Pre-Summer Sale 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exams65

ExamsBrite Dumps

Project Management Professional (PMBOK 7th Version) Question and Answers

Project Management Professional (PMBOK 7th Version)

Last Update Apr 15, 2026
Total Questions : 2191

We are offering FREE PMP PMI exam questions. All you do is to just go and sign up. Give your details, prepare PMP free exam questions and then go for complete pool of Project Management Professional (PMBOK 7th Version) test questions that will help you more.

PMP pdf

PMP PDF

$139.65  $399
PMP Engine

PMP Testing Engine

$157.15  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$209.65  $599
Questions 1

A project manager works for a large software development company that has multiple strategic business groups. The project manager has been assigned to develop maintenance planning software for a power plant. The project manager heard that a similar project that was executed by another business group in the company recently failed. The project manager is concerned about the project's performance and wants to take steps to help the project succeed. What should the project manager do?

Options:

A.  

Evaluate the project risk and try to replace the project with another one within the organization.

B.  

Inform the project sponsor about the risk and try to convince them to withdraw the project.

C.  

Study and apply the lessons learned from the failed project so that this project does not follow the same pattern.

D.  

Continue executing the project using the project manager's usual methods as all projects are unique.

Discussion 0
Questions 2

A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to

take action in advance to ensure the project succeeds.

What should the project manager do?

Options:

A.  

Evaluate the project risk and add external experts to address the potential risks.

B.  

Inform the project sponsor about the risk and try to convince them to withdraw from the project.

C.  

Continue executing the project as planned and add more resources if they are required.

D.  

Review the lessons learned on similar projects so that they do not fall back into the same pattern.

Discussion 0
Questions 3

A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items

What should the project manager do as a servant leader?

Options:

A.  

Ask the sponsor to submit a change request to the change control board (CCB)

B.  

Support the product owners decision to change the priority of the product backlog items

C.  

Accept the request and include the product backlog items in the next sprint

D.  

Review the impact of the change on the schedule management plan baseline

Discussion 0
Questions 4

A project manager assigned to an engineering construction project is receiving questions from the site engineers. Several questions are related to carrying out activities to meet timelines that compromise the work crew's safety. When reviewing these questions, the project manager realizes that the engineers do not (eel empowered to make decisions.

How should the project manager address this?

Options:

A.  

Consult the previous project manager to discuss how they managed these questions.

B.  

Ensure all engineers are aware that questions should only be submitted in their weekly reports.

C.  

Email the company vision to the engineers and tell them they need to meet deadlines

D.  

Reinforce to all engineers the company vision of a safety-first approach to project activities.

Discussion 0
Questions 5

Eight people have been working on a project for an extended period of time. The

scope has changed significantly and the product owner has been replaced multiple times. The

team members are feeling disassociated from the project.

What should the project manager do to ensure team alignment with the goals?

Options:

A.  

Ask the new product owner to explain the importance of the project.

B.  

Email the team a detailed outline of the business requirements.

C.  

Review the project charter with the team.

D.  

Facilitate a discussion of the vision for the project.

Discussion 0
Questions 6

A project manager has noticed that a critical team member is consistently arguing

with a client. This has started to have a negative effect on the meetings.

How should the project manager address this?

Options:

A.  

Explain the impact of the scenario to the project team member.

B.  

Remove the project team member from all future meetings.

C.  

Talk to the client privately to highlight the situation.

D.  

Recommend a performance improvement plan to the project team member.

Discussion 0
Questions 7

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?

Options:

A.  

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team

B.  

Escalate the issue to the functional manager

C.  

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training

D.  

Perform the quantitative risk analysis for the team member.

Discussion 0
Questions 8

A project manager is leading a progress review meeting when some stakeholders who are new to the project express concerns about not having access to previously shared deliverables. What should the project manager do?

Options:

A.  

Document the new stakeholders' concerns in the meeting minutes.

B.  

Schedule an ad hoc meeting with the new stakeholders to discuss concerns.

C.  

Use social media environments to share the project information

D.  

Use the project management information system (PMIS) to share information.

Discussion 0
Questions 9

A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances.

Risk Response Strategies Analyze if someone else could contribute Record the observations and move ahead Check for options to exclude the stakeholder

What should the project manager do to resolve the team member's concerns?

Options:

A.  

Use the withdraw/avoid technique to allow the individuals to resolve the issue between themselves.

B.  

Use a problem-solving approach and set up a discussion with the team lead and team member.

C.  

Establish guidelines for team leads to ensure that all team members are appropriately treated.

D.  

Provide direction to the team lead on how to resolve the issue with the team member directly.

Discussion 0
Questions 10

A team is developing an experimental program to be used by the public. What should

the project manager do to ensure the desired benefits are achieved?

Options:

A.  

Ensure that the project team fully tests the program.

B.  

Ensure a review is done with a representative group of users.

C.  

Meet with government officials to review policy requirements.

D.  

Document the features fully and update the specifications.

Discussion 0
Questions 11

During a scope validation exercise toward the end of a project, a project manager realizes that some operational project requirements were not captured in the project scope of work. Although completing these Items will have an Impact on the project's completion date. It will Increase the likelihood of customer acceptance.

What should the project manager do to address the issue?

Options:

A.  

Issue a change request to remove items from the scope of work and keep the project on schedule.

B.  

Issue a change request to include the additional scope, and track the completion of the work items.

C.  

Document the issue in the lessons learned document, and discuss this with the project sponsor.

D.  

Arrange to pass the cost to the operational area since the customer will benefit.

Discussion 0
Questions 12

Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution

document.

What should the project manager do to avoid a delay in the project?

Options:

A.  

Ask the accounting manager to delegate a team member who can support the project.

B.  

Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed,

C.  

Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource,

D.  

Begin discussions with other functional managers and meet with the accounting manager later.

Discussion 0
Questions 13

During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.

What should the project manager do to reduce exposure?

Options:

A.  

Report the risk owners to the project management office (PMO) with the recommendation to remove them from the team.

B.  

Reassign the outstanding risk tasks to other team members who have implemented their risk responses.

C.  

Ask the risk owners to implement the risk responses before the next meeting and present the results in the meeting.

D.  

Meet privately with the risk owners and work with them to address any impediments to the risk responses.

Discussion 0
Questions 14

A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.

What should the project manager do to communicate with the stakeholders?

Options:

A.  

Provide updates to the project sponsor to review and distribute to each stakeholder.

B.  

Use a single communication medium such as video teleconferencing to limit confusion.

C.  

Use a variety of communication methods that respect cultural, practical, and personal preferences.

D.  

Send frequent updates via email to each stakeholder because this is an information technology project.

Discussion 0
Questions 15

A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor

What should the project manager have created to prevent this situation1?

Options:

A.  

Resource breakdown structure

B.  

Work breakdown structure (WBS)

C.  

Team charter

D.  

Project charter

Discussion 0
Questions 16

An agile coach and technical writer for a globally distributed agile team are In a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but

the agile coach and technical writer feel that is an inconvenient time for them.

How does the project lead ensure adherence to agile practices?

Options:

A.  

Escalate to management that the agile process is not going to work and ask them to speak to the agile coach,

B.  

Have two separate daily standups, one for the agile coach and technical writer and one for the agile development team.

C.  

Have a discussion with the team on the approach and come to a decision on when the daily standups should be.

D.  

Inform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend.

Discussion 0
Questions 17

After months of careful planning and discussions with subject matter experts (SMEs). a new law is announced that may significantly impact the project budget. What should the project manager do first?

Options:

A.  

Consult the risk and issue logs.

B.  

Initiate a project change request.

C.  

Create a baseline impact assessment

D.  

Discuss with the project sponsor.

Discussion 0
Questions 18

A project manager has recently joined an organization and notices that the engineering manager shouts at the project manager during project meetings Also the procurement manager will not return calls and the accountant always insists the project manager clears approved budget line items with them personally before expensing

Which three corrective actions should the project manager perform? (Choose three)

Options:

A.  

Confront the people causing the stress directly with the aim of finding amicable solutions

B.  

Seek support from the project management office (PMO) on addressing issues affecting the project

C.  

Discuss the possible actions with the project sponsor

D.  

Avoid the people causing stress and request a transfer as soon as possible

E.  

Talk to the human resources (HR) manager about these concerns

Discussion 0
Questions 19

A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.

What should the project manager do?

Options:

A.  

Ask the client how the project will affect the client's organization and recommend that all impacted parties be involved.

B.  

involve an executive-level stakeholder at the project manager's own company to speak with the client's executive sponsor.

C.  

Perform an independent analysis to determine the stakeholders from the client's organization.

D.  

Defer to the judgment of the client's executive sponsor since they will determine whether the project is a success.

Discussion 0
Questions 20

During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead

handle this situation?

Options:

A.  

Support the team member by removing the blockers and impediments.

B.  

Allocate the blockers and impediments to the product owner to resolve.

C.  

Insist that the person who raised the blockers and impediments take ownership.

D.  

Add any blockers or impediments to the risk register,

Discussion 0
Questions 21

A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value

What should the new project manager do next?

Options:

A.  

Review the benefits management plan

B.  

Refer to the lessons learned from the first phase

C.  

Consult the project reports from the previous project manager

D.  

Collect information from related departments

Discussion 0
Questions 22

In an agile project, two key stakeholders disagree about a major new requirement. Recognizing that this could lead to potential issues, what should the project manager do next?

Options:

A.  

Facilitate a meeting with the stakeholders and product owner to clarify the new need,

B.  

Update the acceptance criteria documentation to clearly reflect what was approved.

C.  

Review the new requirement and update all the stakeholders accordingly.

D.  

Ask the two key stakeholders to agree on the requirement based on a Pareto analysis.

Discussion 0
Questions 23

A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.

How should the project manager ensure the product increments deliver the anticipated requirements?

Options:

A.  

Appoint a dedicated product manager for the duration of the release

B.  

Have the customer approve the product increment features.

C.  

Ensure every user story has acceptance criteria.

D.  

Track business outcomes for planned user stories.

Discussion 0
Questions 24

During the final iteration of the execution phase, the project has a cost performance

index (CP!) of 0.9 and a schedule performance index (SPI) of 1.0.

How should the project manager avoid a budget shortfall?

Options:

A.  

Follow the risk management plan.

B.  

Reduce the team effort utilization.

C.  

Look for cost-saving opportunities.

D.  

Submit a change request to add to the management reserve.

Discussion 0
Questions 25

we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.

What should the project manager do?

Options:

A.  

Discuss the issue with the team to resolve the disagreement.

B.  

Ensure that there is consensus among the project stakeholders.

C.  

Discuss the issue during the next sprint planning meeting.

D.  

Support the outcome of the architects’ agreement.

Discussion 0
Questions 26

A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.

How should the project manager resolve this situation in their new role as servant leader?

Options:

A.  

Review the organizational process assets (OPAs) to find similar situations and review the resolution actions taken,

B.  

Request that the team use the next sprint to complete all technical debt remaining from the previous sprints.

C.  

Extend the sprints to 3 weeks to allow the work requested by the product owner to be completed.

D.  

Encourage the whole team to be empowered and accountable for the decisions made according to their roles,

Discussion 0
Questions 27

A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?

Options:

A.  

Inform the design team to ensure compliance during the product design phase

B.  

Inform the quality team that they need to ensure that the product is in compliance

C.  

Ensure that compliance is explicitly mentioned in the relevant requirements

D.  

Meet with the team and remind them of the compliance requirements

Discussion 0
Questions 28

A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.

What should the project manager do?

Options:

A.  

Reject the risk because the team is not in agreement on escalating it

B.  

Include the risk in the risk assessment and evaluate it with the team

C.  

Accept the risk and immediately enter the risk into the risk register

D.  

Discuss with the consultant to understand why the risk was escalated

Discussion 0
Questions 29

A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use to update the details and communicate to relevant stakeholders?

Options:

A.  

Risk register

B.  

Project schedule

C.  

Change request

D.  

Issue log

Discussion 0
Questions 30

During the execution phase of a project, all project team members were forced to work from their homes rather than in person During this time, the project manager discovered that 0.-10 team member has made disrespectful remarks about another team member to other team members.

How should the project manager handle this situation''

Options:

A.  

Instruct the team members involved to resolve the issue among themselves

B.  

Discuss the issue with the steering committee to determine the proper course of action.

C.  

Coordinate a video conference with the offending team member to resolve the issue

D.  

Reassign the offending team member to a different project

Discussion 0
Questions 31

In experienced project manager has never managed an agile project until now. Due to the uncertainty of the project, the project manager is struggling with the definition of the project scope and is taking a long time trying to define it.

