actions should the project manager take to ensure that this issue does not occur in this project? (Choose two)

Options:

A.  

Keep the team engaged and focused on the project's direction.

B.  

Encourage the team to do a brainstorming session and provide a mitigation plan.

C.  

Focus on the resource management plan and track project progress,

D.  

Set a clear vision for the project and ensure it is visible to all stakeholders.

E.  

Organize a team-bonding activity and invite an external manager to speak to the team.

Discussion 0
Questions 372

Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.

What should the project manager have done to avoid this situation?

Options:

A.  

Ensured that communications were sent to all stakeholders when requirements change

B.  

Ensured procurement contracts were able be canceled when situations like this arise

C.  

Ensured project requirements were validated and communicated with the procurement team

D.  

Ensured changing stakeholder needs and requests were properly monitored

Discussion 0
Questions 373

During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the

required IT system. What should the project manager do?

Options:

A.  

Fast track this dependency to avoid delaying the project.

B.  

Perform Integrated Change Control.

C.  

Include the dependency in the project schedule.

D.  

Ask IT to prioritize the needed system to meet the schedule.

Discussion 0
Questions 374

A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.

Which risk management process should be performed?

Options:

A.  

Plan Risk Responses, to outline the possible options to bypass the system performance issue

B.  

Perform Qualitative Risk Analysis, to assess the extent of the system performance impact

C.  

Monitor Risks, to install system performance monitoring tools and update the risk register

D.  

Perform Quantitative Risk Analysis, to outline the details of the system performance issues

Discussion 0
Questions 375

In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the project vulnerable.

What should the project manager do?

Options:

A.  

Ensure the activities of this team member are distributed across the project team.

B.  

Assess a mechanism for knowledge transfer among the team members.

C.  

Motivate the team member to stay by providing them with incentives.

D.  

Ask human resources (HR) to counsel the team member to balance the workload.

Discussion 0
Questions 376

A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a

dependency missing between:

+ Test the product

+ Release to customer

According to the quality management plan, the product must be tested before being released.

How should the project manager enter this dependency?

Options:

A.  

Finish to start

B.  

Start to start

C.  

Start to finish

Discussion 0
Questions 377

After an executive-level reorganization, the new project sponsor is not keen on continuing with the project. What should the project manager do?

Options:

A.  

Ask management to replace the new sponsor with the previous sponsor.

B.  

Request the previous sponsor to discuss changes with the project team.

C.  

Explore ways to share the project vision and outcome with the new sponsor.

D.  

Find ways to bypass the new sponsor and reach management for support.

Discussion 0
Questions 378

During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.

What should the project manager do next?

Options:

A.  

Incorporate the changes in the last sprint before the first release.

B.  

Call for an internal meeting to discuss the changes and their value.

C.  

Ask the product owner to prioritize the backlog with the project team.

D.  

Request the scrum team to prioritize the product backlog.

Discussion 0
Questions 379

The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team

Which two actions should the project manager take? (Choose two)

Options:

A.  

Review the issue with project sponsor and submit a change request

B.  

Report the issue to the product manager and business segments

C.  

Analyze the business benefits criteria and assumptions

D.  

Discuss the issue with the operations team to assess expense overruns

E.  

Schedule a project review meeting to analyze the root cause

Discussion 0
Questions 380

A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages.

What should the project manager do?

Options:

A.  

Communicate the risk to the steering committee and request a mitigation plan from senior management.

B.  

Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register.

C.  

Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders.

D.  

Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders.

Discussion 0
Questions 381

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

Options:

A.  

Ask the product owner if some low-priority stories could be cut from the sprint.

B.  

Continue with the sprint as the progress shows buffers for potential interruptions.

C.  

Ask the project team to select any additional stories as they have additional capacity than planned.

D.  

Continue with the sprint work as planned and keep monitoring.

Discussion 0
Questions 382

During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component

managed by an external vendor. How should the project manager address the team member's concern?

Options:

A.  

Ask the team member to resolve the issue independently to minimize further delays.

B.  

Ask the team member to provide details to address the issue with the vendor.

C.  

Implement fast tracking to reduce the impact of the delay on the sprint.

D.  

Update the communications management plan to prevent future reoccurrence.

Discussion 0
Questions 383

A company is using an agile approach to launch a new product. In the second sprint, the team encounters a technical problem they have never faced before.

What should the project manager do?

Options:

A.  

Inform the project sponsor about the problem faced by the team.

B.  

Ask the product owner to write the specifications for the related user story.

C.  

Organize an early retrospective with the team to analyze the problem.

D.  

Facilitate a problem-solving session with the team to analyze the problem.

Discussion 0
Questions 384

A product owner has added new high-priority work to the backlog, A project manager is working with a dedicated agile team that does not specialize in this specific area of work. The team reviewed the work and wants to accept it but acknowledges it may not have the same level of efficiency as another team having specialization in this area.

What should the project manager do In this scenario?

Options:

A.  

Add temporary members with the specialized skill set to the team to accomplish the work with a high level of confidence.

B.  

Assess the impact of a possible delay to the project and encourage the team to take the work if the impact is tolerable.

C.  

Accept the work and outsource it to another team that has the specialized skill set; then integrate the solution,

D.  

Reject the work from this team's backlog and ask the product owner to add It to another team's backlog.

Discussion 0
Questions 385

An engineer working on a project team has tasks that require an additional skill that the engineer does not have a designer on the team is experienced with this skill from previous jobs and is willing to teach this skill even though it is not part of the current work

What should the project manager do?

Options:

A.  

Escalate the situation to the engineer's manager

B.  

Request external training for the engineer

C.  

Request external training for the engineer and designer

D.  

Allow the engineer and designer to cross-train with each other

Discussion 0
Questions 386

A telecommunications company is doing a national network rollout involving continuously changing technical requirements. To address the situation the company has recently adopted a hybrid project life cycle. During a retrospective some team members complain that me majority of me stones are ready to test but have not advanced because they are waiting for the project manager's approval.

What should the project manager do?

Options:

A.  

Update the issue log and review the lessons learned register for options

B.  

Implement conflict resolution to accommodate the team's needs

C.  

Implement decision-making techniques to advance the stones

D.  

Empower the team to self-organize and make their own decisions

Discussion 0
Questions 387

During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?

Options:

A.  

Design a set of metrics including velocity, which is a good measure of value delivered.

B.  

Facilitate sprint planning sessions with a focus on defining the minimum viable product (MVP)

C.  

Promote a productive environment where everybody can work without interruptions from the rest of the team members

D.  

Create a reward system recognizing group contributions to get people motivated and improve performance

Discussion 0
Questions 388

A project manager is assigned midway through a project. The team members are in

different locations across the country and they are unable to meet in-person often. During a status review meeting, one of the stakeholders highlighted that they were unaware of the status for the project deliverables.

What should the project manager do first?

Options:

A.  

Request the project team include the stakeholder's details and make sure the projectstatus reports are shared with the stakeholder.

B.  

Schedule a meeting with the stakeholder and include the stakeholder's needs in the project management plan.

C.  

Review the stakeholder management plan and update the stakeholder register forincorporation in the project management plan.

D.  

Review the communications management plan and verify whether the stakeholder's needs are captured in the project management plan.

Discussion 0
Questions 389

As a project is reaching completion, the project sponsor tells the project manager to

immediately close the project and to move on to another project. Which critical task should the

project manager complete before closing the project?

Options:

A.  

Ensure that the whole team is appropriately recognized and organize a project farewellparty to celebrate the project success and closure.

B.  

Update and close both the risk register and issue log with the latest updates, and savethem in the organization's project management information system (PMIS).

C.  

Archive all the project documents following the organization's accepted practices sothe documents can be used in other future projects.

D.  

Meet with the project sponsor and advise that the new project might be difficult toundertake because the current project is not yet complete.

Discussion 0
Questions 390

A team is given an agile project to build a conceptual product for a new customer.

While planning, the project manager is trying to determine the best way to show value to the

customer, as the technical requirements are not very detailed.

What should the project manager do to help the client understand the value delivered during

project execution?

Options:

A.  

Include a planned value (PV) calculation in the sprint report for each build cycle.

B.  

Conduct a customer demonstration at the end of each build cycle.

C.  

Provide the customer with the refined specification during each build cycle.

D.  

Show the customer a sprint burndown chart for each build cycle.

Discussion 0
Questions 391

A project is about to close and the project manager is p Set up a meeting to perform a root cause analy reparing a draft of the project closure report. The project sponsor has approached the project manager to stay on longer to ensure the benefits in the charter are tracked as completed However, some of the benefits will not be realized until 1year after project implementation.

What should the project manager do?

Options:

A.  

Explain to the project sponsor that the project manager is only accountable for managing the project scope budget quality and schedule

B.  

Document who will be tracking benefits realization what will be tracked and when it will be tracked in the project closure report

C.  

Explain to the project sponsor that they are accountable for tracking benefits realization after project completion

D.  

Discuss extending the project manager's allocation to the project until all benefits are realized with the project management office (PMO)

Discussion 0
Questions 392

A team member is always late to work. The project manager is concerned that this may affect the motivation of other team members The project manager tells the new team member to align with the team's principles and arrive on time

What kind of conflict resolution did the project manager apply in this situation?

Options:

A.  

Smooth/accommodate

B.  

Compromise/reconcile

C.  

Collaborate/problem solve

D.  

Force/direct

Discussion 0
Questions 393

A government agency is developing a new connectivity policy. The assigned project

manager is a famous economist with international recognition. The team is eager to work with

the project manager, but feels intimidated. The project manager realizes that a junior

economist, whose tasks are behind schedule, is especially intimidated by the situation.

What should the project manager do first?

Options:

A.  

Evaluate the performance of the junior economist in the upcoming months.

B.  

Reassign some of the junior economist's tasks to other economists.

C.  

Request to replace the junior economist with a more experienced economist.

D.  

Consider organizing paired work sessions for the junior and senior economists.

Discussion 0
Questions 394

A project manager is assigned to lead a design for a new version of an existing

product with the technology and operations teams. The project manager organizes a joint

requirements session to determine the most practical ideas. The project manager was advised

that the session may become chaotic.

What should the project manager do to ensure the session is interactive, productive, and

efficient?

Options:

A.  

Pick the senior and experienced staff members from both teams and arrange face-toface interviews.

B.  

Organize a formal session led by a skilled facilitator with defined rules for howparticipants will interact with one another.

C.  

Distribute a questionnaire on the key features of the product and encourage the teamsto respond with their design recommendations.

D.  

Hold multiple sessions of manageable sizes with participants from both teams todiscuss their ideas.

Discussion 0
Questions 395

The sponsor approaches the project manager with new features they want added to

the project. The project is 95% complete, but the sponsor insists that continued support for the

project relies on the addition of the new features.

What should the project manager do?

Options:

A.  

Assess the impact of the features and refer it to the change control board (CCB).

B.  

Implement the new features after assessing the impact.

C.  

Reject the new features since it amounts to gold plating.

D.  

Add the new features to avoid losing the sponsor's support for the project.

Discussion 0
Questions 396

A company is moving to a hybrid approach and conducted capacity activities for all of the project managers. During these capacity-building activities, the focus was on agile approaches and team facilitation skills. When starting the implementation phase, the project managers faced issues motivating the newly hired agile staff.

Why are the project managers having issues motivating the agile staff?

Options:

A.  

The capacity building activities missed the servant leadership concept transfer.

B.  

Transitional periods normally cause this type of problem.

C.  

The agile staff is not used to being led by a project manager.

D.  

Project managers are expected to become coaches in agile teams.

Discussion 0
Questions 397

A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days

What should the project manager do first to maintain the project team's performance level?

Options:

A.  

Initiate a performance-based bonus for the team members to provide them with a monetary incentive

B.  

Remind the team frequently that the project must be delivered on time and within budget

C.  

Invite the team to a team-building event to alleviate their stress while strengthening teamwork

D.  

Provide routine mentoring and coaching to the team members to identify any demotivating issues

Discussion 0
Questions 398

A hybrid project team is working on an upgraded version of software for their

product owner. The team is also responsible for supporting the existing product and

customers. For the last three sprints, the team had to stop their project work and focus on

major support items for the product owner. The testers are struggling to cope with the

constant changes to the plan, which has resulted in a number of emotional outbursts.

How should the project manager proceed?

Options:

A.  

Request a replacement for those team members who are unhappy with this way ofworking.

B.  

Schedule a session with the product owner to explain that no support items can betaken into the sprints going forward.

C.  

Ask human resources (HR) to send the team members to a change managementworkshop.

D.  

Schedule a session with the team to discuss the issues and work with them to define aplan to manage the sprints going forward.

Discussion 0
Questions 399

During a product demo with key stakeholders, the team identifies that one of the functionalities failed to perform as expected What should the project manager have the project team do first to address the issue?

Options:

A.  

Update the issue log and document the change

B.  

Review the product specification requirements.

C.  

Perform a root cause analysis

D.  

Submit a change request for corrective action.

Discussion 0
Questions 400

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?

Options:

A.  

Update the risk register including noncompliance with the change process as a probable cause for scope creep

B.  

Make sure that all stakeholders are aware and in agreement with the project governance structure m place

C.  

Advise the team not to engage in modifications unless it follows the proper change approval process

D.  

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced

Discussion 0
Questions 401

A company is conducting a digital transformation project that has a hard deadline.

The marketing team wants to combine this implementation with a new product, and the newly

assigned project manager is not aware of all the dependencies.

Using a hybrid approach, what should the project manager do to ensure the dependencies are

taken into consideration?

Options:

A.  

Implement a project newsletter so the different team members can be informed aboutthe progress of each project.

B.  

Combine all of the small projects into one big project so the team can collaboratebetter as one big team.

C.  

Facilitate communication promoting a Scrum of Scrums so the different teams areaware of the dependencies and progress.

D.  

Make sure that each individual project schedule is aligned with the common deadlines.

Discussion 0
Questions 402

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

Options:

A.  

Communicate the task assignments to the team members in a clear manner.

B.  

Verify that the product owner has made the task assignments clear.

C.  

Confirm that the agile coach has made the task assignments clear.

D.  

Verify that the team members have made the task assignments clear.

Discussion 0
Questions 403

A project manager is leading a project that is on time and under budget. In the

weekly meeting with the team, the project manager finds out that one of the tasks due next

week does not have an assigned resource available for it. The resource is currently assigned

to another project.

What should the project manager do to manage the situation?

Options:

A.  

Ask the procurement department to supply a different resource.

B.  

Change the schedule according to the availability of the resource.

C.  

Ask the sponsor to obtain the resource as originally planned.

D.  

Contact the other project manager to request the resource.

Discussion 0
Questions 404

A key project team member has exhibited high interest in a project. The input from

this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.

What should the project manager do?

Options:

A.  

Reallocate tasks for the team member of concern so that work is handled by another team member.

B.  

Schedule a meeting to discuss recent observations with the team member.

C.  

Organize a team-building session with all of the team members.

D.  

Consult the resource allocation matrix to see if the team member is still required for theproject.

Discussion 0
Questions 405

A project manager finds out that the required project status reports have not been

filled out by most team members. These status reports are urgently needed to compile a

comprehensive status report for the project sponsor.

What should the project manager do to address this situation?

Options:

A.  

Reprimand the team members who did not fill out the status reports.

B.  

Justify the team members' behavior to the project sponsor.

C.  

Quickly put together a report that will satisfy the project sponsor.

D.  

Discuss the issue with the team members at fault.

Discussion 0
Questions 406

During the early phases of a project, mitigation actions were not executed in a

timely manner; therefore, the project schedule was impacted. Several project stakeholders are

now frustrated with the delays.

What should the project manager have done to manage the issue?

Options:

A.  

Identified and reported the issue

B.  

Monitored and controlled the issue

C.  

Identified the appropriate response and had it implemented

D.  

Communicated any identified action to impacted stakeholders

Discussion 0
Questions 407

A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project.

What should the project manager do to address this concern?

Options:

A.  

Ask human resources (HR) to coordinate another activity.

B.  

Reassess the team situation and provide a proper solution.

C.  

Inform HR about the situation and ask for support.

D.  

Meet with the team to explain that conflicts must be addressed and solved.

Discussion 0
Questions 408

A project manager is in the process of creating a strengths-based team and is

organizing a series of workshops to identify and document the strengths of each project team

member. During this session, there are multiple team members who are not actively

participating. These meetings are becoming futile due to a lack of participation.

What should the project manager do?

Options:

A.  

Have a one-on-one discussion with each team member to emphasize their individualtalents.

B.  

Document the behavior of the team members and highlight it during their performancereviews.

C.  

Identify the team members who are not participating and reprimand them.

D.  

Explain the benefits of the approach and the effects of positive psychology.

Discussion 0
Questions 409

A complex, high-value agile project includes sprint demonstrations with the customer

every four weeks. Executive management is concerned about the project's progress and

wants more frequent updates on the project status.

What should the project manager do?

Options:

A.  

Inform executive management that the customer is made aware of the status duringthe sprint demo.

B.  

Prepare a weekly status report and share it with executive management every week.

C.  

Inform executive management about agile principles and processes that are followedin the project.

D.  

Ask the team to prepare and share the status report with executive management everyweek.

Discussion 0
Questions 410

A project team member has lost enthusiasm and is experiencing low morale for a

project they were once excited about. What should the project manager do?

Options:

A.  

Escalate the issue to the team member's functional manager and request a responseas soon as possible.

B.  

Meet with the team member to understand what the issues are and to provide support.

C.  

Leverage other team members who are contributing and making the project a success.

D.  

Have the team member transferred to another project and add other resources to theproject.

Discussion 0
Questions 411

A project team Is working on a relative-weighting approach to assess product features. The product features will be prioritized to highlight the benefits and bring value to the customer.

What should the project manager ask the team to do?

Options:

A.  

Perform collaborative work that is coordinated by the project manager.

B.  

Rely on the expert judgment of the product owner.

C.  

Use a market-based strategy.

D.  

Engage the project sponsor.

Discussion 0
Questions 412

A project is on its sixth iteration out of seven. Select the two points where the team is

performing better than expected. (Choose two.)

Options:

Discussion 0
Questions 413

A project manager is assigned to an important company project. While reviewing the lessons learned from a similar, previous project, the project manager finds that the biggest challenges were related to learn motivation.

What should the project manager do to avoid these challenges?

Options:

A.  

Increase the project budget by 10% for team-related activities and awards.

B.  

Plan to implement team-building strategies throughout the project.

C.  

Ask the functional manager to motivate the team outside of the project.

D.  

Colocate the team to encourage more motivational team activities.

Discussion 0
Questions 414

A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project How should the project manager adjust their responsibilities accordingly?

Options:

A.  

Become a servant leader by supporting team collaboration and removing impediments

B.  

Delegate coordination activities to the product owner so the project manager can locus on managing collaboration

C.  

Request a scrum master to focus on the collaboration while the project manager focuses on the coordination

D.  

introduce new communication tools to the project team members

Discussion 0
Questions 415

A leader from project B consistently reaches out to a team member in project A for

assistance. What should project A's project manager do?

Options:

A.  

Allow project B's leader to continue building relationships.

B.  

Talk with project B's leader to discuss possible impacts to both projects.

C.  

Tell project A's team member to ignore project B's leader.

D.  

Ensure project A's team member can finish the work committed to project A.

Discussion 0
Questions 416

A team lead has been highly engaged and involved in a project and is operating without a chain of command or authority levels What is the team lead dang1?

Options:

A.  

Modeling directive leadership

B.  

Modeling commanding leadership

C.  

Modeling adaptive leadership

D.  

Modeling servant leadership

Discussion 0
Questions 417

A key resource is newly assigned to a project. The project manager and the resource

did not get along well in a previous project. This resource is needed to ensure the completion

of a major component for the project.

What should the project manager do?

Options:

A.  

Work on resolving the differences with the key resource and building a good workingrelationship to ensure project success.

B.  

Monitor the key resource closely throughout the project, but do not let the projectsponsor know about the conflict.

C.  

Request that the key resource's functional manager work directly with the resourceduring the project.

D.  

Discuss this with the project sponsor and request that this key resource be replaced onthe project.

Discussion 0
Questions 418

A retail company identifies that it is losing sales because customers are not promptly

informed about promotions and sales points. The company needs to react quickly. A project charter is created along with requests to develop a mobile application for the customer. The marketing department has a long list of features to add to the application, but there are no specifications.

Considering the objective to deploy customer value, which project life cycle approach should be chosen?

Options:

Discussion 0
Questions 419

A team is the first team m the company to use agile methods for a traditional project. The team's manager is concerned that the risks are not being managed. What should the team do to assess and manage risks regularly?

Options:

A.  

Identify and escalate any identified risks to the facilitator to handle

B.  

Update the risk register during every iteration with any open concerns

C.  

Use regular feedback loops through daily standups iteration demos and retrospectives

D.  

Focus on developing a working deliverable instead of documenting risks

Discussion 0
Questions 420

During a documentation audit of an international company it was identified that the last version of the protect schedule was from one month ago even though the project manager kr. it was recently updated How should the project manager have handled documentation for the project?

Options:

A.  

Reviewed the risk register to identify a response plan for the audit

B.  

Assigned a project team member to ensure all project documentation was updated

C.  

Updated the project management plan regularly and had it securely shared with all stakeholders

D.  

Kept documentation in the project management information system (PMIS) and shared it with appropriate stakeholders

Discussion 0
Questions 421

During a project kick-off meeting the project manager tells team members that they can attend a weekly progress meeting either from home or the office. Which intangible stakeholder engagement quality is the project manager embracing to manage relationships?

Options:

A.  

Asking and listening

B.  

Being collaborative

C.  

Managing expectations

D.  

Building trust

Discussion 0
Questions 422

A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?

Options:

A.  

Seek the sponsor's approval to extend the project schedule.

B.  

Set up a meeting to perform a root cause analysis.

C.  

Update the issue log and communicate it to the team.

D.  

Permanently colocate the team for better performance.

Discussion 0
Questions 423

One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.

What should the project manager do next?

Options:

A.  

Arrange an additional meeting with the team to communicate the agreement made during the last meeting.

B.  

Schedule a new meeting to evaluate the agreement and negotiate a new one.

C.  

Talk with the team member and explain that once the meeting ended, the agreement must be respected.

D.  

Meet with the team member and search for the root cause of their behavior.

Discussion 0
Questions 424

A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications

What should the project manager do?

Options:

A.  

Schedule a meeting with all stakeholders to understand what went wrong and who should be held responsible

B.  

Review the requirements traceability matrix with the team lead and the client to adequately resolve the issue

C.  

Meet with the client and discuss the project deadlines

D.  

Seek approval for more time for rework and resolve the issue

Discussion 0
Questions 425

A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?

Options:

A.  

Request action from the functional manager regarding the team members poor performance

B.  

Avoid selecting the team member to the next project that has an iterative design stage

C.  

Provide feedback and coach the team member during the iterative design stage

D.  

Escalate the issue to the human resources manager and request that the team member be replaced

Discussion 0
Questions 426

A project is almost completed, and both the sponsor and the project management office (PMO) are happy with the project manager's performance reviews. The project manager is under budget and ahead of schedule. However, a team member asks to add a feature to the product that will make the product more impressive and acceptable to the end users.

What should the project manager do first?

Options:

A.  

Accept the feature.

B.  

Determine if the feature is within the scope.

C.  

Submit a change request! for the feature.

D.  

Reject the feature.

Discussion 0
Questions 427

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?

Options:

A.  