What should the project manager do?

Options:

A.  

Submit a change request to leverage previous experience and manage the project using a predictive approach,

B.  

Schedule a daily project definition meeting with the team to define the project scope before starting the execution.

C.  

Start executing the project as the scope will be defined and redefined throughout the project.

D.  

Obtain partial approval from the product owner to baseline the project scope plan before starting the execution.

Discussion 0
Questions 32

A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours, The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues.

What should the project lead have done initially to avoid this situation?

Options:

A.  

Reviewed the project management plan

B.  

Created a detailed operations manual

C.  

Increased support hours for the hours of operation

D.  

Involved operations stakeholders during planning

Discussion 0
Questions 33

A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a

requirement for a user experience design approach.

Which project management approach should the project manager use?

Options:

A.  

The software development has a high uncertainty level, so an agile approach is recommended for the project.

B.  

The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.

C.  

The deliverables are significantly different, so the project should be split into two projects that are driven by a program.

D.  

A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.

Discussion 0
Questions 34

A company is transitioning their projects to utilize hybrid project management approaches While putting together their project team, the project manager discovers the requirements from the customer are unclear and also realizes that the team members are lacking critical technical stalls needed for project success. However the customer will not accept any changes to the requirements

What should the project manager do to resolve this issue?

Options:

A.  

Submit a change request to adapt the objectives of the project to the current situation

B.  

Ask the scrum master to refine the user stones to improve the team members' understanding

C.  

Find and provide training to the project team members who do not have the required skills

D.  

Extend the duration of standup meetings to include skill transference from trained to untrained members

Discussion 0
Questions 35

As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the

project. How should the project manager resolve this?

Options:

A.  

Escalate a schedule risk to the sponsor.

B.  

Conduct team-building exercises.

C.  

Stop the project and perform a team skill assessment.

D.  

Make sure that the team has a full understanding of the scope.

Discussion 0
Questions 36

A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager's supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team

What should the project manager do?

Options:

A.  

Send a formal communication regarding the missed milestone

B.  

Delay sending a formal communication until the project team catches up

C.  

Ask for a meeting with the sponsor to decide whether to send the formal communication

D.  

Forego the formal communication and have a conversation with the supervisor

Discussion 0
Questions 37

A project team delivered a critical deliverable to the customer. The customer

complained that the maintenance manual was not included.

What should the project manager do next?

Options:

A.  

Submit a change request to include the manual.

B.  

Add the needed manual and update the risk log.

C.  

Review the stakeholder engagement plan.

D.  

Review the terms and conditions of the contract.

Discussion 0
Questions 38

A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.

What should the project manager do?

Options:

A.  

Ask senior management to communicate with these departments.

B.  

Hire a project management consultant to help resolve the issue

C.  

Convince senior management to introduce rewards to resisting departments.

D.  

Understand the user concerns and revisit the stakeholder engagement plan

Discussion 0
Questions 39

A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?

Options:

A.  

Stakeholder analysis

B.  

Resource needs analysis

C.  

Accommodations assessment

D.  

Team member assessment

Discussion 0
Questions 40

A project team consists of members based in country A and subject matter experts

(SMEs) based in country B with a 12-hour time difference. What can the project manager do

to improve interactions between the team members in both countries?

Options:

A.  

Ensure full participation of both the product owner and business SMEs in scopeplanning sessions.

B.  

Identify virtual communication methods and arrange for regular team meetingsaccordingly.

C.  

Explore the opportunity to have both teams colocated.

D.  

Plan for frequent face-to-face meetings.

Discussion 0
Questions 41

Vendor A submitted a bid for US$500,000. There is a 65% probability that the

vendor will deliver behind schedule with a cost overrun of US$ 100,000. The vendor will come

in ahead of schedule for a savings of US$50,000.

What should the project manager determine as the value of the vendor's bid?

Options:

A.  

US$650,000

B.  

US$452,500

C.  

US$547,500

D.  

US$582,500

Discussion 0
Questions 42

Two team members are arguing about which technology they should use when implementing iteration tasks. The predictive approach was broken into several legations that need to be completed on time so as not to jeopardize the projects timely completion.

What should the project manager do to resolve this issue and help the team move on to the next iteration?

Options:

A.  

Postpone the selection of the technology used until more information is gathered

B.  

Suggest their own approach to solve the issue and ask the team to follow it

C.  

Call for an open dialogue which the team will arrive at through consensus

D.  

Allow the team to decide since the teams should be autonomous

Discussion 0
Questions 43

A project manager is leading an electrical project that spans five towns. The project

manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.

What should the project manager do?

Options:

A.  

Change the project scope and seek approval to exclude this town from the overallproject.

B.  

Engage with the town's authorities to discuss the reason for the change in commitmentand agree on a solution.

C.  

Instruct the team to move to the next town and continue the project to avoid further delays.

D.  

Retrieve all minutes of stakeholder engagements and send to the town as a reminder of their commitment to the project.

Discussion 0
Questions 44

A customer wants to launch a new product in the market and an agile team is set up to work on this project for 9 months After 1 month the customer feels that it would be better to release the product 2 months earlier than the planned date. The task is now assigned to the most talented resource in the organization to this project tor an early finish.

Which risk management strategy has been adopted in this scenario?

Options:

A.  

Shared

B.  

Accepted

C.  

Enhanced

D.  

Exploited

Discussion 0
Questions 45

A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.

What should the project manager do to address this situation?

Options:

A.  

Inform the steering committee of the situation and request additional resources.

B.  

Coordinate virtual and face-to-face meetings at each site to improve communication

C.  

Coordinate virtual meetings to assess the project team's communication needs

D.  

Inform the project sponsor of this situation and request cultural orientation training.

Discussion 0
Questions 46

A project team member is struggling to understand a specific requirement. How should a servant leader address this issue?

Options:

A.  

Assess and evaluate the team member's skills to ensure alignment to the particular requirement and solution

B.  

Reassign the requirement to another team member who may have ideas on how to meet the requirement

C.  

Assist by connecting the product owner with the team member to discuss what problem is to be solved

D.  

Deprioritize the requirement and assign a task tor it to be restated to provide the necessary clarity

Discussion 0
Questions 47

One of the project manager's important assignments is to formally revise project compliance as it pertains to user data protection regulations. What should the project manager

do to monitor compliance?

Options:

A.  

Assess the risk register.

B.  

Conduct project reviews.

C.  

Perform retrospectives.

D.  

Complete sprint reviews

Discussion 0
Questions 48

Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.

What tool should the project manager use to conduct meetings with the project team and clients?

Options:

A.  

Use a third-party instant messaging tool.

B.  

Use a password-enabled audio/video product,

C.  

Use a popular social media platform.

D.  

Use a collaborative electronic whiteboard,

Discussion 0
Questions 49

A project team member is providing updates to assigned work and reports a task as complete, As the project progresses, it is observed that the task is not fully complete.

What should the project manager do moving forward?

Options:

A.  

Provide clear expectations around task requirements.

B.  

Review the task list with the team on a regular basis,

C.  

Provide templates for the product owner to use in the future.

D.  

Review the task with the sponsor to see if they are satisfied.

Discussion 0
Questions 50

A global program is being kicked off, and various distributed teams are Involved in delivering the initiative. Besides planning and executing the scope for the initiative, team interactions must be considered.

How should the project teams interact in their meetings?

Options:

A.  

Phone conversations

B.  

Encrypted emails

C.  

Videoconferencing

D.  

Chat conversations

Discussion 0
Questions 51

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?

Options:

A.  

Ask the leadership team for help obtaining the needed staff.

B.  

Have a direct talk with the functional manager to understand the reasons behind their attitude.

C.  

Evaluate the impact caused by the delay of forming the team and confront the functional manager.

D.  

Check with human resources (HR) regarding the availability of staff.

Discussion 0
Questions 52

A project manager has just completed a fixed-price project and the stakeholder is unhappy with the result What should the project manager do?

Options:

A.  

Explain to the stakeholder that any modifications require additional budget

B.  

Review the missed program deliverables with the project team

C.  

Review the project charter for the project approval criteria

D.  

Speak with the team's manager to get extra hours from the team

Discussion 0
Questions 53

A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception about the company's brand.

What should the project manager have done to prevent this?

Options:

A.  

Monitored progress in achieving the business value throughout the project

B.  

Asked for additional time to achieve the project goals and increase business value

C.  

Increased the number of project resources to ensure attainment of the business value

D.  

Reviewed previous projects’ lessons learned and applied them to this project

Discussion 0
Questions 54

A project manager /s planning a project and identifies that legislation requirements for specific project tasks will be changing. This will occur half way through the project execution

phase and will affect a few key workers’ licenses, which will become noncompliant.

What should the project manager do?

Options:

A.  

Start scheduling the training for key workers now to ensure compliance.

B.  

Maintain the current key workers since the project has already started.

C.  

Update the project charter to ensure the new legislation is addressed,

D.  

Start a recruitment drive for new workers with the licenses required.

Discussion 0
Questions 55

A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?

Options:

A.  

Rebaseline the project schedule to absorb the delay.

B.  

Report the delay with rectifying actions to the project management office (PMO).

C.  

Notify the project steering committee about the cause of the delay.

D.  

Report the delay with rectifying actions to the change control board (CCB) for review,

Discussion 0
Questions 56

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?

Options:

A.  

Move the solution designer to another team.

B.  

Review the process that resulted in this situation.

C.  

Stop work until the design document is completed.

D.  

Ask the team to document the design.

Discussion 0
Questions 57

A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?

Options:

A.  

Review the project scope to align the project teams

B.  

Review the resource management plan to align the project teams

C.  

Review the project integration plan to align the project teams

D.  

Review the work breakdown structure (WBS) to align the project teams

Discussion 0
Questions 58

One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority

What should the project manager do to mitigate the risk of not having the materials printed on time?

Options:

A.  

Meet with the manager to set a high priority for printing the materials

B.  

Create a change request to modify the print requirements

C.  

Include a risk response in the resource management plan

D.  

Purchase a high-volume printer specifically for this project.

Discussion 0
Questions 59

A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team

What should the project manager do to resolve this?

Options:

A.  

Facilitate a team-building meeting to help this issue

B.  

Allow the team members to remain in their former individual roles

C.  

Directly guide the team members on how to perform their tasks

D.  

Wait until some iterations are completed to intervene

Discussion 0
Questions 60

A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.

What should the project manager do?

Options:

A.  

Process a bank loan to pay the payroll of the third-party supplier.

B.  

Reassign resources from other projects to pay the third-party supplier.

C.  

Explain the third-party supplier situation to the client and request payment.

D.  

Inform the client that the project must be delayed until payment is received.

Discussion 0
Questions 61

A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix

What should the project manager do with regard to community engagement in this situation''

Options:

A.  

Include the local union representative in the high-power, high-impact stakeholder group

B.  

Focus on the sideward stakeholders only and let the organization manage the community.

C.  

Build channels to extend communication efforts to the local community

D.  

Use the city administration to address communication with the community

Discussion 0
Questions 62

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

Options:

A.  

Request for information

B.  

Scope statement

C.  

Issue log

D.  

Risk register

Discussion 0
Questions 63

A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?

Options:

A.  

Work with the product owner to evaluate and prioritize the requirements

B.  

Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list

C.  

Determine the expected benefits of each requirement to maximize the overall business value

D.  

Prioritize the requirements based on the hierarchical level of the requesting stakeholders

Discussion 0
Questions 64

A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity

issues joining team calls during the day.

What should the project manager do?

Options:

A.  

Procure tools that consume less bandwidth for internet calls.

B.  

Record the meeting to share with the team members who were unable to join.

C.  

Ask the team members to use chat tools as an alternative to calls.

D.  

Determine what the problem is and develop an action plan.

Discussion 0
Questions 65

A project learn member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.

What should the project manager do?

Options:

A.  

Assign an experienced resource to support the team member

B.  

Escalate the team member's performance to the project sponsor

C.  

Ask the team member to learn the new system as on-the-job training

D.  

Issue a change request to extend the project schedule

Discussion 0
Questions 66

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?

Options:

A.  

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.

B.  

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.

C.  

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,

D.  

Check with procurement to see if there is another previously used contractor who can develop the task.

Discussion 0
Questions 67

Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?

Options:

A.  

Organize a brainstorming session with the project team to address the issue.

B.  

Advise the project team on the importance of team engagement,

C.  

Invest in coaching and training for all project team members.

D.  

Escalate the issue with the human resource (HR) department to take action,

Discussion 0
Questions 68

A project manager for a large software delivery project is in the process of finalizing the project governance, The project manager would like to implement procedures that do not align with several policies required by the organization's project management office (PMO). The project manager

believes that the procedures outlined in the project governance will be necessary for this particular project due to the unique nature of the

technology.