Ask the leadership team for help obtaining the needed staff.

B.  

Have a direct talk with the functional manager to understand the reasons behind their attitude.

C.  

Evaluate the impact caused by the delay of forming the team and confront the functional manager.

D.  

Check with human resources (HR) regarding the availability of staff.

Discussion 0
Questions 428

A project manager is consolidating information tor all the workstreams within a data center and IT service transition project To ensure the project delivers value quickly the project manager will assess a large number of consolidated project schedules

Which two actions should the project manager take with regard to schedule analysis? (Choose two)

Options:

A.  

Review with subject matter experts (SMEs) to ensure they have contributed to the schedule development

B.  

Evaluate the master schedule and perform fast tracking and task crashing

C.  

Look (or gaps in the different schedules to determine which major risks might evolve over time

D.  

Review the project schedules to ensure that all tasks end with milestones

E.  

Evaluate the schedules for interdependencies to establish the critical path

Discussion 0
Questions 429

A project manager has been asked for performance feedback regarding one of the team members The project manager would like to gather additional input from the project team because there are no metrics in place for evaluating employee performance.

What should the project manager do next?

Options:

A.  

Evaluate demonstrated task accountability

B.  

Determine the appropriate approach

C.  

Analyze team member influence

D.  

Identify levels of decision-making authority

Discussion 0
Questions 430

A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has

doubts about the feasibility of the project.

What should the project manager do in this situation?

Options:

A.  

Validate assumptions using appropriate tools to assess the risks.

B.  

Refer to the lessons learned to determine the impact on the external environment.

C.  

Recommend postponing the project until the uncertainty is resolved,

D.  

Highlight the concern to the project sponsor in the next project review meeting,

Discussion 0
Questions 431

A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements.

What should the project manager do?

Options:

A.  

Ask the team to focus on and deliver only the agreed-upon features.

B.  

Request additional budget because additional features are being added.

C.  

Encourage the team to continue, as this will eventually help the customer.

D.  

Ask the product owner to add the additional features to the requirements.

Discussion 0
Questions 432

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?

Options:

A.  

Move the solution designer to another team.

B.  

Review the process that resulted in this situation.

C.  

Stop work until the design document is completed.

D.  

Ask the team to document the design.

Discussion 0
Questions 433

A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important

milestone in a week.

What should the project manager do next?

Options:

A.  

Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline.

B.  

Perform market research to find out if there are other vendors that can produce similar kinds of materials.

C.  

Submit a change request to the change control board (CCB) asking to extend the deadline in order to reflect the late delivery.

D.  

Involve the legal department, as the vendor is breaching the contract by not delivering the full amount in time.

Discussion 0
Questions 434

A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?

Options:

A.  

Escalate the situation to the customer management team.

B.  

Ask the customer to discuss these changes with the product owner.

C.  

Request that the customer to meet with the team only at the weekly meeting.

D.  

Ask the customer to discuss these changes with the management team.

Discussion 0
Questions 435

A compliance strategy was created during the planning phase of a project During execution, the project manager left the organization and another project manager was assigned to the team

What should the project manager do first to ensure the project is compliant?

Options:

A.  

Meet with the team to discuss compliance concerns

B.  

Review the organizational process assets (OPAs) for compliance topics

C.  

Review the compliance strategy and version history

D.  

Meet with the project sponsor to discuss their compliance concerns

Discussion 0
Questions 436

A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?

Options:

A.  

Review the deliverable carefully and determine the right status

B.  

Assign one person to be responsible for the task

C.  

Establish a clear definition of done (DoD) for each task

D.  

Encourage team members to work together

Discussion 0
Questions 437

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?

Options:

A.  

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project

B.  

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful

C.  

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor

D.  

Report the unsuccessful bidder to the local community leadership who have been supportive of the project

Discussion 0
Questions 438

In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.

What should the project manager do?

Options:

A.  

Maintain a central repository of artifacts with a version control system.

B.  

Maintain separate document control via regions to avoid discrepancies.

C.  

Develop a document management software for version control.

D.  

Facilitate training on version control and project artifacts,

Discussion 0
Questions 439

A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country's economy is struggling, and some stakeholders cannot agree on this transformation need

What should the project manager do'?

Options:

A.  

Escalate the issue to the sponsor and ask for stakeholder engagement

B.  

Review the project business case and update it periodically

C.  

Plan for strategic program management

D.  

Implement a communications management plan

Discussion 0
Questions 440

A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be

enough to add business value.

With the project on a fixed budget, what should the project manager do next?

Options:

A.  

Plan the project based on the available resources and submit a change request upon completion.

B.  

Gather all stakeholders and provide recommendations on a smaller, more feasible project scope,

C.  

Identify the technical requirements and request that management hire external resources,

D.  

Document the problem in the issue log and suggest a change request to decrease the scope.

Discussion 0
Questions 441

A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.

What should the project manager do next?

Options:

A.  

Explore the minimum requirements of the product and their feasibility.

B.  

Explain the resource constraints of the project to management.

C.  

Outsource the management of the product to an external team.

D.  

Conduct a detailed risk analysis to highlight the risks in the project.

Discussion 0
Questions 442

What should an agile lead do lo ensure their team is set up for success?

Options:

A.  

Pay attention to team dynamics and understand that coaching is done simultaneously at an individual and whole-team level

B.  

Schedule sprint meetings and coaching sessions to discuss project-related information

C.  

Plan quarterly informal meetings or team bonding sessions to encourage the team to work together

D.  

Document team tasks and challenges in order to understand when to step in and help a member of the team

Discussion 0
Questions 443

At the end of a third planning meeting, the client and a functional manager requested additional meetings to add more features to the product.

What should the project manager do to start building the product faster?

Options:

A.  

Allow the sponsor to determine how long the planning phase should last.

B.  

Allow the client ta determine how long the planning phase should last.

C.  

Ask the functional manager to work with the team to finalize planning and begin building the product.

D.  

Explain that more features can be planned in upcoming Iterations and begin building the product.

Discussion 0
Questions 444

A company is implementing a project with team members who are located in different countries and lime zones Performance assessments show that team performance is low because the team doesn't have a common understanding about task distribution

What should the project manager do?

Options:

A.  

Colocate the team members

B.  

Perform team-building activities

C.  

Review and reassign tasks

D.  

Revisit the communications management plan

Discussion 0
Questions 445

During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining

What should the project manager do?

Options:

A.  

Work with the team to understand and solve the issues

B.  

Provide testing training to all the project team members

C.  

Increase the sprint duration so the testing can be completed

D.  

Add a new resource with testing skills to the team

Discussion 0
Questions 446

The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.

What is the project manager's priority in this situation?

Options:

A.  

Request that the team member gel the contract signed as soon as possible

B.  

Determine a mitigation strategy to move the project forward

C.  

Take over contract negotiations for the team member to speed up the process

D.  

Assist with the removal of impediments and blockers so that the project can continue

Discussion 0
Questions 447

A senior-level executive approached the project manager of a highly visible project that is currently in the execution phase. The executive indicated that they do not support the project

and will be actively trying to prevent its success by reailocating key team members to another critical project.

What should the project manager do?

Options:

A.  

Request help from human resources to keep the key team members on the project.

B.  

Work with the project sponsor to determine an appropriate response.

C.  

Ask to meet privately with the senior-level executive to discuss the matter further.

D.  

Discuss the incident with the key project team members.

Discussion 0
Questions 448

A project manager is working on a project that will transform the organization's operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.

Knowing that there are no additional funds available, how should the project manager proceed?

Options:

A.  

Allocate the budget to the phases of the project and meet with upper management to consolidate the final funds.

B.  

Ensure that the budget is enough to cover the internal resources, since external supplies can be covered by procurement.

C.  

Allocate the budget to the deliveries that have higher business value for the organization than those with lower business value.

D.  

Decide to work on the small deliveries, leaving the big deliveries until the end of the project, and track critical expenses.

Discussion 0
Questions 449

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

Options:

A.  

Developing new product lines

B.  

Complying with new regulations

C.  

Establishing company processes

D.  

Certifying sustainable products

Discussion 0
Questions 450

During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating As a result lots of misunderstandings occurred

What should the project manager do to address this issue?

Options:

A.  

Book one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates

B.  

Check the ground rules of the meeting to review the initial agreement with the team members

C.  

Identify one team representative to speak up during the daily meeting and share the team updates

D.  

Use round-robin check-ins to facilitate the meeting so all participants have the opportunity to speak

Discussion 0
Questions 451

A project is approaching its project closure phase, and the project manager receives

an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.

Which three actions should the project manager ask the project specialist to take? (Choose

three)

Options:

A.  

Create a quality assurance plan for the documentation.

B.  

Identify the components of the project documentation.

C.  

Archive only the initial and draft versions of the documents.

D.  

Ensure that the documents are in an easily retrievable form.

E.  

Collect the documents at the time of their creation.

Discussion 0
Questions 452

A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?

Options:

A.  

Provide a project management template for the project manager to follow as a guide.

B.  

Suggest using an agile approach since customer and team collaboration is critical for project success.

C.  

Work with the project manager to develop a new approach that will bring benefits to the project.

D.  

Establish a project management methodology that requires the customer to provide daily updates to the team.

Discussion 0
Questions 453

Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.

What tool should the project manager use to conduct meetings with the project team and clients?

Options:

A.  

Use a third-party instant messaging tool.

B.  

Use a password-enabled audio/video product,

C.  

Use a popular social media platform.

D.  

Use a collaborative electronic whiteboard,

Discussion 0
Questions 454

An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.

Options:

Discussion 0
Questions 455

A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.

How will the project manager be able to complete this task?

Options:

A.  

Tell the owner that a rough order of magnitude will be provided.

B.  

Contact a subject matter expert (SME) for advice and consultation.

C.  

Call a meeting with the project team to identify the most appropriate approach.

D.  

Tell the owner that the task requires more time and expertise

Discussion 0
Questions 456

A project engineer in country A is complaining about the sample received from the supplier in country B because the sample is not the correct length. During a telephone conference, the supplier checked the drawings and insisted that the measurement was accurate.

What should the project manager do next?

Options:

A.  

Escalate the issue to the purchasing department for review.

B.  

Evaluate the procurement contract to determine the agreed-upon specifications.

C.  

Hire a company in country B to perform a quality check before shipment.

D.  

Add an additional task to cut the received part according to the specifications,

Discussion 0
Questions 457

A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity

issues joining team calls during the day.

What should the project manager do?

Options:

A.  

Procure tools that consume less bandwidth for internet calls.

B.  

Record the meeting to share with the team members who were unable to join.

C.  

Ask the team members to use chat tools as an alternative to calls.

D.  

Determine what the problem is and develop an action plan.

Discussion 0
Questions 458

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.

How should the project manager address the situation?

Options:

A.  

Discuss the vacation plan and include scheduling changes in the change log database.

B.  

Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project.

C.  

Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule.

D.  

Push out the project timeline according to the vacation plan in place based on the recent company policy.

Discussion 0
Questions 459

A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.

What should the project manager do?

Options:

A.  

Advise the teams to follow the company’s existing project management approach.

B.  

Allow the teams to continue using their approaches and gradually adapt to a hybrid model.

C.  

Let a senior team member select the approach that is appropriate.

D.  

Insist the teams both follow either a predictive or agile approach.

Discussion 0
Questions 460

Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?

Options:

A.  

Organize a brainstorming session with the project team to address the issue.

B.  

Advise the project team on the importance of team engagement,

C.  

Invest in coaching and training for all project team members.

D.  

Escalate the issue with the human resource (HR) department to take action,

Discussion 0
Questions 461

A complex project is m its execution phase. The project is set up to produce both predictive and incremental deliverables. The agile team is running late on their tasks There is a resource on the agile team who is responsible for producing progress reports for the project manager This resource has the required skills to help other team members with their workload

What should the project manager do to optimize the time of the resource who produces the progress reports?