What should the project manager do?

Options:

A.  

Engage stakeholders to modify policies outlined by the PMO.

B.  

Move forward with the project governance and inform the PMO.

C.  

Discuss the proposed changes with the PMO.

D.  

Disregard the initial procedures and follow the policies outlined by the PMO,

Discussion 0
Questions 69

A project manager has been asked for performance feedback regarding one of the team members The project manager would like to gather additional input from the project team because there are no metrics in place for evaluating employee performance.

What should the project manager do next?

Options:

A.  

Evaluate demonstrated task accountability

B.  

Determine the appropriate approach

C.  

Analyze team member influence

D.  

Identify levels of decision-making authority

Discussion 0
Questions 70

A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.

What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?

Options:

A.  

Receive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.

B.  

Organize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.

C.  

Issue the team lead a warning, and consider recommending the team lead for emotional intelligence training.

D.  

Find ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.

Discussion 0
Questions 71

During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?

Options:

A.  

Document the issues and extend the project delivery timeline.

B.  

Convene the steering committee and inform them of the impact to the project.

C.  

Prioritize the user stories with issues and have the team resolve them

D.  

Update the project management plan and risk management plan.

Discussion 0
Questions 72

A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.

What should the servant leader do to address this risk?

Options:

A.  

Include this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of everyiteration.

B.  

Forecast the cost of the risk to calculate the required contingency reserve that needs to be allocated if the risk materializes.

C.  

Ask the functional manager to educate the team about this risk and ensure that disciplinary actions will be taken.

D.  

Contact the human resources (HR) department to ensure that disciplinary actions will be taken if the employees disclose any confidentialinformation.

Discussion 0
Questions 73

The project management office (PMO) has recently adopted some agile practices. During an iteration a key stakeholder in the business is concerned with the benefits management plan in the project document repository and mentions that some benefits have not been updated.

What should the project manager do first?

Options:

A.  

Update the risk register in order to add the issue.

B.  

Review the issue log regarding the concern

C.  

Revise the benefits management plan

D.  

Assess the repository to check for inconsistencies.

Discussion 0
Questions 74

A key stakeholder has recently started in a company and has been assigned to a hybrid project. Although very experienced in their domain, the stakeholder has only been exposed to predictive project approaches.

What should the project manager do?

Options:

A.  

Inform the stakeholder that they must level their knowledge with other stakeholders.

B.  

Update the risk register with the potential impact and apprise the steering committee.

C.  

Inform the project management office (PMO) that the team will use a predictive approach for this project.

D.  

Allocate time to mentor the stakeholder in the selected project approach.

Discussion 0
Questions 75

A project manager gas been asked by the project manager office (PMO) to select the appropriate project management approach for three upcoming projects. Match the projects on the left with the approach that should be used on the right.

Options:

Discussion 0
Questions 76

One of the risks identified during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.

What should the project manager do?

Options:

A.  

Create a risk probability matrix to address the incompatibility.

B.  

identify an alternative component in case of incompatibility.

C.  

Use the contingency fund to redesign the interface if it is incompatible,

D.  

Require the vendor to redesign the incompatible component to fit the system.

Discussion 0
Questions 77

At the end of a third planning meeting, the client and a functional manager requested additional meetings to add more features to the product.

What should the project manager do to start building the product faster?

Options:

A.  

Allow the sponsor to determine how long the planning phase should last.

B.  

Allow the client ta determine how long the planning phase should last.

C.  

Ask the functional manager to work with the team to finalize planning and begin building the product.

D.  

Explain that more features can be planned in upcoming Iterations and begin building the product.

Discussion 0
Questions 78

A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team

members and stakeholders who have contradictory opinions.

What should the project manager do?

Options:

A.  

Meet with the stakeholders to determine the approach using the project goals and desired outcomes.

B.  

Leverage agile methods only as the project pertains to software implementation, which can be broken into increments.

C.  

Leverage hybrid methods as the project has a blend of work that needs to bring in both agile and predictive methods,

D.  

Determine what methods the team has been trained on and utilize those methods for the project.

Discussion 0
Questions 79

A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

Options:

A.  

Have a discussion with the sales team to find a solution to the issue

B.  

Validate the reason and add n as an issue m the issue log

C.  

Escalate the issue to the functional manager

D.  

Direct the sales team to speak with accounting to resolve the issue

Discussion 0
Questions 80

A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

Options:

A.  

Have a discussion with the sales team to find a solution to the issue

B.  

Validate the reason and add it as an issue in the issue log

C.  

Direct the sales team to speak with accounting to resolve the issue

D.  

Escalate the issue to the functional manager

Discussion 0
Questions 81

A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new

Hems

Match the risks on the left lo the correct category on the right.

Options:

Discussion 0
Questions 82

A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,

What should the project manager do?

Options:

A.  

Descope low-priority features that were not explicitly requested and add this feature as a high priority.

B.  

Inform the senior manager that they will need a new project management plan for this feature,

C.  

Complete the most current feature and release the resources for the new feature.

D.  

Analyze the impact of this change and present the options to the senior manager.

Discussion 0
Questions 83

A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.

What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?

Options:

A.  

Schedule a training course for the new team member to fill in their gaps in experience.

B.  

Log this as an issue in the project issue log and speak with the resource manager.

C.  

Provide weekly feedback to all project team members, including the new member.

D.  

Ensure that coaching meetings are in place for this team member within the project timeline.

Discussion 0
Questions 84

It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.

What should the project manager do?

Options:

A.  

Ask the team member to send their concerns in writing.

B.  

Empathize with the team member and discuss next steps.

C.  

Review the organization's human resources (HR) policy.

D.  

Schedule a meeting with the team member for the next work day.

Discussion 0
Questions 85

A project is almost completed, and both the sponsor and the project management office (PMO) are happy with the project manager's performance reviews. The project manager is under budget and ahead of schedule. However, a team member asks to add a feature to the product that will make the product more impressive and acceptable to the end users.

What should the project manager do first?

Options:

A.  

Accept the feature.

B.  

Determine if the feature is within the scope.

C.  

Submit a change request! for the feature.

D.  

Reject the feature.

Discussion 0
Questions 86

A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?

Options:

A.  

Revise the project schedule and inform the stakeholders regarding any delays

B.  

Revise the project estimates and meet with the project team to discuss delays

C.  

Review the management reserve to identify any costs associated with the delays

D.  

Review the contingency reserve to identify any delays to the project

Discussion 0
Questions 87

A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards

in order to ensure this, what should the project manager define and document?

Options:

A.  

Quality

B.  

Estimates

C.  

Objectives

D.  

Requirements

Discussion 0
Questions 88

A self-organizing team brings an internal problem to the project manager. What should the project manager do as a servant leader?

Options:

A.  

Provide the team with a solution that solves the problem.

B.  

Coach the team to solve the problem independently,

C.  

Discuss the issue with the management team and provide a solution,

D.  

Speak with the team lead about the issue and provide a solution,

Discussion 0
Questions 89

A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.

What should the project manager do next?

Options:

A.  

Explore the minimum requirements of the product and their feasibility.

B.  

Explain the resource constraints of the project to management.

C.  

Outsource the management of the product to an external team.

D.  

Conduct a detailed risk analysis to highlight the risks in the project.

Discussion 0
Questions 90

During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining

What should the project manager do?

Options:

A.  

Work with the team to understand and solve the issues

B.  

Provide testing training to all the project team members

C.  

Increase the sprint duration so the testing can be completed

D.  

Add a new resource with testing skills to the team

Discussion 0
Questions 91

project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?

Options:

A.  

Coercion

B.  

Conflict resolution

C.  

Emotional intelligence

D.  

Negotiating

Discussion 0
Questions 92

A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.

How should the project manager resolve this conflict?

Options:

A.  

Meet with all project stakeholders to identify how to implement the technology.

B.  

Identify the disagreement in the risk register and develop a contingency plan.

C.  

Update the project charter to align with the desires of the project sponsor.

D.  

Negotiate with the project sponsor to develop a mutually beneficial solution.

Discussion 0
Questions 93

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

Options:

A.  

Developing new product lines

B.  

Complying with new regulations

C.  

Establishing company processes

D.  

Certifying sustainable products

Discussion 0
Questions 94

A project manager became aware of misunderstandings between a key stakeholder

and a team member with regard to some of the features defined in the project scope. What

should the project manager do?

Options:

A.  

Reconcile the key stakeholder to the team member's recommendation.

B.  

Reconcile the team member to the key stakeholder's recommendation.

C.  

Escalate the communication concerns to the project management office (PMO) andrequest that they take action

D.  

Work with both the team member and the key stakeholder to reach a consensus.

Discussion 0
Questions 95

What should an agile lead do lo ensure their team is set up for success?

Options:

A.  

Pay attention to team dynamics and understand that coaching is done simultaneously at an individual and whole-team level

B.  

Schedule sprint meetings and coaching sessions to discuss project-related information

C.  

Plan quarterly informal meetings or team bonding sessions to encourage the team to work together

D.  

Document team tasks and challenges in order to understand when to step in and help a member of the team

Discussion 0
Questions 96

The sponsor approaches the project manager with new features they want added to

the project. The project is 95% complete, but the sponsor insists that continued support for the

project relies on the addition of the new features.

What should the project manager do?

Options:

A.  

Assess the impact of the features and refer it to the change control board (CCB).

B.  

Implement the new features after assessing the impact.

C.  

Reject the new features since it amounts to gold plating.

D.  

Add the new features to avoid losing the sponsor's support for the project.

Discussion 0
Questions 97

During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope What should the project manager do to improve the stakeholder's engagement?

Options:

A.  

Discuss the work breakdown structure (WBS) with the key stakeholder and refine the requirements

B.  

Update the project backlog and discuss it with the key stakeholder

C.  

Update the project charter and discuss it with the key stakeholder.

D.  

Discuss the project scope statement with the key stakeholder and build prototypes

Discussion 0
Questions 98

A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.

What strategy should the project manager implement to deal with this situation?

Options:

A.  

Ask the team.to accelerate the iterations and avoid interruptions.

B.  

Discuss the problem with the team and decide how to do the work together.

C.  

Verify team performance and ask for improvement during daily standup meetings.

D.  

Recommend that the project sponsor increases the budget to bring new resources.

Discussion 0
Questions 99

In a geographically distributed team, a developer continues to delay a coding activity. This activity is on the critical path. The project manager

found out that the delay is due to the developer's lack of understanding of the customer requirements shared by the off-site team.

What should the project manager do?

Options:

A.  

Replace the developer with a skilled resource.

B.  

Perform a root cause analysis (RCA) with the team members.

C.  

Facilitate communication to ensure clarification of the requirements.

D.  

Conduct frequent performance reviews.

Discussion 0
Questions 100

A project manager for an agile project wants to have a highly engaged team. How should the project manager achieve this objective?

Options:

A.  

Be clear with directions and assignments so people stay focused and engaged with their work.

B.  

Promote an environment where everybody knows what their contribution means to the project as a whole.

C.  

Design a reward system to get people motivated by recognizing significant individual contributions from the last sprint

D.  

Encourage continuous rotation of roles among team members to keep people motivated throughout project delivery.

Discussion 0
Questions 101

During the initiation stage of a multimedia exhibition-design project the project manager is developing the project management plan What should the project manager do to complete this task?

Options:

A.  

Benchmark other similar exhibitions' deliverable lists and final outcomes

B.  

Initiate a survey to solicit end-customer opinions and prioritize exhibition contents

C.  

Clarify the high-level business requirements with the event organizer as a basis for forming the deliverables list.

D.  

Initiate an additional services agreement in case the key deliverables list was not clearly stated in the contract

Discussion 0
Questions 102

After a performance review, a team member approaches the project manager and asks for feedback. The project manager mentions anecdotal information about this team member being a positive team player and generally getting their work done on time, even though they have been late with work once or twice. The team member expresses frustration at not having better information included in the annual performance review.

What should the project manager do to prevent this frustration going forward?

Options:

A.  

Request the human resource (HR) department to provide the key performance indicators (KPls) that were defined for this project.

B.  

Set team performance goals and explain how the team receives the same performance scores.

C.  

Review the key performance indicators (KPIs) for this team member and remind the team member how they are determined.

D.  

Provide the team member with velocity tracking tools and explain how the team member can see and track performance.

Discussion 0
Questions 103

A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.

What should the project manager do given the urgency?

Options:

A.  

Consult preferred vendors from the company.

B.  

Perform research on experienced vendors in the market.