Options:

A.  

Work more closely with the agile team to eliminate the need for progress reports

B.  

Record this in the issue log and find a resource to produce the reports

C.  

Produce the progress reports on their own

D.  

Engage a new resource to produce the progress reports

Discussion 0
Questions 462

A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no longer work due to the team member's personal commitments.

What should the project manager do?

Options:

A.  

Allow the most senior team members to decide the time that works for the team.

B.  

Reassess the team's hours collaboratively so that the team is not impeded by the issue.

C.  

Discuss the lack of dedication with the team member and their functional manager.

D.  

Remove the team member from the project team to be fair to the other members.

Discussion 0
Questions 463

A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.

What should the project manager do?

Options:

A.  

Ask the client how the project will affect the client's organization and recommend that all impacted parties be involved.

B.  

involve an executive-level stakeholder at the project manager's own company to speak with the client's executive sponsor.

C.  

Perform an independent analysis to determine the stakeholders from the client's organization.

D.  

Defer to the judgment of the client's executive sponsor since they will determine whether the project is a success.

Discussion 0
Questions 464

A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,

What should the project manager do?

Options:

A.  

Descope low-priority features that were not explicitly requested and add this feature as a high priority.

B.  

Inform the senior manager that they will need a new project management plan for this feature,

C.  

Complete the most current feature and release the resources for the new feature.

D.  

Analyze the impact of this change and present the options to the senior manager.

Discussion 0
Questions 465

During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?

Options:

A.  

Document the issues and extend the project delivery timeline.

B.  

Convene the steering committee and inform them of the impact to the project.

C.  

Prioritize the user stories with issues and have the team resolve them

D.  

Update the project management plan and risk management plan.

Discussion 0
Questions 466

A project manager has recently joined an organization and notices that the engineering manager shouts at the project manager during project meetings Also the procurement manager will not return calls and the accountant always insists the project manager clears approved budget line items with them personally before expensing

Which three corrective actions should the project manager perform? (Choose three)

Options:

A.  

Confront the people causing the stress directly with the aim of finding amicable solutions

B.  

Seek support from the project management office (PMO) on addressing issues affecting the project

C.  

Discuss the possible actions with the project sponsor

D.  

Avoid the people causing stress and request a transfer as soon as possible

E.  

Talk to the human resources (HR) manager about these concerns

Discussion 0
Questions 467

A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.

What should the project manager have done*?

Options:

A.  

Confirmed that the communication was understood and solicited feedback from the team

B.  

Sent the roles and responsibilities matrix along with the project management plan

C.  

Discussed the roles with the managers to help explain them to their team members

D.  

Briefed each team member on their roles before sending the project management plan

Discussion 0
Questions 468

A customer wants to launch a new product in the market and an agile team is set up to work on this project for 9 months After 1 month the customer feels that it would be better to release the product 2 months earlier than the planned date. The task is now assigned to the most talented resource in the organization to this project tor an early finish.

Which risk management strategy has been adopted in this scenario?

Options:

A.  

Shared

B.  

Accepted

C.  

Enhanced

D.  

Exploited

Discussion 0
Questions 469

A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools

In order to deliver the project successfully, what should the project manager focus on as part of the plan?

Options:

A.  

Align with the organization's project management office (PMO) to inform and make them aware of the new approach

B.  

Explain and communicate the new approach to the project sponsor and key stakeholders

C.  

Develop a detailed schedule for the entire project m the planning phase and communicate that to the stakeholders

D.  

Communicate with other project managers to see how they manage hybrid projects

Discussion 0
Questions 470

A project manager working on a software development project asked the software development about the status of a task. The developer responded that the task was delivered 1 week ago and mentioned that the delivery was reported via a specific project management software.

What should the project manager do next?

Options:

A.  

Review the stakeholder engagement plan and communicate which technology is available to develop, transmit, and store project artifacts.

B.  

Engage the software developer, let them work with this project management software, and then conduct a train-the-trainer activity to ensure everyone can use it.

C.  

Research the project management software to understand how it works, and establish it as the acceptable software to hold the project artifacts.

D.  

Review the communications management plan and communicate which technology is to be used to develop, transmit, and store project artifacts,

Discussion 0
Questions 471

During the final iteration of the execution phase, the project has a cost performance

index (CP!) of 0.9 and a schedule performance index (SPI) of 1.0.

How should the project manager avoid a budget shortfall?

Options:

A.  

Follow the risk management plan.

B.  

Reduce the team effort utilization.

C.  

Look for cost-saving opportunities.

D.  

Submit a change request to add to the management reserve.

Discussion 0
Questions 472

What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?

Options:

A.  

Hire employees who specialize in agile approaches so they can better contribute toprojects.

B.  

Assign employees to agile projects so they can quickly adjust to the new approach.

C.  

Train all employees in agile approaches.

D.  

Shift the way the company views, reviews, and assesses employees.

Discussion 0
Questions 473

A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members

Which three actions should the project manager take? (Choose three)

Options:

A.  

Allow team members to resolve personal issues without involving the project manager

B.  

Arrange and conduct team-building sessions to improve team effectiveness

C.  

Obtain feedback from the isolated team member to understand the situation

D.  

Get feedback from other team members to understand what led to this situation

E.  

Identify the isolated team member as a risk and document the situation in the risk register.

Discussion 0
Questions 474

An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager's management approach?

Options:

A.  

Laissez-faire

B.  

Transactional

C.  

Transformational

D.  

Charismatic

Discussion 0
Questions 475

A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team

What should the project manager do?

Options:

A.  

Add a user story during sprint planning that gives recognition to behaviors that are aligned with the new values

B.  

Send a standard email to the team prior to every daily standup containing the new values

C.  

Organize a team meeting focusing on the new values associated with the transformation

D.  

Give recognition to team members' behaviors that are aligned with the new values during the sprint retrospectives

Discussion 0
Questions 476

A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,

yet some stakeholders lack an understanding of how it will provide value to the organization.

What should the project manager do next?

Options:

A.  

Ask the sponsor to identify requirements for a new project to monitor and report achievement of the benefits.

B.  

Direct the team to implement the benefits management plan and track achievements before the end of the project.

C.  

Coordinate with the stakeholders to ensure the benefits management plan is in alignment with the goals.

D.  

Update the work breakdown structure (WBS) and project schedule with tasks and resources to track benefits realization.

Discussion 0
Questions 477

A key stakeholder has recently started in a company and has been assigned to a hybrid project. Although very experienced in their domain, the stakeholder has only been exposed to predictive project approaches.

What should the project manager do?

Options:

A.  

Inform the stakeholder that they must level their knowledge with other stakeholders.

B.  

Update the risk register with the potential impact and apprise the steering committee.

C.  

Inform the project management office (PMO) that the team will use a predictive approach for this project.

D.  

Allocate time to mentor the stakeholder in the selected project approach.

Discussion 0
Questions 478

A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.

What should the project manager do?

Options:

A.  

Meet with the project sponsor to explain that the project cannot be completed as planned

B.  

Meet with the technical lead to review the sprint plan

C.  

Meet with the product owner to confirm the minimum viable product (MVP) option

D.  

Meet with the project team and reprioritize the backlog

Discussion 0
Questions 479

A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception about the company's brand.

What should the project manager have done to prevent this?

Options:

A.  

Monitored progress in achieving the business value throughout the project

B.  

Asked for additional time to achieve the project goals and increase business value

C.  

Increased the number of project resources to ensure attainment of the business value

D.  

Reviewed previous projects’ lessons learned and applied them to this project

Discussion 0
Questions 480

A project manager was recently assigned to a new project that is about to start. The

organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.

What should the project manager do next?

Options:

A.  

Create an issue log template that will be used to identify and track impediments.

B.  

Create a contingency plan in case the project deviates from the initial plan.

C.  

Create a schedule management plan to ensure the project meets the delivery date.

D.  

Create an assumption log and map assumptions to impediments based on the impact tothe project value.

Discussion 0
Questions 481

A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?

Options:

A.  

Meet with each team member separately and apply an appropriate approach with each one.

B.  

Approach the project sponsor and request help in discussing the project deliverables with team members.

C.  

Explain to the team that the project manager is ultimately responsible for the delivery.

D.  

Assign multiple managers to the various teams and delegate all of the tasks to them.

Discussion 0
Questions 482

Clients are complaining about the delay on a product delivery timeline. It is confirmed that the issue is related to the product inventory and availability.

What should the project manager do to engage the stakeholders?

Options:

A.  

Ask the team to work on the complaint raised by the clients.

B.  

Escalate the issue raised by the clients to the project sponsor,

C.  

Develop a solution with the team to identify the inventory level.

D.  

Work with the team and the product owner to define the next steps.

Discussion 0
Questions 483

A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?

Options:

A.  

Work with the product owner to evaluate and prioritize the requirements

B.  

Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list

C.  

Determine the expected benefits of each requirement to maximize the overall business value

D.  

Prioritize the requirements based on the hierarchical level of the requesting stakeholders

Discussion 0
Questions 484

A project manager Is working on a project using a hybrid approach. The project Is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company which was approved by their functional manager

What should the project manager do first in this situation'?

Options:

A.  

Ask the functional manager why a decision was made without consulting them

B.  

Use soft skills to influence the team member to slay until the project is completed

C.  

Ask the functional manager for an immediate replacement for the team member.

D.  

Review the risk management plan and mitigation plan to understand the impact of this issue

Discussion 0
Questions 485

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?

Options:

A.  

Use compression techniques to break down the scope and assign the scope pieces todifferent vendors with a fixed-price contract.

B.  

Use the contingency budget for hiring additional vendor resources to mitigate any projectrisk.

C.  

Engage in a time and materials (T&M) contract and hire a local vendor to supportdevelopment.

D.  

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.

Discussion 0
Questions 486

During the execution phase of a large project there is an extremely high number of change requests Because of this the project manager realizes that there is a greater risk for rejection of the deliverables

How should the project manager mitigate this risk without compromising the completion date?

Options:

A.  

Review the integrated change control process to restrict the number of changes

B.  

Focus on delivering incremental value through multiple smaller deliveries

C.  

Request sponsor support to get buy-in from the users and stakeholders

D.  

Restart the stakeholder engagement process by collecting user requirements again

Discussion 0
Questions 487

A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards

in order to ensure this, what should the project manager define and document?

Options:

A.  

Quality

B.  

Estimates

C.  

Objectives

D.  

Requirements

Discussion 0
Questions 488

A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project.

How should the project manager handle this situation?

Options:

A.  

Ask the product owner to create a new entry in the risk management plan regarding likelihood and imped

B.  

Review the backlogs from similar projects and understand how change requests were implemented

C.  

Ask the product owner to follow the change request process to formalize new requirements

D.  

Make sure that the product and sprint backlogs have the required level of documentation and both are visible to the team

Discussion 0
Questions 489

A project manager for a large software delivery project is in the process of finalizing the project governance, The project manager would like to implement procedures that do not align with several policies required by the organization's project management office (PMO). The project manager

believes that the procedures outlined in the project governance will be necessary for this particular project due to the unique nature of the

technology.

What should the project manager do?

Options:

A.  

Engage stakeholders to modify policies outlined by the PMO.

B.  

Move forward with the project governance and inform the PMO.

C.  

Discuss the proposed changes with the PMO.

D.  

Disregard the initial procedures and follow the policies outlined by the PMO,

Discussion 0
Questions 490

Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.

What should the project manager do to address this concern?

Options:

A.  

Schedule a dedicated session to review the team charter.

B.  

Set up a meeting with the team member to review the team charter.

C.  

Ask another team member to meet with this team member for a discussion.

D.  

Send a reminder to the team member about the rule being violated.

Discussion 0
Questions 491

A client comes to the company asking to copy a project that was executed 2 years ago

in the same city, with the expectation that the new project will have the same cost and duration.