C.  

Source vendors with extensive experience.

D.  

Follow the company's standard vendor selection criteria process,

Discussion 0
Questions 104

A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.

What should the project manager do first?

Options:

A.  

Send an email to the client team member explaining that they have the information already.

B.  

Review the stakeholder register to gain insight into the expectations of that team member.

C.  

Inform the client project manager that they are sending too many trivial requests.

D.  

Update the project risk register to include potential delays in answering these requests.

Discussion 0
Questions 105

A new project manager has been assigned to a project that is in danger of failing The stakeholders do not know the project status nor do they know what benefits will be delivered by the project.

How can the project manager convey these benefits to the stakeholders?

Options:

A.  

Rebaseline the project schedule to show the current status of the project.

B.  

Create a benefits management plan mapped to the organization's strategic objectives

C.  

Perform a project cost-benefit analysis for the stakeholders

D.  

Update the deliverables map against the agreed-upon project requirements

Discussion 0
Questions 106

During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.

What should the project manager do?

Options:

A.  

Schedule a meeting with the new sponsor in order to explain the agile approach and how teams are supposed to be self-organized.

B.  

Schedule an emergency meeting with the project team so they fulfill every request that comes from the sponsor.

C.  

Review the sponsor's request with the project team during the next daily review meeting in order to provide the requested control.

D.  

Review the sponsor's request with the project team during the next iteration review meeting in order to obtain a team decision.

Discussion 0
Questions 107

A project team was established for a community impacted by oil and gas exploration activities. The team is required to interact with several external stakeholders. The local council authority has requested a meeting with the project team to discuss the impact of the project on the community. The project manager was not available at the time of the meeting, and the team was in disagreement regarding who should attend the meeting.

What should the project manager have done to prevent this conflict?

Options:

A.  

Provided copies of the stakeholder engagement plan to all team members.

B.  

Defined the roles and responsibilities of the team members.

C.  

Updated the communications management plan.

D.  

Established ground rules for the team

Discussion 0
Questions 108

A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?

Options:

A.  

Escalate the issue to the team's manager.

B.  

Remove some of the team members.

C.  

Review the roles and responsibilities document.

D.  

Develop working agreements with the team.

Discussion 0
Questions 109

A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?

Options:

A.  

Determine a leadership style that is suitable for that location.

B.  

Check if resources from headquarters can also be assigned to the project.

C.  

Mentor the team members to perform project management.

D.  

Assign a local resource to manage communication with the team.

Discussion 0
Questions 110

In an agile product development environment, work is distributed to Cities A, B, and

C, which are geographically dispersed. The small teams work and collaborate to deliver the

sprints.

• City A's team focuses on the features of data capture.

• City B's team focuses on the user experience and development pieces.

• City C's team coordinates testing.

What should the project manager do to ensure a successful rollout of sprints?

Options:

A.  

Ensure all three teams deliver independently without interactions so that they remainfocused and meet customer requirements.

B.  

Implement communication techniques and ensure the teams follow a relay pattern ofhanding off work from one team to the other.

C.  

Use a fishbone analysis to resolve problems and iron out communication issuesbetween the teams.

D.  

Maintain localized teams to circumvent the challenges of delay or any otherunforeseen risks that might prevent progress.

Discussion 0
Questions 111

A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs

How should the project manager ensure the work continues smoothly?

Options:

A.  

Postpone the required work on the project until school holidays begin

B.  

Advise the school to close (or the duration of the project work

C.  

Continue the work as planned and inform the school when the project team arrives on-site

D.  

Liaise with the school to include nonworking project hours during school start and finish times

Discussion 0
Questions 112

A project manager decided to incorporate the latest technological advancement with the client's devices at no additional cost to the project.

Upon completion and submission of the project deliverables, the client rejected the devices, despite having the latest features.

What should the project manager have done?

Options:

A.  

Incorporated the change within the scope of the project

B.  

Reviewed the quality inspections

C.  

Complied with the customer specifications

D.  

Documented the technical reviews with the new change

Discussion 0
Questions 113

An events company is planning their annual event for a retirement fund. The organization has run the event planning using agile approaches for the last 3 years. During the initiation phase, while assessing possible risks and improvements for the event, the project manager uses previous event feedback to assist in developing the risk register.

Which ceremony should be used in developing this register?

Options:

A.  

Sprint plans

B.  

Retrospective results

C.  

Sprint report

D.  

Project status report

Discussion 0
Questions 114

A project manager is working on a large project with a very difficult client. During

the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.

How should the project manager approach this?

Options:

A.  

Concentrate on the current project milestones.

B.  

Update the project management plan for this new work.

C.  

Develop a business case and submit it to the client.

D.  

Make all the changes and then show the client the results.

Discussion 0
Questions 115

A large company has agreed on a business case for an environmental project. The

project will cause some major changes in their operations, such as reduction in paper use,

which will obviously affect all of the users.

What is the first thing the appointed project manager should do?

Options:

A.  

Evaluate the impact to the users and create a plan to address it.

B.  

Inform users about the new changes and ask for their collaboration.

C.  

Ask all managers to collaborate implementing this change to users.

D.  

Start implementing the change so that users will eventually get used to it.

Discussion 0
Questions 116

The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.

What should the project manager do to resolve and prevent additional arguments?

Options:

A.  

Monitor the interactions between the vendor and infrastructure manager going forward.

B.  

Host a meeting with the vendor and infrastructure manager to help resolve their disagreement.

C.  

Escalate the issue to the sponsor so appropriate action can be taken.

D.  

Instruct the vendor to correct the problem without additional arguments.

Discussion 0
Questions 117

A project manager is new to hybrid project management and is worried about the project because it has a high level of requirements uncertainty. The team has experience with hybrid projects, performs daily standups, and is committed to the project. The project manager is concerned about losing control of the project and would like to have a more central role.

How should the project manager address this issue?

Options:

A.  

Modify the daily standup meetings to include project status reporting.

B.  

Escalate the issue to the change control board (CCB) and ask for advice.

C.  

Adopt the role of supporting and empowering the project team to do the work.

D.  

Change the approach for the project to a predictive approach.

Discussion 0
Questions 118

At the end of the last iteration, the customer rejects the deliverables since they did

not meet the customer's expectations. What should the project manager have been done

to prevent this situation?

Options:

A.  

Involved the customer more in the planning process for the project, and ensuredagreement on the proceedings.

B.  

Included all relevant criteria in the agreed upon definition of done (DoD), and crafted a shared product vision.

C.  

Provided the customer with the backlog and the specified user stories at the beginning of the iteration.

D.  

Developed the DoD in close cooperation with all stakeholders to ensure their expectations were included.

Discussion 0
Questions 119

A team has been working together for several months and has successfully

delivered work. A new team member has joined the team but is having difficulty

contributing.

What should the project manager do to help the new team member integrate effectively?

Options:

A.  

Give the new team member time to contribute until they ask for help and support.

B.  

Assign the new team member tasks so that the team member knows on what to focus.

C.  

Approach the team member to identify any issues and then plan a resolution accordingly.

D.  

Review the project with the team member to ensure the project scope is understood

Discussion 0
Questions 120

An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.

What should the project manager do?

Options:

A.  

Provide feedback to the team and conduct a meeting to review the team rules.

B.  

Provide feedback to the team and conduct a retrospective meeting to find a root cause.

C.  

Provide feedback to the team and request agile training for the new member.

D.  

Provide feedback to the team and coach the new team member in agile methodology.

Discussion 0
Questions 121

During a sprint planning meeting, a stakeholder is told that their requirement is in progress and on track for the final product to be ready in the next two sprints. The stakeholder is very satisfied with the timeline and gives their full support to the agile team. After the meeting, the project sponsor calls the project manager about a large requirement they want the team to work on right away as it has significant

business value. What should the project manager do?

Options:

A.  

Call the stakeholder to tell them that the final product schedule must be extended due to this last minute, urgent request.

B.  

Perform an impact analysis and share the overall schedule impact before deciding on a new priority.

C.  

Reject the new requirement from the sponsor as this is going to impact the delivery of the stakeholder's final product.

D.  

Ask the product owner to prioritize the new request from the sponsor and ask the team to work on it immediately.

Discussion 0
Questions 122

A project manager is hired by a global company. The project manager is an agile specialist and is tasked with supporting the project team to reduce rework and dissatisfaction.

How should the project manager address these objectives?

Options:

A.  

Decrease the scope of the portfolio and send new solutions to the customer.

B.  

Deliver a schedule with the portfolio timeline and delivery to the customer.

C.  

Adopt an incremental cycle of delivering value to the customer.

D.  

Prepare deliveries with more details to satisfy the customer.

Discussion 0
Questions 123

A senior management team member contacts an agile project lead and mentions

that certain features the senior manager thought would be in the current release were not

included. What should the agile project lead do?

Options:

A.  

Assure the senior manager that these features will be queued up in the next sprint.

B.  

Meet with the team to understand why the senior manager’s features were not included.

C.  

Invite the senior manager to the next planning meeting.

D.  

Send the product roadmap to the senior manager.

Discussion 0
Questions 124

During the execution phase, the project manager discovered that the deliverables

are not meeting the quality specifications requested by the main stakeholder. This has

caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost

performance index (CPI) from 1.5 to 1.1.

What action should the project manager take to mitigate the issue of the deliverables being

rejected during the next iteration?

Options:

A.  

Submit a change request to prioritize resolutions for the quality issue to minimize the impact on the rest of the deliverables.

B.  

Reinforce the definition of done (DoD) during sprint planning so that the team has a common understanding of expectations.

C.  

Assure that the product backlog is properly prioritized to avoid dependencies that cause rejection.

D.  

Create a dedicated sprint to complete all of the pending specifications from previous sprints.

Discussion 0
Questions 125

During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past

What should the project manager do next to improve this situation?

Options:

A.  

Call for a team meeting to identify the root cause for the declining performance

B.  

Estimate the baseline impacts and submit a change request.

C.  

Implement compression techniques to bring the project back on track.

D.  

Review the resource management plan and organizational assets

Discussion 0
Questions 126

When reviewing the project team's performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?

Options:

A.  

Increase the sprint duration to allow the team more time

B.  

Prioritize the contents of the backlog and remove some stories

C.  

Create a change request to modify the gate review goals

D.  

Use the standup meeting to assess impediments and problems

Discussion 0
Questions 127

The project sponsor requested technical specifications for a project-related component. The project sponsor does not have the authorization to see the specifications, but insists on seeing them.

What should the project manager do first in this situation?

Options:

A.  

Meet with the project sponsor as soon as possible to discuss the matter further

B.  

Update the issue log to make the project team aware and to develop a strategy

C.  

Create a stakeholder engagement plan to help the team formulate a response

D.  

Provide the specifications to the project sponsor with some information removed

Discussion 0
Questions 128

A company is leading a project to develop a new product using an agile approach. A supplier was contracted to provide a solution for one of the product features based on mandatory scope, stable requirements, and fixed-price contract. During a meeting with the supplier, the project manager was informed that the company's business analyst also asked the supplier to add a solution for another feature as part of their deliverable.

What should the project manager do?

Options:

A.  

Add the feature to the supplier's requirement list so they can deliver it.

B.  

Ask the supplier to accommodate the additional scope under the current agreement.

C.  

Ensure the project team understands the agreement and contract in place with the supplier.

D.  

Monitor the work the business analyst is performing to avoid scope creep.

Discussion 0
Questions 129

A company is initiating a project to decommission inefficient sales channels. Several stakeholders argue that one channel that indicates a downturn in generating value is still more efficient than some of the channels that are planned to remain.

What should the project manager do?

Options:

A.  

Plan for incremental and iterative delivery based on feedback from the marketing and sales team.

B.  

Review and update the success criteria to ensure that the channel is not decommissioned.

C.  

Inform the stakeholders that the list of channels to be decommissioned was approved by the CEO.

D.  

Escalate the objection to the steering committee and human resources (HR) as a personal intimidation incident.

Discussion 0
Questions 130

A project manager has been asked to participate in the procurement process for a

software application that allows customers to buy online e-learning courses. The project

manager will take over the project once the supplier has been sourced.

What should the project manager do before the project starts?

Options:

A.  

Ensure that the requirements for the project are understood and that the objectivesare verified before approval of an agreement.

B.  

Inform the project sponsor that once the agreement has been signed, there cannotbe any changes to the scope of the project.

C.  

Notify the project sponsor that the project manager cannot be involved in theagreement negotiation process.

D.  

Ask the project sponsor to involve the legal department in the negotiation for the project agreement.

Discussion 0
Questions 131

On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?

Options:

A.  

Escalate the issue to the project sponsor.

B.  

Review the stakeholder engagement plan.

C.  

Update the issue log.

D.  

Neutralize the negative stakeholders.

Discussion 0
Questions 132

A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.

What should the project manager use to document the project deliverables?

Options:

A.  

Service level agreement (SLA)

B.  

Statement of work (SOW)

C.  

Scope management plan

D.  

Memorandum of understanding (MOU)

Discussion 0
Questions 133

A project manager identifies an issue between two team members that is affecting the development of one of the deliverables during the second iteration of a project. How should the project manager address this issue to avoid any impact to the project?

Options:

A.  

Contact the functional managers to request substitutes for the conflicting team members.

B.  

Send a warning to both team members indicating that if the issue continues, both will be removed from the project.

C.  

Schedule a meeting with both team members to understand the issue and facilitate a solution that satisfies both parties.

D.  

Escalate both team members to their respective functional managers and let them take the appropriate actions

Discussion 0
Questions 134

A company is transitioning from a predictive to agile delivery of projects. Based on

the requirements, the project team estimates the budget and decides to use a fixed-price

contract with its vendor. However, during the execution of the project, the requirements

evolve and priorities start to change constantly, which puts the project and the estimate at completion (EAC) off by 40%.

What should the project manager do next?

Options:

A.  

Send a detailed status report highlighting the issue with funding to all of the stakeholders.

B.  

Submit a change request to the financial manager to increase the funding and continue as is.

C.  

Meet with the stakeholders to recommend the use of a time and materials (T&M) contract to address the problem.

D.  

Wait until the next gate review meeting to highlight the risk of low funds to the stakeholders.

Discussion 0
Questions 135

A major project is unable to access the US$12 million funding allocated for the project. This prevents the start of the procurement process and is already leading to costly delays.

What should the project manager do?

Options:

A.  

Escalate to the project steering committee.

B.  

Invite the finance department to the next project demo.

C.  

Review the project requirements.

D.  

Use the currently available resources.

Discussion 0
Questions 136

A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?

Options:

A.  

Accommodate the change request to serve the client's needs

B.  

Consult with team members and allow them to make a decision

C.  

Convince the client not to make changes to the project

D.  

Make transactional decisions focusing on the project goals

Discussion 0
Questions 137

Since the beginning of a project, the product owner keeps asking during ceremonies about the budget spent for each product iteration The product owner seems much more interested in the cost rather than the product itself.

What should the project manager have done earlier to change the product owner's behavior''

Options:

A.  

Worked on a fixed-price contract to switch the product owner's attention to value instead of money

B.  

Worked on a communications management plan with reports of budget spent in each iteration versus planned to avoid these discussions during ceremonies

C.  

Worked on different approaches of estimating to give confidence of the cost spent in each product increment.

D.  

Worked with the product owner to clarify their role in an agile project and the scope of the agile ceremonies

Discussion 0
Questions 138

Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.

How should the agile project leader resolve this situation?

Options:

A.  

Update the restriction log with the new team capacity.

B.  

Explain the new project requirements to the team.

C.  

Update the project budget with the released team members.

D.  

Explain the new team velocity to the customer.

Discussion 0
Questions 139

A project manager receives a request for proposal (RFP) from a client. The client

is very clear about the requirements. A requirements analysis must be done in the first

month of the project, and the client wants to see a demo of the work completed every two

weeks.

What project approach should the project manager use?

Options:

A.  

Iterative for the requirements analysis and delivery phases of the project

B.  

Agile for all of the phases of the project, including the requirements analysis and delivery

C.  

Predictive for the requirements analysis and agile for delivery of the project

D.  

Predictive for the requirements analysis and delivery phases of the project

Discussion 0
Questions 140

A large organization decided to adopt an agile methodology based on the trends

seen in the industry. The organization invested a large amount of money in adopting it, but

after a few months, the implementation failed.

What should the project manager have done differently to avoid the implementation failure?

Options:

A.  

Conducted agile training for all employees ranging from the project teams throughmid-level to upper-level management.

B.  

Conducted a postmortem and captured the learning in organizational process assets(OPAs) for future use.

C.  

Assessed the organization's culture, performed a suitability analysis, and determinedthe future state.

D.  

Hired a third-party agile delivery team to do the implementation.

Discussion 0
Questions 141

A team has been consistently delivering outcomes. However, based on their current performance, it was discovered that their velocity has decreased by 30%.

What should the project manager do to ensure the velocity is under control?

Options:

A.  

Ask the product owner to look at a minimum of four to eight iterations and replan the velocity for the next iteration based on the team's current performance.

B.  

Ask the scrum master to plug gaps in the team's performance by adding a team member to compensate for the velocity decrease.

C.  

Request that the team improve their cycle time to compensate for the velocity decrease.

D.  

Request the team to improve the lead time, cycle time, and response time individually and track closure.

Discussion 0
Questions 142

A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?

Options:

A.  

Assign the feature to another team member, and have them try to complete the feature by the end of this iteration

B.  

Review team capacity and reassign the functionality to additional iterations as required

C.  

Determine if the team member can work from home to complete the functionality.

D.  

Review the work in progress with the product owner to determine the next step

Discussion 0
Questions 143

An agile project team is building a new product. The stakeholders require ongoing

illustration of project business value.

How should the project manager proceed?

Options:

A.  

Prepare performance value reports for the business on an ongoing basis.

B.  

Include demonstrations of the built portion of the product at the end of every sprint.

C.  

Prepare a project report for the stakeholders and distribute it weekly.

D.  

Confirm the minimum viable product (MVP) and demonstrate it to the business when it is ready.

Discussion 0
Questions 144

Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not

delivered, the company could receive a fine from the government. What should the project manager do?

Options:

A.  

Discuss the issue with the project sponsor.

B.  

Review the resources required for the tasks on the critical path.

C.  

Review and update the risk management plan.

D.  

Allocate resources to develop the competencies of the other team members

Discussion 0
Questions 145

An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.

What should the project manager do to avoid this situation in the future?

Options:

A.  

Ensure that customer requirements do not change from the start of the project.

B.  

Ensure that the definition of done (DoD) is well defined and complete for future iterations.

C.  

Ensure that the development and quality assurance team members implement the feature correctly.

D.  

Ensure that the team facilitator allocates tasks correctly to team members.

Discussion 0
Questions 146

A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.

What should the project manager do?

Options:

A.  

Apply fast-tracking techniques to compress the schedule of the critical project

B.  

Analyze both projects to determine the most effective use of common resources

C.  

Use resource optimization to justify requesting more resources for the critical project.

D.  

Provide schedule optimization training to the project teams to improve their skills.

Discussion 0
Questions 147

In a project management team meeting, one of the team members always argues with the project manager about the objective, timeline, and deliverable of any assigned task.

What should the project manager do to manage this conflict?

Options:

A.  

Schedule a meeting with the team member and their manager to discuss the issue.

B.  

Talk to the project sponsor about the team member's attitude.

C.  

Schedule a one-on-one meeting with the team member to talk about it and get theircooperation.

D.  

Find another person to replace this team member.

Discussion 0
Questions 148

In a fixed time and budget project the customer wants the development of a core component to be based on agile practices, as the final scope of (he requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project.

Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose two)

Options:

A.  

Limit the number of iterations for development in the contract.

B.  

Establish a governance committee to review the contract delivery

C.  

Tier the contract for fixed and agile components

D.  

Provide alternatives to scope change at specific project phases within the contract.

E.  

Require that only internal resources be utilized for this project

Discussion 0
Questions 149

A company's leadership team has decided to invest in a new product using an agile approach The commercial and product teams have started the planning activity for this new venture Which three key factors does the project manager need in order to deliver this product? (Choose 3)

Options:

A.  

High-level product backlog

B.  

Key performance indicators (KPls)

C.  

Product vision

D.  

Schedule performance indexes (SPIs)

E.  

Product roadmap

Discussion 0
Questions 150

A team member has indicated their user story will not be finished until the end of the iteration as their functional manager has requested they assist in resolving a high-priority production issue. What should the project manager do?

Options:

A.  

Discuss with the product owner that the user story will not be completed this iteration.

B.  

Meet with the team member's functional manager to try to remove the impediment.

C.  

Tell the project team member not to work on the production issue and to inform their manager.

D.  

Escalate the issue to the project sponsor to resolve and adjust the project burndown chart.

Discussion 0
Questions 151

An agile project is starting its seventh out of eight iterations In a planning meeting, the team realizes that an unidentified risk became an issue and the contingency reserve has to be used.

What should the project manager do?

Options:

A.  

Ask the sponsor to approve inclusion of an additional iteration to the project

B.  

Ask the team to include the contingency plan in the iteration backlog

C.  

Help the team review the project approach to initiate the corrective actions

D.  

Ask the sponsor for money to implement the contingency plan.

Discussion 0
Questions 152

A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets with the stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive.

What should the project manager have done to avoid this situation?

Options:

A.  

Initiated requirements planning to analyze, document, and manage requirements

B.  

Applied requirements elicitation to involve engaging stakeholders consistently in the requirements process

C.  

Implemented the change request process to harness change to the stakeholders’ advantage

D.  

Used progressive elaboration to enhance the scope management plan with additional details

Discussion 0
Questions 153

On a project to create the perfect paper airplane, the development of the airplane Is performed In iterations. The artwork to go on the wings and tail is done using a predictive approach. One of the stakeholders provides a requirement that conflicts with the product owner's requirements.

Who is responsible for analyzing the new requirement and making the final decision?

Options:

A.  

Project manager

B.  

Scrum master

C.  

Project sponsor

D.  

Product owner

Discussion 0
Questions 154

In a multinational project, stakeholders are in different time zones. The project

manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the

project sponsor that they know very little about the project.

What should the project manager do?

Options:

A.  

Discuss the issue with all stakeholders and work on a communications management plan to meet all stakeholder requirements.

B.  

Ensure that the stakeholders who are complaining are present for the next project update meetings.

C.  

Record the regular project update meeting and share it with all stakeholders after the meeting is completed.

D.  

Change the meeting time to the working time zones of the stakeholders who are complaining.

Discussion 0
Questions 155

For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product

After collecting the new requirements, what should the project manager do?

Options:

A.  

Assess the impact of the new requirements and initiate the change request process.

B.  

Work with the product manager and the rest of the team to update the project backlog.

C.  

Assess the impact and communicate the updated product roadmap to the stakeholders.

D.  

Follow the change management plan to update the risk register so It accounts for the added scope.

Discussion 0
Questions 156

A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area

What should the project manager do first?

Options:

A.  

Identify an alternative site.

B.  

Update the issue log

C.  

Issue a change request

D.  

Update the risk register.

Discussion 0
Questions 157

A new relevant project stakeholder suggested a change to some of the project parameters midway through execution What should the project manager do next?

Options:

A.  

Accept the change and use contingency funds to implement this change with minimal schedule impacts

B.  

Reject the change because it is contrary to what was agreed to during earlier phases of the project

C.  

Transfer the change to the steering committee for them to evaluate and decide the appropriate next steps

D.  

Evaluate the proposed change with integrated change controls and discuss the change with the project sponsor

Discussion 0
Questions 158

A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule

Which two actions should the project manager take to manage Impediments and improve the team's velocity? (Choose two)

Options:

A.  

Look for processes that cause bottlenecks and slow down the team's agility

B.  

Assign the items with high complexity lo senior developers

C.  

Empower the learn to make decisions to remove impediments

D.  

Work with the team to remove impediments as quickly as possible

E.  

Move the items with high complexity to the last iterations

Discussion 0
Questions 159

Close to the end of a project, a customer claims that some deliverables have not

been met and starts initiating change requests. What should the project manager do next?

Options:

A.  

Refer to the requirements traceability matrix.

B.  

Revise the project scope baseline.

C.  

Escalate the change request to the project sponsor.

D.  

Review the approved project charter.

Discussion 0
Questions 160

An agile team is working on a product deliverable in an organization that is transforming itself to quickly respond to change. The finance

team is requesting a project budget for the new product.

What should the team do to address this request?

Options:

A.  

Work with the finance team to transition to incremental budgeting.

B.  

Request the finance team to allocate a budget based on historical data.

C.  

Provide the budget to the finance team for only the planned increments.

D.  

Extrapolate the budget based on the current cost performance index (CPI).

Discussion 0
Questions 161

A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings

What should the project manager do?

Options:

A.  

Ask the individual who is hosting the event to use private communication methods.

B.  

Set up a meeting with the distracted team member to discuss any issues

C.  

Add a social events section to the charter to handle these situations

D.  