While finalizing the project management plan, the project manager realizes that the baseline

costs are much higher than the original project.

What could the project manager have done to avoid this?

Options:

A.  

Verified applicable budget inputs related to this project

B.  

Assigned the same project resources to this project

C.  

Estimated a budget for the project's quality management

D.  

Determined a budget reserve for this project

Discussion 0
Questions 492

A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours, The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues.

What should the project lead have done initially to avoid this situation?

Options:

A.  

Reviewed the project management plan

B.  

Created a detailed operations manual

C.  

Increased support hours for the hours of operation

D.  

Involved operations stakeholders during planning

Discussion 0
Questions 493

A project manager notices that one of the marketing executives in the firm always appears stressed. The project manager observes that the executive's performance is gradually declining and is affecting the project deliverables.

What should the project manager do?

Options:

A.  

Assign the marketing executive's tasks to another project team member

B.  

Review the executive's declining performance with human resources (HR)

C.  

Show empathy and praise the marketing executive's strengths

D.  

Make the marketing executive accountable for their work and output

Discussion 0
Questions 494

A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.

In order to help the team, what should the project leader do?

Options:

A.  

Recommend that the product owner reviews the backlog refinement processes.

B.  

Recommend that the team reviews the length of the iteration with the stakeholders.

C.  

Recommend limiting the work in progress to improve the team’s focus.

D.  

Recommend a review of the team members’ individual performances.

Discussion 0
Questions 495

A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use to update the details and communicate to relevant stakeholders?

Options:

A.  

Risk register

B.  

Project schedule

C.  

Change request

D.  

Issue log

Discussion 0
Questions 496

An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase

What should the team do next?

Options:

A.  

Start with the end user documentation review with the customer and gather feedback

B.  

Start with design of the prototype review with the customer and gather feedback

C.  

Start with the product prototype development, review with the customer, and gather feedback

D.  

Start with the product architecture review with the customer and gather feedback

Discussion 0
Questions 497

It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.

What should the project manager do?

Options:

A.  

Ask the team member to send their concerns in writing.

B.  

Empathize with the team member and discuss next steps.

C.  

Review the organization's human resources (HR) policy.

D.  

Schedule a meeting with the team member for the next work day.

Discussion 0
Questions 498

A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.

How should the project manager have handled the situation?

Options:

A.  

Collaborated with the functional manager to determine which critical activities could be accommodated by the budget

B.  

Engaged with the project sponsor to ensure support for the project manager's decision

C.  

Conducted a meeting with the functional manager to explain why the activities needed to be stopped

D.  

Convinced the functional manager to stop the activities that will run beyond the budget

Discussion 0
Questions 499

A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

Options:

A.  

Have a discussion with the sales team to find a solution to the issue

B.  

Validate the reason and add it as an issue in the issue log

C.  

Direct the sales team to speak with accounting to resolve the issue

D.  

Escalate the issue to the functional manager

Discussion 0
Questions 500

A project manager has just completed a fixed-price project and the stakeholder is unhappy with the result What should the project manager do?

Options:

A.  

Explain to the stakeholder that any modifications require additional budget

B.  

Review the missed program deliverables with the project team

C.  

Review the project charter for the project approval criteria

D.  

Speak with the team's manager to get extra hours from the team

Discussion 0
Questions 501

A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status,

What should the project manager do first?

Options:

A.  

Review the stakeholder engagement plan.

B.  

Review the communications management plan.

C.  

Send the CEO one executive summary per week instead of five reports per week.

D.  

Meet with the team and decide the type and frequency of the reports to send to the CEO.

Discussion 0
Questions 502

A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.

How should the project manager resolve this situation in their new role as servant leader?

Options:

A.  

Review the organizational process assets (OPAs) to find similar situations and review the resolution actions taken,

B.  

Request that the team use the next sprint to complete all technical debt remaining from the previous sprints.

C.  

Extend the sprints to 3 weeks to allow the work requested by the product owner to be completed.

D.  

Encourage the whole team to be empowered and accountable for the decisions made according to their roles,

Discussion 0
Questions 503

A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?

Options:

A.  

Rebaseline the project schedule to absorb the delay.

B.  

Report the delay with rectifying actions to the project management office (PMO).

C.  

Notify the project steering committee about the cause of the delay.

D.  

Report the delay with rectifying actions to the change control board (CCB) for review,

Discussion 0
Questions 504

A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.

What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?

Options:

A.  

Receive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.

B.  

Organize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.

C.  

Issue the team lead a warning, and consider recommending the team lead for emotional intelligence training.

D.  

Find ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.

Discussion 0
Questions 505

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?

Options:

A.  

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client,

B.  

Continue working with the predictive approach to deliver the value at the end of the project.

C.  

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.

D.  

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.

Discussion 0
Questions 506

An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story

What should the agile leader do1?

Options:

A.  

Emphasize to the team that each member is responsible for their story but the team is collectively responsible for finishing the sprint

B.  

Ask the team to address this at the next sprint planning instead of at the retrospective

C.  

Suggest that the team assign stones at the beginning of the sprint based on each person's strengths to maximize performance

D.  

Work with the product owner to remove the story from the sprint because the points cannot be splits

Discussion 0
Questions 507

During a status review meeting a team member raises concerns about tasks that are not being completed due to an underperforming resource on the team. What should the project manager do first?

Options:

A.  

Ask the team to solve the issue internally and review the underperforming resource's situation

B.  

Meet with the team member privately to discuss the problem and work together to find a solution

C.  

Contact the functional manager and request to replace the team member with a better resource

D.  

Discuss various options to improve the team member's performance with their functional managers

Discussion 0
Questions 508

A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.

How should the project manager resolve this conflict?

Options:

A.  

Meet with all project stakeholders to identify how to implement the technology.

B.  

Identify the disagreement in the risk register and develop a contingency plan.

C.  

Update the project charter to align with the desires of the project sponsor.

D.  

Negotiate with the project sponsor to develop a mutually beneficial solution.

Discussion 0
Questions 509

A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not have enough capacity and they want to be involved only a few times during the project.

How should the project manager plan and manage the project?

Options:

A.  

Refuse to manage the project as there is too much risk in developing this kind of project without a product owner.

B.  

Define the project's requirements, prepare a long-term detailed plan, and manage the project according to it.

C.  

Convince the client that a product owner is needed, as the project manager is not able to run an agile project without all the relevant roles in place,

D.  

Agree up front on a minimum viable product (MVP), establish deadlines for review, and run the project with a backlog and weekly sprints.

Discussion 0
Questions 510

A project manager is working on the delivery of a solution that needs to be deployed to the public quickly. The project team is experienced, the stakeholders are supporting the delivery, and the customer is cooperating.

What strategy should the project manager use to ensure on-time delivery of the solution?

Options:

A.  

Have a high-level plan for incremental deliveries and get the customer's feedback as early as possible.

B.  

Ask the sponsor for support regarding the allocation of additional resources to finish on time.

C.  

Have a detailed plan of all milestones, deliverables, functionalities, and allocation of resources.

D.  

Meet with the customer to agree on the components of the solution and the priorities.

Discussion 0
Questions 511

During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project.

What should the project manager do?

Options:

A.  

Review the procurement documentation and modify requirements as needed.

B.  

Study the new regulations with the team and evaluate if there is any impact on theproject variables.

C.  

Update the contingency plan to take this issue into account.

D.  

Meet with the stakeholders to update the risk register and risk management plan.

Discussion 0
Questions 512

A new resource has joined an iterative project team The project manager notices that the resource is unable to complete the deliverables on time

How should the project manager address this situation?

Options:

A.  

Address the lack of performance by coaching the new team member

B.  

Discuss options to improve performance with the resource manager

C.  

Provide performance feedback as part of the retrospective ceremony.

D.  

Request a more efficient replacement resource from the project sponsor

Discussion 0
Questions 513

A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals

What two options will help the team initially address this obstacle? (Choose two)

Options:

A.  

Escalate the issue to the project sponsor.

B.  

Review and update dependencies

C.  

Schedule a retrospective.

D.  

Conduct a root cause analysis.

E.  

Create a risk management plan.

Discussion 0
Questions 514

During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible

What approach should be used in this situation?

Options:

A.  

The team facilitator gets support from external team members.

B.  

The team members bring in a specialist to help them

C.  

The product owner moves it to the product backlog.

D.  

The cross-functional team member work together to complete the activity

Discussion 0
Questions 515

A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.

How can the project manager promote empowerment and accountability among the team?

Options:

A.  

Assign the tasks individually based on the role of the team member to ensure expertise on the subject.

B.  

Encourage and assign the team to perform demos of their products or software with the customers

C.  

Give the team autonomy to make their own decisions on how to perform the tasks.

D.  

Encourage the team to keep the product owner involved when choosing ways to resolve the given task

Discussion 0
Questions 516

For the purposes of quality assurance a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available

Why is an attendance list important?

Options:

A.  

It is standard practice on projects to conduct risk review meetings which should have records on meeting attendance

B.  

The attendance list is evidence that risk review meetings were held with the appropriate project team members

C.  

It is a record that shows the number of attendees in the meeting

D.  

It is a document that is registered within the lessons learned register

Discussion 0
Questions 517

During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting

What should the project manager do?

Options:

A.  

Call for a change control board (CCB) meeting, and inform the stakeholder about the outcome

B.  

Update the communications management plan and implement the change

C.  

Meet with the project sponsor to discuss how to address the situation.

D.  

Meet with the stakeholder prior to the meeting to obtain their opinion

Discussion 0
Questions 518

The project manager just started leading a project team from which the previous project manager resigned After a quick evaluation of the project it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule

What should the project manager do?

Options:

A.  

Conduct a meeting with the project team to discuss and address the sources of disagreement

B.  

Inform the stakeholders that the project will be delayed due to previous team management

C.  

Crash the project timeline to ensure the project is back on schedule

D.  

Issue a change request to extend the project schedule based on identified delays

Discussion 0
Questions 519

A project manager receives a voicemail from a business analyst on the project team The business analyst indicates that an internal stakeholder is upset that they were not included before the project began The stakeholder is asking for an addition to the requirements traceability matrix

What should the project manager do to improve the stakeholder relationship?

Options:

A.  

Consult the project scope document to make sure the addition is in scope.

B.  

Update the stakeholder engagement plan to ensure the stakeholder is included in the project stakeholder list

C.  

Initiate a project change request so the change control board (CCB) can decide if it is in scope.

D.  

Engage the stakeholder to solicit more information before responding to the request

Discussion 0
Questions 520

After the second iteration of a component development project, the project team conducts a retrospective It shows that in the initial phase the project has failed to comply with a product functionality. The planning for this product has a predominantly predictive approach.

Which technique will help the project manager to accelerate the deliverable?

Options:

A.  

Impact mapping

B.  

Rolling wave planning

C.  

Collective code ownership

D.  

Scrum of Scrums

Discussion 0
Questions 521

A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain

What should the project manager do now?

Options:

A.  

Reduce the priority of project risks as all remaining risks are low-level

B.  

Notify stakeholders that all high-level risks have been resolved

C.  

Reevaluate identified risks and update the risk register

D.  

Reclassify low-level risks as high-level risks

Discussion 0
Questions 522

A company's CEO has just returned from a conference on the use of artificial intelligence (Al) and would like the project manager to implement this technology in the organization What should the project manager do first?

Options:

A.  

Start developing a business case.

B.  

Start a strengths, weaknesses, opportunities and threats (SWOT).

C.  

Engage stakeholders and allocate resources

D.  

Gather requirements from stakeholders

Discussion 0
Questions 523

During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.

What should the project manager do?

Options:

A.  

Guide the team to revert back to the forming and storming stages

B.  

Escalate the issue to the project sponsor.

C.  

Convene a team building event to address key performance indicators (KPIs).

D.  