Ask the individual who is hosting the event to mark it as private

Discussion 0
Questions 162

During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?

Options:

A.  

Review the project scope statement

B.  

Confirm ownership for ongoing value realization

C.  

Escalate the issue to the project sponsor

D.  

Appraise the stakeholders of value gain progress

Discussion 0
Questions 163

Due to a recent budget reduction, two team members were released from an agile

team. The customer is still expecting early results for the project.

Which two actions should the project manager take to align customer expectations? (Choose

two)

Options:

A.  

Ask the agile team to review the updated sprint velocity with the customer.

B.  

Ask the product owner to review the prioritized backlog with the customer.

C.  

Ask the agile team to review and update the quality management plan with thecustomer.

D.  

Review the impediments log with the customer.

E.  

Send a detailed project management plan to the customer.

Discussion 0
Questions 164

After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.

How should the project manager handle this situation?

Options:

A.  

Comply with the project sponsor's request to not archive the project artifacts.

B.  

Document the project sponsor's instructions as the archived project artifacts.

C.  

Archive the project artifacts on the project manager's local computer for future reference

D.  

Consult with the project management office (PMO) for guidance on project artifacts.

Discussion 0
Questions 165

At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.

What should the project manager do next?

Options:

A.  

Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.

B.  

Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.

C.  

Address this concern with the functional managers to ensure there will be no further delays.

D.  

Schedule a meeting with all of the functional managers to resolve the resource conflicts.

Discussion 0
Questions 166

A project needs to purchase a specific piece of equipment, as stated in the

project documents and approved by the project sponsor. The procurement division is

questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.

What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?

Options:

A.  

Communicated the project charter to the procurement division

B.  

Included a procurement division member on the project team

C.  

Reminded the project sponsor about the procurement division's reputation

D.  

Communicated the project management plan to the procurement division

Discussion 0
Questions 167

For an ongoing project, match the key performance indicators (KPIs) on the left to the correct categories on the right.

Options:

Discussion 0
Questions 168

A project manager has noticed that the performance of a new team member has increased dramatically over the past few months The project manager has been measuring this team member's performance through the cost performance index (CPl) and schedule performance index (SPl) of work packages. The project manager has also assigned new. unrelated work packages to this team member The project manager wants to formally record the team member's success in the project documentation

What should the project manager do?

Options:

A.  

Attach a note to the project management plan about the team member

B.  

Hold a project team meeting about the team member's contribution and take minutes

C.  

Record the team member's contribution in the responsibility assignment matrix (RAM)

D.  

Send a communication to management recognizing the team member's contributions

Discussion 0
Questions 169

A project started 12 months ago and is currently on iteration 12 of 14. The team

has performed well and completed all deliverables on time. However, some team members

are starting to complain about the length of the project, creating a risk for lack of

performance at this critical stage.

What should the project manager do as a servant leader to mitigate this risk?

Options:

A.  

Meet with the team to reinforce their responsibilities and the consequences if theproject deliverables are not completed on time.

B.  

Apply additional controls to the project deliverables to ensure that all milestonesare achieved on time.

C.  

Contact the functional manager to ensure that team motivation remains high untilthe end of the project.

D.  

Schedule a team event with the project sponsor to highlight the importance of theproject and recognize the work of the team.

Discussion 0
Questions 170

As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.

What should the project manager do?

Options:

A.  

Create an entry in the impediment board and assign it.

B.  

Invite the project team to a swarming session to define a solution

C.  

Leverage the network of the former department and ask for help

D.  

Escalate the issue to the product owner to define the next steps

Discussion 0
Questions 171

A project team's performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?

Options:

A.  

Focus on remediation not merely on correcting symptoms

B.  

Compare the team's performance against other project teams

C.  

Identify potential failure points based on the iteration workload

D.  

Motivate the team to perform better

Discussion 0
Questions 172

A project manager was recently appointed to an agile project. The project will have a lot of visibility and impact for the company, so the project management office (PMO) manager wants to ensure that the project manager manages the risks correctly.

What should the project manager do?

Options:

A.  

Implement the agile risk manifesto to ensure the proper tracking, analysis, and remediation of the project risks.

B.  

Ask the product owner to act as a risk manager to assist with the remediation of risks.

C.  

Implement the role of an agile risk manager to take care of the risk management process.

D.  

Follow the risk management process while ensuring that risks are identified, analyzed, and managed during each iteration.

Discussion 0
Questions 173

A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.

What should the project manager do?

Options:

A.  

Ensure that relevant stakeholders and expectations are identified and assess the component delay.

B.  

Perform a detailed analysis of the release content for each component of the solution.

C.  

Propose a new design of the solution to replace the external component with an internal one.

D.  

Ask for expedited delivery of the component to mitigate the risk of schedule delays.

Discussion 0
Questions 174

A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.

What is the next step for the project manager?

Options:

A.  

Document the lessons learned and implement improvements in the next sprint

B.  

Facilitate a daily standup with the team to track the implementation of changes

C.  

Organize a demonstration of the changes in the enterprise system

D.  

Request that all team members think of ideas to improve processes.

Discussion 0
Questions 175

In a functional organization, a product analyst is assigned to a short-duration application development effort The analyst expresses concerns about the task and asks the project manager to provide the support of a peer with expertise in this domain

What should the project manager do?

Options:

A.  

Make sure the analyst has regular pairing meetings with the other team member throughout task execution

B.  

Ask the analyst to use skills to develop the tool, then move development to another team member

C.  

Enroll the analyst in a capacity-building program and keep this analyst assigned to the task

D.  

Recognize the analyst's concerns and reassign the task to another team member

Discussion 0
Questions 176

A project manager is leading a virtual team that is geographically dispersed. What

should the project manager do to avoid uncertainty in the project due to different cultures?

Options:

A.  

Start the project and add any uncertainty that arises to the risk register.

B.  

Dissolve the virtual team and build a colocated team.

C.  

Gather relevant cultural data and engage members in discussions covering their work ethics.

D.  

Build a culturally neutral team that will not be affected by cultural differences.

Discussion 0
Questions 177

A project manager has received feedback from stakeholders regarding poor communication about project progress. Weekly status reports were provided to the project management office (PMO), and the standard communications management plan was followed.

What should the project manager do?

Options:

A.  

Perform a root cause analysis (RCA) of the existing communication approach.

B.  

Ensure that all of the complaining stakeholders are on the distribution list.

C.  

Create a change request for implementing an online collaboration tool.

D.  

Distribute hard copies of status reports and confirm that messages were read.

Discussion 0
Questions 178

A project manager at a large corporation has been assigned to oversee a customer experience project. Within the project, customer satisfaction is

a big issue and there are many unresolved customer queries on a daily basis. The project manager has been informed that the customer service

team is overwhelmed with these unresolved queries.

Which two actions should the project manager take to correct this problem? (Choose two)

Options:

A.  

Contact the customers in batches and inform them that the issues are being worked on currently.

B.  

Confirm the issues truly exist by conducting a survey and other analyses that may detect the real issue.

C.  

Deploy solutions that will track, prioritize, and resolve queries as soon as possible.

D.  

Ask senior management to replace the customer service manager with a more qualified one.

E.  

Request that the customer service team prioritizes work on queries that are received this week.

Discussion 0
Questions 179

A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers

arranged time off to allow time for installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for 2 days.

What does the project manager need to do now?

Options:

A.  

Inform the relevant stakeholders.

B.  

Inform the project team only.

C.  

Inform the product owner.

D.  

Inform the project sponsor.

Discussion 0
Questions 180

A company faces challenges and decides to cut a few product features from the main project due to market conditions. During a status meeting, a new stakeholder expresses concern about the discrepancies between the current deliverables and the deliverables agreed upon in the project charter.

What should the project manager do first?

Options:

A.  

Ask the project team to increase the number of updates provided to the stakeholder.

B.  

Determine the root cause of the discrepancy with the project team and agree on the project scope.

C.  

Ask the new stakeholder to submit a change request to the change control board (CCB).

D.  

Review the project objectives for alignment with the intended corresponding business value.

Discussion 0
Questions 181

During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not convinced that the return on investment (ROI) can be achieved.

How should the project manager address this issue?

Options:

A.  

Re-visit the project charter and seek other alternatives.

B.  

Proceed and issue the purchase order as this project is important.

C.  

Speak with the CEO and ask for their support to approve the offer.

D.  

Analyze the bounds of negotiations for project agreements.

Discussion 0
Questions 182

A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a timely manner.

In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?

Options:

A.  

Delegate most authorities and control the authority by withholding important information.

B.  

Delegate certain authorities and control the authority by withholding important information.

C.  

Delegate certain authorities and share information to allow fair decision-making.

D.  

Delegate most authorities and share information to allow fair decision-making.

Discussion 0
Questions 183

A project team is implementing an enterprise notification tool with a vendor. The project manager noticed that this vendor's developer has been reporting the same status for

several weeks in a row. A few days later, the vendor communicates that the deliverable will not be completed on time due to resource constraints within their company.

What should the project manager do next?

Options:

A.  

Update the risk register to reflect the delay, communicate the impact to the schedule, and escalate to management for assistance.

B.  

Conduct a project review with the project sponsor to explain the delay and add a developer to work with the vendor.

C.  

Review the contract with the vendor to go over the financial penalty that is applicable to this situation.

D.  

Add the delay to the issue log and work with the vendor for a resolution that will bring the schedule back on track.

Discussion 0
Questions 184

A company just started managing a project using an agile approach. Due to this change, the general manager is worried about the scope definition process for upcoming projects.

What should the project manager do to ensure the project scope is completely defined?

Options:

A.  

Ask the general manager to review every requirement to ensure all projects will deliver the requested products

B.  

Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements

C.  

Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations

D.  

Meet with the general manager and convince them to return to using predictive approaches to avoid any risk

Discussion 0
Questions 185

Companies A and B are codeveloping a cutting-edge technology product. Based on customer feedback, the marketing department urgently requests a new feature in 2 weeks. Company A's front end is ready, but company B requires 4 weeks to deliver the complete back end and is busy with the current release.

What should the project manager do to obtain agreement from both companies and acceptance from marketing?

Options:

A.  

Create a special release 4 weeks after the current release to deliver the new feature in its entirety.

B.  

Stop the current release work for 4 weeks in order to work and deliver the new feature completely.

C.  

Plan the delivery of a minimum viable feature in 2 weeks to enable early showcasing of business value.

D.  

Add the new feature to the list for the next release and continue working on the current release.

Discussion 0
Questions 186

A large matrix organization is adopting a new communications approach. This is necessary because their projects often require the resourcing of expert knowledge in the form of specialists from various departments and divisions.

What should the project manager do to set up effective communications?

Options:

A.  

Plan on transmitting the information in an easily understandable manner.

B.  

Focus on the recipients’ needs and not the information itself.

C.  

Use the highest possible technical language and avoid using metaphors.

D.  

Ensure that messages sent to the recipients are delivered.

Discussion 0
Questions 187

An agile team is geographically separated across multiple continents, and the project manager is in the process of identifying the tools to manage the communication among the virtual teams. Drag the appropriate tool on the left to each project task on the right.

Options:

Discussion 0
Questions 188

A project manager has been given a critical, 5-day window and is allocated a maximum of US$100,000 as a contingency reserve. Subsequently, the project manager drafted

a course of action based upon the best available information. Overall, five actions were required to be completed at a cost of US$20,000 and a duration of 1 day each. After

3 days of work, the project manager completed two actions and spent US$80,000.

What should the project manager do next?

Options:

A.  

As the CPI and SPI are greater than 1.0, reevaluate and prioritize the remaining actions.

B.  

Stop the work and raise a project change request to the change control board (CCB) for additional funds and a project schedule extension.

C.  

As the cost performance index (CPI) and schedule performance index (SPI) are less than 1.0, reevaluate and prioritize the remaining actions.

D.  

Complete all actions and then inform the client of the additional cost and schedule overrun needed to complete the project.

Discussion 0
Questions 189

A project manager is assigned to a new project that will launch the digital version of a current product. Even though the product is well known, the vision for its digital version

is not clear to the stakeholders.

What should the project manager do to increase value delivery?

Options:

A.  

Use spikes to dig deeper into the technical challenges of the new product, thus reducing the technical risk.

B.  

Create a visual task board with all of the relevant stakeholders to support backlog prioritization.

C.  

Work with the team on the definition of a minimum viable product (MVP) and present it to the stakeholders.

D.  

Gather the team to create a comprehensive product roadmap but only commit to requirements for the next quarter.

Discussion 0
Questions 190

A project team is working on the design of a solution for a complex project. Due to a lack of clarity of the customer's requirements, daily meetings

were agreed upon between the team and the customer. There are a few external contractors in the project who do not agree with this idea as they

feel it is a waste of time.

What should the project manager do?

Options:

A.  

Welcome and involve the contractors as part of the project team.

B.  

Ask the contractors to meet with the customer independently.

C.  

Ask the customer to develop a document with the requirements.

D.  

Warn and penalize the contractors who do not attend the meeting.

Discussion 0
Questions 191

During iteration planning, team A identifies that an important deliverable is dependent upon a deliverable from team B. What should the project manager do?

Options:

A.  

Inform team B of the dependency and ensure that the deliverable is planned.

B.  

Make team Aa part of team B and ensure that the deliverable is ready.

C.  

Request team B to immediately start this activity and deliver to team A.

D.  

Ask team B to focus on their backlog and deliver based on their priority,

Discussion 0
Questions 192

A project manager is working on an agile project in a changing business environment. The project sponsor is worried about benefits realization

and asks the project manager to pay attention to changes that can affect the project.

Which action should the project manager take to identify changes that may affect the product?

Options:

A.  

Implement face-to-face communication between the team and product owner to change the iteration objectives as needed.

B.  

Stop the iteration as soon as possible in case an external change that makes the product invaluable is identified.

C.  

Take action to reprioritize the backlog after every iteration to evaluate if user stories are still valuable to the business.

D.  

Apply a pair programming technique to react to changes immediately, even in the middle of the interaction.

Discussion 0
Questions 193

During project initiation meetings, the project manager of a 9-month project states that a specific task would be out of schedule. At the project

kick-off meeting, a key project stakeholder strongly objects, stating that this task is the key value of the project and should be completed on time.

What should the project manager do to reduce the chances of having a strong rejection from stakeholders during the project initiation stage?

Options:

A.  

Develop a stakeholder-by-stakeholder engagement assessment matrix.

B.  

Send a letter to the stakeholders to inform them about the project scope and start date.

C.  

Schedule meetings with key stakeholders in advance to gather feedback on the project scope.

D.  

Identify stakeholder rejection as a risk in the project risk register.

Discussion 0
Questions 194

A project manager is assigned to a project where a vendor has been engaged to build a new system One week before user acceptance testing (UAT) is scheduled the vendor informs the project manager that they can only deliver half of the promised functions by the UAT start date.

What should the project manager do next?

Options:

A.  

Wait until the vendor cannot deliver and then invoke liquidated damages based on the contract

B.  

Escalate to management and prepare tor project closure by canceling the contract with this vendor

C.  

Adjust the protect schedule to accommodate the current development progress of the vendor

D.  

Communicate with the vendor and project team and explore possibilities lor resolving the issue

Discussion 0
Questions 195

An urgent meeting has been established with the project team to discuss the cause of some quality issues that are preventing delivery to the client. The product owner recommends a root cause analysis (RCA).

What should the project lead do?

Options:

A.  

Facilitate the meeting so anyone can share their ideas and is heard during the session.

B.  

Allow the team to self-organize so one of the resources can lead the team to achieve consensus.

C.  

Discuss the product owner's recommendations with the team and implement the agreed-on solutions.

D.  

Discuss the recommendations with the test manager and request better quality control.

Discussion 0
Questions 196

A key project team member is out on sick leave in the middle of a critical project iteration. The project sponsor learns that any delay with the end-of-iteration release will displease the business stakeholders. Although all team members are cross-functional, they are also working close to full capacity.

What should the project manager do to address this situation?

Options:

A.  

Discuss the issues with the sponsor to fully convey the problem of the unavailable resource and the amount of work being done. shared.

B.  

Discuss this with the sponsor and hold a meeting with the stakeholders so all of the team challenges can be shared.

C.  

Discuss this with the team so they can complete the work of the unavailable team member and aim for the release deadline.

D.  

Discuss this with the team so they are able to reprioritize critical tasks and aim for the release deadline.

Discussion 0
Questions 197

A project development team is located in different areas around the world. Last week, a very important release was delayed because one of the developers did not respond on time to an email that was sent to everyone. The developer seems to have missed reading the email.

What should the project manager do to avoid these situations?

Options:

A.  

Review the risk management plan.

B.  

Review the resource management plan.

C.  

Review the communications management plan.

D.  

Review the stakeholder engagement plan.

Discussion 0
Questions 198

A new team member has joined a project team. During the first sprint, the new team member approached the project manager and requested to implement a new way of testing. The team has been resistant to the proposed change.

What should the project manager do?

Options:

A.  

Ask the new team member to focus only on development and not do the testing.

B.  

Coach the new team member to conduct the testing the way it has always been done for this project.

C.  

Schedule a meeting with the new team member to learn about the new method of testing.

D.  

Request that the new team member do the testing the way it has always been done for this project.

Discussion 0
Questions 199

A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is dissatisfied, stating that the deliverables do not meet the quality specifications.

What should the project manager do in this situation?

Options:

A.  

Notify the stakeholder that arbitration procedures will be followed.

B.  

Inform the project sponsor of the stakeholder's dissatisfaction.

C.  

Document the issue in the issue log and send a report to management.

D.  

Review the requirements traceability matrix and conduct inspections.

Discussion 0
Questions 200

A team is delivering features to a customer at every iteration. After completing each iteration, the customer is invited for a review. However, the customer is frequently not

available and the review is often delayed, which results in increased rework for the team.

What should the project manager do?

Options:

A.  

Ask the customer to review the deliverables in each iteration based on their availability.

B.  

Request the customer to clarify all requirements at the start of each iteration.

C.  

Plan ahead and define the best way to review the deliverables with the customer.

D.  

Include the customer in daily project activities to gain the required guidance.

Discussion 0
Questions 201

The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path.

What should the project manager do in this situation?

Options:

A.  

Escalate the supplier-related issues to the sponsor for resolution.

B.  

Review the work breakdown structure (WBS) with the suppliers.

C.  

Review the critical path with the stakeholders to define next steps.

D.  

Discuss the critical path issues with the purchasing department.

Discussion 0
Questions 202

A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted

that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.

What should the project manager have done to avoid this situation?

Options:

A.  

Allocated a dedicated handover team at early stages of the project

B.  

Allocated proper resources for training on BMS in the project plan

C.  

Made some adjustments to BMS to be more suitable for the teams

D.  

Brought both teams together in a joint meeting to resolve the issue

Discussion 0
Questions 203

A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?

Options:

A.  

Empower the team members to conduct their job activities and hold each person accountable to improve the schedule.

B.  

Notify the project sponsor that the team is underperforming and request additional resources to compress the schedule,

C.  

Contact each team member to inform them that further schedule slips will not be tolerated by the project sponsor.

D.  

Begin holding daily meetings to assign each team member discrete tasks with specific due dates.

Discussion 0
Questions 204

During a project meeting, the project manager expressed the importance of delivering reports on time. These individual reports will be

consolidated into a single report. One of the team member's reports was not delivered on time and therefore the report could not be integrated

with the other reports. This demonstrates a lack of teamwork and impacts project success.

What should the project manager do to resolve this issue?

Options:

A.  

Assign the task to someone else on the team.

B.  

Discuss it with the team member in confidence.

C.  

Discuss this matter during the project meeting.

D.  

Include this item in the risk register.

Discussion 0
Questions 205

A team is finishing the third release to present to the stakeholder as part of a demonstration. The company that subcontracts the developers has communicated that there is a cash flow problem and the company will not be able to provide the same resources for the next iterations.

What should the project manager do next?

Options:

A.  

Create a risk register to track the risks and request additional budget.

B.  

Analyze the impact against the release plan if the blocker is not addressed.

C.  

Work with the project owner to prioritize the product backlog.

D.  

Escalate the situation to the project sponsor for a possible resolution.

Discussion 0
Questions 206

A project manager is leading a global project with resources spread out in different locations. The stakeholders have different interpretations of the

requirements. The project manager is concerned about scope creep.

Which action should the project manager take to control the scope?

Options:

A.  

Ensure that all key stakeholders agree to the project deliverables and there will be no need for changes.

B.  

Accept only those changes to requirements that provide additional value to the project.

C.  

Reject all changes that will increase the budget or increase the time line of the project.

D.  

Accept only those changes that are approved by the change control board (CCB) prior to being implemented.

Discussion 0
Questions 207

A customer initiated a minor scope change and expects this to be completed without delays or additional costs. The project manager believes that they have adequate

authorization to make the decision themselves but is not quite sure.

What should the project manager do next?

Options:

A.  

Use the project contingency and implement the change without charging the customer, since the customer's satisfaction is top priority.

B.  

Exploit this change opportunity and calculate the cost, risk, and time, then add a reasonable margin and submit to the customer.

C.  

Use the Perform Integrated Change Control process and submit this to the change control board (CCB) for approval.

D.  

Keep the change pending and decide to take this up as part of final settlement at the end of the project.

Discussion 0
Questions 208

An agile team is required to address a technical, complex requirement that has no visual deliverable to show the customer. What guidance should the product manager provide to improve the requirement development?

Options:

A.  

Discuss this with the team and reprioritize the backlog to deliver maximum value by including a portion of the complex work.

B.  

Reprioritize the product backlog by lowering the priority of the complex activity, so it will be worked on later in the project.

C.  

Allow the team to focus and complete the complex work because it will reduce the risk of finding issues later in the project.

D.  

Inform the customer that there will not be any deliverable due to the complexity involved in the requirement.

Discussion 0
Questions 209

A company that uses a predictive approach and operates in a highly regulated market is losing profitability because its product life cycle is taking longer than those of its

competitors. A new project manager has been hired to change this scenario.

What approach should the project manager propose?

Options:

A.  

Change to an agile model, focusing primarily on the incremental life cycle, leaving the iterative approach as a next step.

B.  

Maintain a predictive approach, but increase the focus on better planning and tracking to anticipate problems and avoid delays.

C.  

Migrate to an agile model, focusing primarily on an iterative approach, leaving the incremental life cycle as a next step.

D.  

Propose a hybrid approach, leveraging the benefits of an agile approach while respecting some aspects of the company’s industry.

Discussion 0
Questions 210

A team needs to implement a mandatory compliance regulation in a product, which is required for its release. While nearing the product release, when completeness was

being verified, it was found that the compliance part was not implemented in the project.

What should the project manager do next?

Options:

A.  

Get an exception approval from the legal team.

B.  

Request the team to implement the compliance.

C.  

Ask the stakeholder to descope the compliance.

D.  

Obtain approval from management and release.

Discussion 0
Questions 211

A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case.

What should the project manager do?

Options:

A.  

Ensure the client representative is involved in the estimation.

B.  

Review the completion costs of similar projects.

C.  

Ensure that a 20% contingency is included in the estimation.

D.  

Review the lessons learned from similar projects.

Discussion 0
Questions 212

An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and followup calls with key stakeholders. The team seems to be disengaged.

How should the project manager approach this situation?

Options:

A.  

Give the team members a few days off to reduce stress.

B.  

Reduce the number of internal and external meetings.

C.  

Review team assignments and reduce the workload.

D.  

Schedule one-to-one meetings and team-building meetings.

Discussion 0
Questions 213

A project manager is reviewing a draft of the project charter with key stakeholders. During the meeting, a conflict occurs between the sponsor and the product owner.

How should the project manager deal with the situation?

Options:

A.  

Postpone the meeting and invite a subject matter expert (SME) to join the next meeting.

B.  

Continue the meeting and ask the project sponsor and product owner to take their discussion offline.

C.  

Postpone the meeting and ask the project sponsor and product owner to take their discussion offline.

D.  

Continue the meeting and use facilitation techniques to improve communication within the team.

Discussion 0
Questions 214

A project is in the execution phase. The client was actively involved in the early stages but has been less engaged lately. A number of changes to the requirements have

recently been requested.

What should the project manager do next?

Options:

A.  

Reject the changes and stay the original course as initially agreed with the client.

B.  

Review the changes and make the decision based on the project team's recommendations.

C.  

Discuss the changes with the client and jointly make the decision on how to proceed.

D.  

Review the risk register to see if mitigations have already been outlined for this scenario.

Discussion 0
Questions 215

After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are

being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting

market requirements.

What should the project manager do?

Options:

A.  

Continue the iteration and add the requested changes.

B.  

Continue the iteration and review the change with the customer.

C.  

Cancel the iteration and meet with the product owner.

D.  

Cancel the iteration and add the requested changes.

Discussion 0
Questions 216

A senior manager attends one of the project review meetings and expresses concern that the project will not meet the quality standards. What should the project manager do?

Options:

A.  

Estimate the backlog items to forecast quality.