Discuss the decrease in productivity with human resources

Discussion 0
Questions 524

During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope The project manager decided to update the risk register and escalate the opportunity to a higher level

What should the project manager do next with this opportunity?

Options:

A.  

Share this opportunity with another project

B.  

Establish a contingency reserve to support the opportunity

C.  

Further monitor the opportunity

D.  

No more action is required

Discussion 0
Questions 525

A team has been working on a project for several months,, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.

How can the project manager prevent this situation from happening in the future?

Options:

A.  

Create a prioritized backlog and define iteration review sessions with stakeholders

B.  

Create a detailed work breakdown structure (WBS) and milestone schedule approved by all stakeholders

C.  

Schedule a daily meeting to review team performance and impediments

D.  

Schedule a kick-off meeting for every project phase to share the project management plan with all stakeholders

Discussion 0
Questions 526

A project team has recently finished a sprint for developing two features for a fleet management system Although the team delivered the required features, they encountered several issues and conflicts during the sprint. Team members were upset about this experience and are now showing a lack of motivation due to what has occurred.

What can the project manager do to help increase the team's motivation and engagement with the project?

Options:

A.  

Review sprint progress with the project team members

B.  

Set up one-on-one meetings with the project team members

C.  

Review sprint planning procedures with the project team members

D.  

Perform a sprint retrospective with the project team members

Discussion 0
Questions 527

A company's project management office (PMO) has started to implement iterative tools A project manager is starting a new project and has identified an opportunity to use the iterative tools One of the senior managers is concerned about this modified framework as it is fairly new to the company

What should the project manager do first?

Options:

A.  

Organize individual sessions with the stakeholders to build awareness and trust in the new framework

B.  

Look for external training on the new framework to eliminate the risk of low engagement from stakeholders.

C.  

Send documentation to the senior manager about the advantages of the new framework

D.  

Escalate the senior manager's concern to the project sponsor and distribute the status to the team

Discussion 0
Questions 528

A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing

What should the project manager review?

Options:

A.  

The project charter and scope statement

B.  

The requirements traceability matrix

C.  

The business requirement documents (BRD)

D.  

The WBS dictionary

Discussion 0
Questions 529

A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts

What should the project manager do next?

Options:

A.  

Raise the issues in the retrospective and propose solutions

B.  

Inform management that commitments will not be met.

C.  

Involve management to help resolve the conflicts

D.  

Coach the team both as a whole and individually

Discussion 0
Questions 530

During daily calls team members share task progress One team member does not usually communicate many details and has critical tasks to be completed All team members are located in different countries and critical work is about to start Which two options will help the project manager in this situation? (Choose two)

Options:

A.  

Encourage all team members to use a virtual workspace

B.  

Ask the team to send emails with detailed task progress

C.  

Talk to the team member about their engagement and take appropriate action.

D.  

Reassign the work to a resource who participates in the daily calls

E.  

Report the team member’s poor performance to the functional manager

Discussion 0
Questions 531

A project manager has been asked to lead a project. The performing organization does not have a project management office (PMO) or formal governance policies procedures, and guidelines for this type of project

What should the project manager do first to determine a governance approach for the project?

Options:

A.  

Consult a subject matter expert (SME) as to the best governance policies, procedures, and guidelines to be used by the project

B.  

Consult with team members and stakeholders to determine whether the organization has any informal governance policies procedures, and guidelines

C.  

Choose either a predictive or agile framework best suited to the nature of the project, and use this framework as the basis for project governance policies, procedures, and guidelines

D.  

Coach the self-managing team to produce tailored governance policies, procedures and guidelines for the project

Discussion 0
Questions 532

Which two actions should a project manager consider while launching a new virtual team? (Choose two)

Options:

A.  

Recruit the best resources within the organization to be part of the virtual team

B.  

Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls

C.  

Identify the types and quantities of resources required for each work package or activity

D.  

Establish in the beginning, how progress will be monitored and the best means for communicating progress

E.  

Verify if team members are on more than one team and cannot devote enough time to this team

Discussion 0
Questions 533

A company has decided to implement a new archiving system A data breach occurred during the implementation of the project

What should the project manager do first?

Options:

A.  

Implement the planned risk response to handle the issue.

B.  

Review possible alternative documentation methods with team

C.  

Update the risk register with the risk and proposed impact.

D.  

Ask the team to fix the system to resolve the issue

Discussion 0
Questions 534

A project is in the knowledge transfer phase, and a few subject matter experts (SMEs) went to the client site for knowledge transfer The SMEs captured various process deviations without sharing with the project team

How can the project manager ensure knowledge transfer across the team?

Options:

A.  

Ask the project team to run a deviation log review meeting with the client, highlighting that the project may not be able to go live as scheduled

B.  

Ask the project management office (PMO) to provide team members with real-time visibility for deviations and facilitate team members to resolve issues

C.  

Ask the SMEs to share the knowledge transfer documents with all other members by placing the documents in the project management information system (PMIS)

D.  

Ask the project team to facilitate a lessons learned session during the projectclosure phase to incorporate this issue

Discussion 0
Questions 535

A project just kicked off and management’s expectation is to ensure that the deliverable of the first iteration helps the marketing team present the product prototype to potential customers. What should the project manager do?

Options:

A.  

Increase the details of the work breakdown structure (WBS) to minimize errors and delays.

B.  

Split the backlog into phases to ensure that the key features are delivered first

C.  

Ask the sponsor to prioritize some functionalities of the product.

D.  

Identify the minimum functionality required for the product

Discussion 0
Questions 536

During the course of the project several obstacles are identified that are preventing the project from moving forward. What should the project manager do to remove the obstacles?

Options:

A.  

Have the project team work on other activities

B.  

Implement plans to remove the obstacles

C.  

Escalate to the project steering committee

D.  

Prioritize the obstacles for resolution

Discussion 0
Questions 537

A company is working on a project and is using a hybrid approach to streamline a customer service process. At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.

What should the project manager do to support the business analyst?

Options:

A.  

Assign resources to coach the business analyst

B.  

Ask the business analyst to focus on their work allocation for the needs of the project

C.  

Create reports to inform the business analyst about the schedule and project cost

D.  

Provide the business analyst with access to the financial and scheduling information

Discussion 0
Questions 538

During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.

What should the project manager do?

Options:

A.  

Ask the human resources director to appoint a senior team leader

B.  

Inform the project sponsor about the possible delay

C.  

Directly manage the project team to avoid project delays

D.  

Provide mentoring to the newly appointed team leader

Discussion 0
Questions 539

A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.

Which action should the project manager take to improve the team's performance?

Options:

A.  

Set up a training session for all project team members

B.  

Reach out to the functional managers for support

C.  

Speak individually with each project team member about making the needed updates

D.  

Send an email asking all project team members to complete updates at the end of the day

Discussion 0
Questions 540

During the execution of a maintenance project the contractor submits an offer for additional work The project manager realizes that the activities billed are included in the initial scope of work.

What should the project manager do next in this situation?

Options:

A.  

Review the project scope and negotiate with the contractor

B.  

Refuse the offer as it is included in the initial project scope

C.  

Review the project costs and communicate this to the project sponsor

D.  

Submit a change request to approve the offer

Discussion 0
Questions 541

A product company is transforming the way it develops and releases products in the market Executives believe that this is a high-risk initiative, and this initiative must be successful

What should the project manager do in this scenario?

Options:

A.  

Develop a business case with assumptions for the new model

B.  

Develop a communications management plan to inform the employees about the new business model

C.  

Adopt an iterative rollout approach that delivers the highest business value earlier

D.  

Develop a detailed sprint plan with clear deliverables

Discussion 0
Questions 542

In an advanced stage of a project a stakeholder who is not receiving the project status report communicates this to the project manager After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.

What should the project manager do next1?

Options:

A.  

Update the communications management plan to include the missed stakeholder, and send the current project status documentation to this stakeholder

B.  

Inform the project sponsor that there are stakeholders who are not included in the communications management plan

C.  

Inform the stakeholder that the project team cannot provide information to anyone who is not registered in the project's communications management plan

D.  

Ask the stakeholder to get the project status report from another stakeholder listed in the communications management plan.

Discussion 0
Questions 543

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?

Options:

A.  

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project

B.  

Use lessons learned from the previous project as a guide for the current project's stakeholder register

C.  

Refer to the stakeholder register from the previous project as it was similar to the current project

D.  

Document in the risk register that the current project may have differentstakeholders than the previous project

Discussion 0
Questions 544

While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined The actual invoice payments received have also been late and were outside of the contracted payment schedule Recent invoices have only been partially paid

What should the project manager do?

Options:

A.  

Add nonpayment to the issue log and keep tracking payments

B.  

Hold a meeting with the client to address the issue

C.  

Review past projects for payment-related lessons learned

D.  

Conduct a meeting with the project team to update the procurement management plan

Discussion 0
Questions 545

for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier To stay on schedule, the vendor proposed replacing the sub- supplier's component with a similar part that is different from the one that is stipulated in the project specifications.

What should the project manager do next?

Options:

A.  

Accept the proposed replacement in order to keep procurement activities on track

B.  

Insist on using the component per the project specifications and air freight the equipment to mitigate the delay

C.  

Instruct the vendor to use the part that is compliant with the project specifications and update the schedule

D.  

Consult with a subject matter expert (SME) to see if the proposed change isacceptable

Discussion 0
Questions 546

A project manager has two projects that are being executed at the same time The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal In addition, the schedule does not have activities that can be overlapped

What should the project manager do?

Options:

A.  

Analyze both projects to determine the most effective use of common resources

B.  

Use resource optimization to justify requesting more resources for the critical project

C.  

Provide schedule optimization training to the project teams to improve their skills.

D.  

Apply fast-tracking techniques to compress the schedule of the critical project

Discussion 0
Questions 547

A new project manager is planning an information security project for a company that resides in different countries. What is the first step the project manager should take to gather customer requirements?

Options:

A.  

Conduct a stakeholder analysis to identify how regional policies may influence needs

B.  

Request relevant stakeholders to conduct an analysis and reach consensus independently

C.  

Conduct a project scope review workshop with relevant stakeholders.

D.  

Conduct project planning meetings in one location with relevant stakeholders

Discussion 0
Questions 548

As part of the strategic plan, a company decides to implement a new software platform to manage a centralized document repository. Some requirements are clear and some need more detail.

What should the project manager do first to decide how to manage this project?

Options:

A.  

Select a predictive development life cycle based on the team's experience

B.  

Determine the most appropriate life cycle approach for the project

C.  

Register all requirements into a backlog for further detailed analysis.

D.  

Split the requirements, put them into two separate projects, and apply different approaches

Discussion 0
Questions 549

During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy What should the project manager share with the key resource?

Options:

A.  

The updated benefits management plan

B.  

The updated scope management plan

C.  

The updated project management plan

D.  

The updated communications management plan

Discussion 0
Questions 550

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?

Options:

A.  

Increased bum rate

B.  

Increased cost

C.  

Increased technical debt

D.  

Decreased efficiency

Discussion 0
Questions 551

During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version

How can the project manager prevent this outcome in the new project?

Options:

A.  

Hire a team of external users to perform acceptance testing on the product.

B.  

Define a user focus group as external stakeholders with a high influence on outcomes

C.  

Hire a consultant to perform a benefit analysis as an input to the project charter.

D.  

Define a high-level risk and plan mitigation after completing the work breakdown structure (WBS

Discussion 0
Questions 552

One of the main inputs required for a deliverable is missing due to a miscommunication between the vendor and project manager Because of the missed deliverable, the critical path of the project is extended

What should the project manager do next?

Options:

A.  

Start an audit of the vendor's processes and procedures

B.  

Review lessons learned from previous projects with this vendor

C.  

Make a detailed analysis on vendor issues during the project

D.  

Execute a contingency plan to address the issue with the vendor

Discussion 0
Questions 553

A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other What should the project manager do?

Options:

A.  

Review lessons learned from previous projects that used the same team

B.  

Review the organizational culture, structure, and governance

C.  

Coordinate a meeting to understand the situation and resolve any conflicts.

D.  

Coordinate a meeting with regional managers to ask for support

Discussion 0
Questions 554

A project manager is implementing a new software system Some department staff members are questioning the necessity of the change and feel the new system will impede their current processes

What should the project manager have done at the start of the project to prevent this resistance?

Options:

A.  

Created a communications management plan that outlined the method of communicating to stakeholders.

B.  

Ensured that the company culture encourages changes before accepting the project

C.  

Encouraged leadership to discuss the change with departments that are typically resistant to change

D.  

Involved stakeholders from all levels of the company so everyone understands the change

Discussion 0
Questions 555

An agile project is running its fifth iteration out of eight After the last iteration planning the team was informed that there is a new competitor in the market and it is necessary to move faster to ensure market share is not missed What should the project manager do?

Options:

A.  

Add the competitor's functionalities to the product backlog to improve the product

B.  

Ask the sponsor to add more people to the team

C.  

Help the team to find a new approach to launch the product as soon as possible

D.  

Ask the team to increase the velocity to launch the product as soon as possible

Discussion 0
Questions 556

A project has a very tight delivery schedule. The project is approaching the delivery date, and the project sponsor often sends the project manager alerts to avoid any schedule slippage . The project team has performed at an acceptable level until new, but the project manager wants to ensure that team’s performance level is performance is maintained until the end.

What action should the project manager take to motivate the project team's performance?

Options:

A.  

Award certificates of appreciation to encourage the team

B.  

Inform the team about the delivery pressure from the project sponsor

C.  

Send a formal notice to team members instructing them to maintain performance

D.  

Hire a few temporary team members to help with the additional work.

Discussion 0
Questions 557

A team member misses a project meeting without it being approved and has been penalized as defined in the ground rules. This team member, as well as other team members, insist that it is the first time they have seen this rule regarding the project and they do not agree with the penalty

What should the project manager have done to avoid this situation?

Options:

A.  

Ensured the team charter was developed by the team members

B.  

Ensured the team members are fully supportive of all decisions.

C.  

Distributed the project charter to all team members.

D.  

Used a charismatic leadership style

Discussion 0
Questions 558

During the execution of a project within an operations function the project manager encounters scope changes and a delay in the delivery of critical tasks How should the project manager address this situation?

Options:

A.  

Communicate the concerns to the project management office (PMO) during the weekly project reports

B.  

Call for a team meeting to decide if the changes should be included

C.  

Initiate the change request to modify the scope and adjust the timelines

D.  

Conduct an impact analysis and present the results to the steering committee for approval

Discussion 0
Questions 559

The project manager has observed that two team members have been arguing with each other openly at meetings To push their ideas through, each team member individually spoke with the sponsor directly and made decisions without informing the project manager or other team members

What two actions should project manager take? (Choose two)

Options:

A.  

Ask the team members to work it out themselves

B.  

Discuss this situation with other project managers and ask for advice

C.  

Reiterate ground rules at the next meeting and ensure that all team members are clear about these rules.

D.  

Address the behavioral issue with each team member

E.  

Discuss the behavior directly with their managers and request them to correct the behavior.

Discussion 0
Questions 560

As a member of an organizational change management team, a project manager must pass on any changes to the project team The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change

What should the project manager do?

Options:

A.  

Conduct meetings with resistant members to facilitate smooth project implementation

B.  

Meet with the team on a regular basis to ensure they are aware of changes.

C.  

Influence the team to communicate any changes

D.  

Check with the

Discussion 0
Questions 561

During the retrospective ceremony, the agile team is talking about the product owner’s expectations not being met What should the project manager have done at the beginning of the project?

Options:

A.  

Defined the expected agile team contribution in the creation of the backlog.

B.  

Assessed the capabilities of the agile team and planned for the required training

C.  

Defined the team ground rules and shared project vision.

D.  

Communicated project vision and sprint goals clearly to the team

Discussion 0
Questions 562

A new project manager is assigned to a project midway through its implementation During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using

What should the project manager have done to avoid this issue?

Options:

A.  

Referred to the communications management plan

B.  

Validated the issue log

C.  

Validated the project artifacts

D.  

Performed expert judgment

Discussion 0
Questions 563

The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?

Options:

A.  

Ask the team to work overtime to complete the deliverable on time

B.  

Evaluate the situation and identify ways to compress the schedule without impacting baselines

C.  

Check the scope to verify if there is scope creep and get the project on schedule

D.  

Submit a change request to the project sponsor to change the schedule

Discussion 0
Questions 564

A project manager is in a learn meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change What should the project manager do?

Options:

A.  

Make the decision on behalf of the organization

B.  

Review the stakeholder map along with the organizational chart and delegate the most senior person to make the decision

C.  

Schedule a project decision meeting with all stakeholders to discuss the decision.

D.  

Follow the stakeholder engagement plan

Discussion 0
Questions 565

To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations

What should the project manager do?

Options:

A.  

Review the organizational process assessment to determine if a contingency reserve was considered in the budget estimate

B.  

Review the historical information and lessons learned from last year’s project to justify the new budget estimate

C.  

Change the budgeting technique to a more accurate, bottom-up cost estimation.

D.  

Use soft skills to convince the project sponsor to approve the new budget estimate

Discussion 0
Questions 566

Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects

How should a project manager solve this issue?

Options:

A.  

Propose implementing a new project management information system (PMIS).

B.  

Request a meeting with senior management to escalate the situation

C.  

Promote adoption of the communications management plan with the project team.

D.  

Host a team-building event to develop team cohesion and improve communication

Discussion 0
Questions 567

During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule What should the project manager do first?

Options:

A.  

Update the issue log and act to minimize the impact

B.  

Update the schedule to include the delay

C.  

Add the risk and the delay to the risk register

D.  

Escalate to the management team for delay approval

Discussion 0
Questions 568

The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete The project manager reviews the work breakdown structure (WBS) and confirms that the component Is included.

What does the project manager need to do first?

Options:

A.  

Raise a change request to immediately implement the printing module component.

B.  

Escalate this issue to the project sponsor immediately

C.  

Ask the project team to conduct a quality audit of the printing module components.

D.  

Meet with the project team to understand the issue and define actions.

Discussion 0
Questions 569

In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1 25 The project manager must provide the first project status review soon and wants to emphasize that the project is under control

How should the project manager report the project status to key stakeholders?

Options:

A.  

Prepare a detailed presentation for stakeholders on earned value including how it is calculated and the project's current earned value results

B.  

Report that the project is behind schedule but that an additional experienced resource can be added to stay within schedule and maintain the budget.

C.  

Perform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to demonstrate that the project is under control.

D.  

Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away

Discussion 0
Questions 570

A product owner presented the backlog to the team, and the team raised concerns over implementing some of the features due to various impediments What should the project manager suggest that the product owner do next?

Options:

A.  

Ensure that the impediments are captured and prioritized based upon the highest valued features

B.  

Estimate the financial impact of the impediments and request additional funding

C.  

Begin to remove the impediments, starting with the easiest ones first, to foster team accomplishment

D.  

Capture the impediments and inform management that their assistance is neededin resolving the impediments

Discussion 0
Questions 571

A project manager presented the project schedule to the mam stakeholders They have requested that the project be completed two months earlier than the scheduled date

What should the project manager do?

Options:

A.  

Hold a stakeholder meeting to align timelines and scope expectations.

B.  

Crash the schedule to shorten the timeline while keeping the scope unchanged

C.  

Update the cost management plan to allocate more resources to the project to finish the scope earlier.

D.  

Reduce the scope of the project by removing activities and shortening the timeline

Discussion 0
Questions 572

A newly formed team has become accustomed to agile practices The project lead has noticed that while they are performing according to expectations, there is boredom with daily team practices among many of the team members.

What should the project lead do in this situation?

Options:

A.  

Challenge the team to find new ways to achieve higher levels of performance to improve the situation.

B.  

Speak with individual team members to determine what they would like to do to improve the situation in the team

C.  

Have the team inform senior management of the situation and ask for recommendations.

D.  

Allow the team to self-organize and have them analyze the situation in their retrospective session and self correct

Discussion 0
Questions 573

During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?

Options:

A.  

Check the approved list of requirements to see if there are any missing items.

B.  

Work with the stakeholder to improve the requirements' acceptance criteria

C.  

Review the requirements traceability matrix with the concerned stakeholder

D.  

Discuss with the stakeholder which additional requirements should be added

Discussion 0
Questions 574

An agile project is in its eighth iteration out of 16 After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply

Which two actions should the project manager take? (Choose two)

Options:

A.  

Ask the team members to analyze the impact of including this regulation

B.  

Ask the stakeholders about the priority of this regulation

C.  

Ask the product owner to include the requirements in the product backlog

D.  

Ask the security department for details about regulations

E.  

Ask the team members to include the requirements in the next iteration

Discussion 0
Questions 575

An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product's feasibility of functionality and accelerated testing What should the project manager do as a servant leader?

Options:

A.  

Support the team as necessary to find the minimum viable product (MVP).

B.  

Amend the project budget to include MVP testing

C.  

Submit a change request to the project sponsor for accelerated testing.

D.  

Develop the product as per the schedule to perform integration and testing

Discussion 0
Questions 576

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

Options:

A.  

Plan for overtime apply crashing and fast tracking and share the risk of failure with project stakeholders

B.  

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.  

Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule

D.  

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Discussion 0
Questions 577

A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders The project manager has been assigned and is now in the project planning phase

What item(s) should the project manager develop first?

Options:

A.  

A product backlog and identification of the features to be delivered

B.  

A business case and scope document

C.  

A communications management plan that addresses the team's needs

D.  

A risk management plan to incorporate known risks

Discussion 0
Questions 578

A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.

Which activity should be considered as a priority?

Options:

A.  

Mark the product backlog completion status and update the communications management plan.

B.  

Ensure that knowledge transfer activities are executed as planned

C.  

Release the resources and plan for a project completion celebration.

D.  

Hold a steering committee meeting to inform them of the project completion

Discussion 0
Questions 579

A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks

Drag each risk type on the left to its correct example on the right

Options:

Discussion 0
Questions 580

A company's project management office (PMO) has been trying to implement an adaptive approach in the project management framework and a project manager has been asked to use adaptive tools in their next project This is not the first time the request has been made and the previous project failed when adaptive tools were implemented

What should the project manager do?

Options:

A.  

Prepare a change request and seek approval from the steering committee regarding the new project framework

B.  

Conduct individual interviews with key stakeholders in order to understand all concerns, then prepare a communications management plan

C.  

Bring in a third party company to develop and implement a hybrid framework for this specific project.

D.  

Recommend to the PMO that it is not the right time to start implementing adaptive tools in projects

Discussion 0
Questions 581

During the last sprint review, the mam stakeholder complained that the product was missing many features they had been expecting The project team argued that every increment met the acceptance criteria and was approved by the mam stakeholder The cost performance index (CPI) of the project is 1 15 and the schedule performance index (SPI) is 1.43

What should the project manager do?

Options:

A.  

Ask the project team to perform the modifications since the project budget and schedule can support them.

B.  

Ask the stakeholder to submit a change request to increase the budget and time for the modifications requested

C.  

Explain to the stakeholder that since the acceptance criteria for every increment were met the project can be closed.

D.  

Analyze the reason for the gap in understanding with both sides and negotiate a solution

Discussion 0
Questions 582

A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points

Which team is performing better?

Options:

A.  

Team A as they have calculated fewer story points than team B.

B.  

Team B as they have calculated more story points than team A

C.  

The team that completes the most stories selected from the sprint backlog

D.  

The team with the least amount of defects in their deliverables

Discussion 0
Questions 583

A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?

Options:

A.  

Ask the project sponsor for assistance in getting the budget back on track

B.  

Meet with the project team to analyze the actual cost to determine deviations

C.  

Inform the stakeholders that the project will be finished over budget.

D.  

Issue a change request including the analysis to increase the budget

Discussion 0
Questions 584

A company is changing their current business model The change requires implementing a complex project using multiple agile teams.

What three options should the project manager have the testing team adopt as testing mechanisms? (Choose three)

Options:

A.  

Independent personal testing

B.  

Security and performance testing

C.  

An experimental approach to cover all possible choices

D.  

Story testing

E.  

Tests based on behavior and test-driven development

Discussion 0
Questions 585

A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts What should the project manager do in this situation?

Options:

A.  

Work to understand the key stakeholder's concerns and provide feedback in regular project status reports

B.  

Arrange an ad hoc meeting to address the key stakeholder's concerns with team members

C.  

Reinforce with the key stakeholder that the project is performing on schedule\

D.  

Escalate the situation to the project sponsor because the key stakeholder's behavior is impacting progress

Discussion 0
Questions 586

An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures What should the project manager do to help avoid this situation in the future?

Options:

A.  

Switch to a Kanban approach, implementing features on a first-come, first-serve basis, fostering a sustainable pace

B.  

Review the velocity of the team over the last several sprnts and adjust the plan accordingly

C.  

Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan

D.  

Replace junior team members with more experienced ones and negotiate the project scope to compensate for the budget gap

Discussion 0
Questions 587

Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members

What should the project manager do?

Options:

A.  

Encourage frequent small team meetings with two or three team members.

B.  

Give up the daily standup and replace it with a daily report

C.  

Let the team members decide themselves if they want to join the meeting.

D.  

Require all team members to join the daily standup regardless of the meeting time

Discussion 0
Questions 588

During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation How should the project manager respond?

Options:

A.  

Tell the junior team member that the information is available in lessons learned

B.  

Offer guidance and follow up with some developmental activity for the junior team member

C.  

Inform the junior team member that risk mitigation is not part of their work

D.  

Refer the junior team member to the senior team member who develops the risk mitigation strategy

Discussion 0
Questions 589

The project manager has learned that the project sponsor is unhappy with the development of the project requirements In order to realign the project with the sponsor's expectations, what should the project manager do?

Options:

A.  

Review the project goal diagram with the team.

B.  

Perform a stakeholder evaluation

C.  

Confirm which templates the team should be using

D.  

Review the risk management plan

Discussion 0
Questions 590

In an industrial plant, the owner has decided to add more capacity to the plant by installing a new machine and updating the software used in production. This capacity enlargement will occur while the plant is still functioning and producing The software update will be accomplished using an agile approach in order to minimize risk The machine procurement, installation, and integration will be accomplished using predictive approaches

What types of communications will the project manager have to design into the schedule management plan to ensure the project will be on schedule'’

Options:

A.  

Weekly colocated meetings with the relevant stakeholders

B.  

Biweekly conference calls with the relevant stakeholders

C.  

Weekly one-on-one meetings with each of the relevant stakeholders

D.  

Biweekly written status reports from the relevant stakeholders

Discussion 0
Questions 591

The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline There have been complaints from some stakeholders about some of the team members' performance The project manager wants to understand the situation and provide feedback to the team as soon as possible

What three actions should the project manager take to address this situation? (Choose three)

Options:

A.  

Define team ground rules

B.  

Perform a retrospective session

C.  

Implement daily team meetings.

D.  

Request a manager performance review

E.  

Conduct an annual review.

Discussion 0
Questions 592

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME) The SME refuses to accept this rejection and does not want to continue the project without the change

What should the project manager have done to avoid this situation?

Options:

A.  

Requested that the sponsor approved the change request first.

B.  

Assessed the change's overall impact to the project before submission

C.  

Ensured that the change request was aligned with the project scope

D.  

Submitted the change request directly to the CCB

Discussion 0
Questions 593

A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization's senior management and external stakeholders. What should the project manager do?

Options:

A.  

Review the stakeholder register and ensure that communications are being followed in line with the communications management plan.

B.  

Isolate the project team from external factors such as senior management and stakeholders so that decisions can be made more quickly

C.  

Review the remaining scope and rebaseline the project’s schedule to take into account delays in decision making

D.  

Review the adequacy of the project's governance and ensure that an appropriate structure is in place

Discussion 0
Questions 594

In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?

Options:

A.  

Ask the team member to enter this potential schedule delay in the risk register.

B.  

Explain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges

C.  

Actively listen to the team member and identify ways to support their needs in completing the tasks.

D.  

Set up team-building activities with the project team members to reduce tension

Discussion 0
Questions 595

A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results Which tool or technique should the project manager use?

Options:

A.  

Autocratic decision making

B.  

Expert judgment

C.  

Context diagram

D.  

Change control tools

Discussion 0
Questions 596

A team is currently working on a mobile app solution. During sprint execution, one of the developers requires clarification about the acceptance criteria for a particular task

What should the project manager do to obtain the information required by the developer?

Options:

A.  

Request direction from the project sponsor

B.  

Write an email to the client requesting clarification

C.  

Seek support from the development manager.

D.  

Work with the product owner to clarify the requirement

Discussion 0
Questions 597

A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches The scope of the project contains a number of unclear requirements.

How should the project manager plan the delivery of the project?

Options:

A.  

Wait for the requirements to be more clear before any further action is taken on the project

B.  

Ignore the unclear requirements and focus on the delivery plan of the project

C.  

Escalate the issue of unclear requirements to the management team and wait for final authorization

D.  

Break down the requirements and prioritize the requirements into iterative work packages

Discussion 0
Questions 598

After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run. What two actions should the project manager take? (Choose two)

Options:

A.  

Prepare the lessons learned from the project phase.

B.  

Obtain official approval on the new process from the various countries

C.  

Send a questionnaire to the project participants and seek their feedback.

D.  

Refer to the communications management plan

E.  

Deliver the project materials to the users and see if they have any comments

Discussion 0
Questions 599

A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?

Options:

A.  

Ensure the stakeholder engagement plan is accurate and properly documented.

B.  

Review the lessons learned from the previous project

C.  

Identify the risk of implementing the new solution and evaluate the impact on the project.

D.  

Create a lessons learned document for the initiation phase

Discussion 0
Questions 600

An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.

What should the project manager do?

Options:

A.  

Add 4 additional weeks to the schedule and request additional resources.

B.  

Ask the sponsor to obtain a special work permit to continue work.

C.  

Review the project management plan to see the impact of the possible delay.

D.  

Crash the resource management plan to keep the schedule on track.

Discussion 0
Questions 601

Project team member A has a conflict with project team member B. The project manager believes project team member A's behavior is unacceptable. However, project team member A believes their behavior is appropriate.

What should the project manager do?

Options:

A.  

Review the resource requirements to determine if the project team member is a good fit.

B.  

Add an agenda item to the next team meeting to manage the conflict.

C.  

Ask the project team member to review the team charter and follow up with a one-on-one meeting.

D.  

Review the roles and responsibilities of each team member with the team.

Discussion 0
Questions 602

During a design workshop, the engineers ask the project manager about the safety prerequisites for the new product's operating procedures.

What should the project manager do?

Options:

A.  

Provide the team with the enterprise environmental factors (EEFs).

B.  

Run a benchmark with similar sites to compare compliance constraints.

C.  

Look into lessons learned documentation for similar projects.

D.  

Hire a specialized engineer to support the design team.

Discussion 0
Questions 603

A project is approaching successful completion, and all stakeholders are really proud of the achieved results. The project management office

(PMO) recommends the project manager to lead the next similar project.

What should the project manager do next?

Options:

A.  

Engage key stakeholders to complete and deliver lessons learned.

B.  

Select the same stakeholders for the next project to avoid doing knowledge transfer.

C.  

Present the project achievements and delegate knowledge transfer to the steering committee.

D.  

Request the PMO to manage the lessons learned repository.

Discussion 0
Questions 604

Anew major road project is starting, and the contractor has contractually committed to submitting regular status reports and participating in integration meetings. Halfway through the project life cycle, the contractor stops participating in meetings and submitting reports, stating these items consume too much time.

What should the project manager do first?

Options:

A.  

Assess the risk of the contractor not attending meetings and submitting reports for the rest of the project and escalate it to the project sponsor.

B.  

Submit a claim for not fulfilling the contract terms and handle the claim in accordance with the alternative dispute resolution.

C.  

Remind the contractor that they committed to attending meetings and submitting reports per the contract.

D.  

Speak with the company’s lawyer and request that they demand the contractor fulfill their contractual commitments.

Discussion 0
Questions 605

An agile project is running its third iteration with a duration of 2 weeks. A new operations director, who only has a predictive background, started

working at the company. In the first meeting with the project manager, the director demands a weekly project status report.

What should the project manager do?

Options:

A.  

Invite the director to attend the daily standup meetings.

B.  

Share this with the team and ask them to develop reports for the director.

C.  

Introduce the agile aspect to the director and agree on a solution.

D.  

Explain to the director that agile projects have live reports.

Discussion 0
Questions 606

A company faces challenges and decides to cut a few product features from the main project due to market conditions. During a status meeting, a new stakeholder expresses concern about the discrepancies between the current deliverables and the deliverables agreed upon in the project charter.

What should the project manager do first?

Options:

A.  

Ask the project team to increase the number of updates provided to the stakeholder.

B.  

Determine the root cause of the discrepancy with the project team and agree on the project scope.

C.  

Ask the new stakeholder to submit a change request to the change control board (CCB).

D.  

Review the project objectives for alignment with the intended corresponding business value.

Discussion 0
Questions 607

A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.

What should the project manager do next?

Options:

A.  

Suggest that the team member contact the IT department.

B.  

Facilitate a priority resolution of the issue with the IT department.

C.  

Update the issue log and escalate the problem to the product owner.

D.  

Ask the other team members to step in and do the work.

Discussion 0
Questions 608

During execution of a complex project, the project manager encounters numerous change requests from various teams. These changes may result in the project not meeting its objectives.

How should the project manager ensure that these changes are managed effectively?

Options:

A.  

Include the changes in the backlog and review priorities with the product owner.

B.  

Record the changes using the risk register and continue monitoring.

C.  

Deny the change requests and keep delivering the project as planned.

D.  

Review the project and communications management plan with the main stakeholder.

Discussion 0
Questions 609

A team is delivering features to a customer at every iteration. After completing each iteration, the customer is invited for a review. However, the customer is frequently not

available and the review is often delayed, which results in increased rework for the team.

What should the project manager do?

Options:

A.  

Ask the customer to review the deliverables in each iteration based on their availability.

B.  

Request the customer to clarify all requirements at the start of each iteration.

C.  

Plan ahead and define the best way to review the deliverables with the customer.

D.  

Include the customer in daily project activities to gain the required guidance.

Discussion 0
Questions 610

An organization embarking on a significant transformation initiated a project to improve and document business processes. One of the objectives of the project is to implement agile project delivery.

What is the main reason for adopting agile?

Options:

A.  

Projects will be completed faster, saving time and money.

B.  

Projects will deliver early and use value based on priority.

C.  

Projects will be delivered with very low risk to the organization.

D.  

Projects will be delivered with significant cost savings.

Discussion 0
Questions 611

A project manager joins an existing project. One project stakeholder is unhappy with the frequency and types of project updates received and has made a request for more What should the project manager do next?

information to be shared.

Options:

A.  

Inform the stakeholder to wait for the annual stakeholder review meeting

B.  

Schedule a meeting with the stakeholder to better understand their request

C.  

Update the project communications management plan immediately

D.  

Consult the scope baseline document to track project updates

Discussion 0
Questions 612

At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project manager mainly make reference to?

Options:

A.  

Feedback from the project sponsor

B.  

Agreed-upon key performance indicators (KPIs)

C.  

Input from project stakeholders

D.  

Competencies of team members

Discussion 0