B.  

Ask the senior manager to approve the user acceptance testing (UAT) plan.

C.  

Review the quality management plan with the senior manager.

D.  

Inform the senior manager that there are approved quality standards.

Discussion 0
Questions 217

A project manager is leading a hybrid project funded by a time and materials (T&M) agreement. The project was completed, and the client

accepted the delivery of the product. One week later, the client asked the project manager to fix two defects they found in the product. The project

manager responded with an estimate of time and money and asked the client to confirm this. The client disagreed and insisted that the work

should be done for free because it is a defect in the product.

What should the project manager have done to prevent this?

Options:

A.  

Trained client engineers to support the product after its delivery.

B.  

Reviewed the project quality control plan with the client.

C.  

Suggested a fixed-cost basis and included free bug fixes for 1 month.

D.  

Planned how the delivered product will be supported after its delivery.

Discussion 0
Questions 218

A client from the travel and hospitality industry is building software for an ongoing project. The project sponsor and key project stakeholders ask to add four new functionalities to the upcoming sprint.

What should the product owner do next?

Options:

A.  

Ask the team to start implementing the new tasks.

B.  

Add the new tasks to the current sprint backlog.

C.  

Request a change control to expand the scope with the new tasks.

D.  

Prioritize the new tasks in the planning of the upcoming sprint.

Discussion 0
Questions 219

A government procurement team has been running a vendor selection process for more than 1 year, going beyond the originally planned 6 months due to a variety of factors. Two vendors have submitted proposals that were evaluated. The project manager asked for an estimated completion date 4 weeks ago, but it was not provided.

What should the project manager do?

Options:

A.  

Work with the procurement team to build a high-level timeline.

B.  

Explain to the steering committee that vendor negotiations are unpredictable.

C.  

Ask the project sponsor to request an estimate from the procurement team.

D.  

Escalate the delay issue to the project steering committee.

Discussion 0
Questions 220

In a project, one team member has been asking for directions and what actions to take on many tasks. As a result, the team member has performed slowly in project delivery.

What should the project manager do to help this team member?

Options:

A.  

Assign another senior team member to coach the team member.

B.  

Empower the team member to make decisions.

C.  

Mentor the team member on a regular basis.

D.  

Address the team member's performance accordingly.

Discussion 0
Questions 221

In a fixed-budget project, the team has received a prioritized list of requirements and has nearly completed the first iteration. The CEO has decided to redirect the team to focus on creating a presentation for their upcoming technology summit. The CEO is not flexible about this request.

Which two actions should the project manager take? (Choose 2)

Options:

A.  

Request the CEO to assign some of the functional team members to work on the presentation.

B.  

Ask the team to work overtime to make up the time lost by supporting the technology summit.

C.  

Determine a new target completion date for the project based on the redirection of the team.

D.  

Divide the team to continue working on both the presentation and the project work.

E.  

Attempt to complete the presentation work alone so that the timeline is not negatively impacted.

Discussion 0
Questions 222

A project lead is working on an agile project to build the team's vision, including the decision-making process. It was decided that the team will

vote on items, and if 90% of the team agrees on a decision, then it will be carried forward. At the very first technical design meeting, the team

makes a decision that the project lead strongly disagrees with.

How should the project lead proceed?

Options:

A.  

Refuse to let the team proceed with the work based on their decision.

B.  

Take the technical team lead aside and try to persuade them to change their vote.

C.  

Note the reasons for the disagreement and let the team proceed.

D.  

Set up a meeting with the project champion and ask them to intervene.

Discussion 0
Questions 223

During a final investment decision meeting, all of the stakeholders were aligned on the project benefits, proposed budget, and schedule. Before final approval was given, the executive requested an aspirational target for the project team to obtain an enhanced benefit from the project.

What should the project manager do in this situation?

Options:

A.  

Accept the request and commit to some benefit improvement opportunities for the project.

B.  

Investigate the request and express willingness to find ways to obtain higher project benefits.

C.  

Review the proposal and suggest optional benefit improvement opportunities for the project.

D.  

Explain the planning and budgeting process and demonstrate that the project proposal maximizes benefits.

Discussion 0
Questions 224

A credit collection company is implementing new software to assist customer service agents when calling clients for payments. The software will benefit the company by freeing up staff to work on other projects. Several business areas want to take advantage of this benefit.

What should the project manager do?

Options:

A.  

Request all of the business areas to plan for a portion of the benefit equally and include it in their staffing plans.

B.  

Set up a stakeholder session with all teams to agree and document the benefits and establish ownership.

C.  

Ask the project sponsor for approval to distribute the project benefits equally to the business areas.

D.  

Ask the project sponsor to make a decision on who will own the benefit and document the decision.

Discussion 0
Questions 225

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?

Options:

A.  

Ask the team to raise blockers or impediments in daily meetings.

B.  

Prioritize deliverables based on business value and define frequent releases.

C.  

Ask the team to challenge the project estimations for a faster delivery.

D.  

Prioritize the tasks with high risks to reduce the number of iterations required.

Discussion 0
Questions 226

A project is about to start with a global project team. Travel is not a viable option for project team members, so most will participate virtually.

What should the project manager do to engage the team?

Options:

A.  

Have one-on-one meetings with team members to improve communication.

B.  

Ask human resources (HR) for team-building recommendations.

C.  

Schedule weekly team meetings to encourage collaboration.

D.  

Invest in a virtual collaboration/colocation environment.

Discussion 0
Questions 227

A project team's performance is being impacted by impeding internal procedures that are affecting the progress of activities and team autonomy. What should the project

manager do first to address this situation?

Options:

A.  

Try to remove the barriers and empower team members.

B.  

Ask the organization to improve the internal procedures.

C.  

Train the team members on the organization's procedures.

D.  

Discuss the issue in the next sprint review meeting.

Discussion 0
Questions 228

During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The

project manager is sure that the stakeholder was duly identified and classified in the stakeholder register.

Which project document should the project manager review in order to determine the reason for this issue?

Options:

A.  

Requirements traceability matrix

B.  

Stakeholder register

C.  

Stakeholder engagement assessment matrix

D.  

Issue log

Discussion 0
Questions 229

A team member has experienced personal conflicts on past projects, making them nervous about working on the current project. The project

manager knows this team member could add value to the project.

What should the project manager do to get the most value from this team member?

Options:

A.  

Advise the team member not to share personal information from past projects with the entire team.

B.  

Consult with the project sponsor to find out if it is allowed to share personal information with the entire team.

C.  

Advise the team member to focus on the current project and consider the past conflicts as lessons learned.

D.  

Consult with human resources (HR) and check company policies on what is allowed to advise the team member.

Discussion 0
Questions 230

The project sponsor reports that a key stakeholder is complaining about performance differences in the metrics reported by the project manager,

which gives the impression that the project is out of control. The project manager has been providing the project's status according to the agreedupon communications management plan. This key stakeholder, however, seldom attends the status report meetings.

What should the project manager do first to address this situation?

Options:

A.  

Evaluate the communication needs to discover the gaps and adjust the original plan if needed.

B.  

Use the contingency reserves to implement fast tracking and improve the schedule key performance indicators (KPIs).

C.  

Review the resource breakdown structure (RBS) to request the main stakeholder's manager to replace the stakeholder.

D.  

Provide evidence to the project sponsor that the project is on track and the communications have been sent.

Discussion 0
Questions 231

The change control board (CCB) has approved a change request to add a new component within a product. The operations manager discovers the change after its approval and complains that the implementation of the change will cause significant disruption to the production line.

What should the project manager do first?

Options:

A.  

Lead a root cause analysis workshop with the design team to identify the failures that led to the decision to add a component that was not compatible with the production line.

B.  

Meet with the operations manager to explain the background for the change and understand the operation manager's concerns about the change.

C.  

Escalate the issue to the project sponsor, as the decision to add the component brings many benefits even though it will be disruptive to the production line.

D.  

Formally acknowledge the operation manager's concerns and raise a new risk that the project may deliver late and over budget due to manufacturing difficulties.

Discussion 0
Questions 232

A project management office (PMO) director finds that the project managers leading software development projects are not consistently seeking approval from other division leaders in cybersecurity and operations before deploying code into production. The PMO director asks the project manager to develop a solution for this issue.

What should the project manager do to fix this problem?

Options:

A.  

Establish a daily scrum meeting and invite division leaders to attend so they can be aware of upcoming code releases.

B.  

Provide division leaders with a teleconference phone number to call if they have concerns after code is deployed into production.

C.  

Create a new policy requiring project managers to email division leaders before deploying code into production.

D.  

Launch an enterprise governance structure comprised of division leaders to establish policies for code releases.

Discussion 0
Questions 233

A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team

member's deliverables do not meet the requirements.

What should the project manager do first?

Options:

A.  

Assemble the project team via conference call to tell them that disciplinary action will be taken if any more noncompliant deliverables aresubmitted.

B.  

Discuss the process used to create the noncompliant deliverables with the project team to see if there was a potential misunderstanding.

C.  

Schedule time with the project sponsor to inform them that the project schedule is slipping due to the time it will take to rework thedeliverables.

D.  

Meet with the project team to explain that noncompliant deliverables must be reworked and submitted immediately to avoid project delays.

Discussion 0
Questions 234

When trying to track project benefits, a project manager realizes that some key performance indicators (KPIs) are not yet defined. What should the project manager do?

Options:

A.  

Work with the business analysts to track and collect the missing data and build the KPIs.

B.  

Coordinate with the benefit owner to track and collect the missing data and build the KPIs.

C.  

Forward the issue to the benefit owner and ask them to collect the missing data and build the KPIs.

D.  

Ask the program manager to track and collect the missing data and work to build the KPIs.

Discussion 0
Questions 235

A website application project is underway and the agile team has reached a stable velocity. After eight iterations, they complete 20 story points per sprint. The project lead and team plan to maintain the same velocity for the next 2 months. After this period, the team completed 100 story points. The project sponsor asks for the project status.

How should the project lead respond?

Options:

A.  

The cost performance index (CPI) is below average with a 25% reduction.

B.  

The schedule performance index (SPI) is 25% less than expected.

C.  

The team's performance indicator is higher than expected.

D.  

The cost and schedule performance indicators are equivalent.

Discussion 0
Questions 236

An agile project manager notices that one of the team members is developing extensive knowledge in a specific matter. Other team members are

likely to require this knowledge in the future.

What should the agile project manager do?

Options:

A.  

Ask the team member to develop more expertise and become a subject matter expert (SME).

B.  

Ask the team member to provide a training session for the rest of the team.

C.  

Ask the team member to produce a lessons learned document and share it with the team.

D.  

Ask the team member to record highlights the team may want to know.

Discussion 0
Questions 237

A major public-transportation construction project is aimed at significantly reducing emissions. The project has been severely delayed due to noncompliance with environmental codes and bylaws.

What should the project manager have done to prevent this?

Options:

A.  

Incorporated sufficient schedule reserves based on similar delays in past projects.

B.  

Appointed a senior environmental compliance officer to report directly to the project manager.

C.  

Mapped environmental compliance requirements, identified risks to achieving them, and prepared mitigations.

D.  

Approached the regulator for a partial waiver in light of the environmental importance of the project.

Discussion 0
Questions 238

A project manager is leading a project that needs to be deployed quickly to the market. An influential stakeholder does not believe that the project management processes bring business value.

What can the project manager do to gain the support of the stakeholder?

Options:

A.  

Ask the stakeholder for a meeting to review the project's charter and project management plan.

B.  

Disregard the stakeholder's concerns and continue following the project management plan to execute the project.

C.  

Hold a training workshop to educate the stakeholder about project management best practices.

D.  

Clarify the project roles and responsibilities, and share the purpose to gain the stakeholder's buy-in.

Discussion 0
Questions 239

A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second

iteration, the project manager realizes that a significant regulatory feature is missing in the project backlog.

What should the project manager do?

Options:

A.  

Ask the product owner to add the missing feature in the backlog.

B.  

Invite stakeholders to discuss the impact of adding the regulatory feature.

C.  

Estimate the related cost and ask for a project extension.

D.  

Increase the capacity of the team to include the missed feature.

Discussion 0
Questions 240

A project manager has been assigned to deliver a challenging project on time and within budget. The project manager needs to empower the team members by removing organizational impediments and facilitating collaboration.

What should the project manager do to lead the project?

Options:

A.  

Use a servant leader approach.

B.  

Assume the functional manager role.

C.  

Perform the project sponsor activities.

D.  

Act as the project owner.

Discussion 0
Questions 241

An organization is transitioning to agile delivery, and a new team has been assembled. A project is not going well because the variation of the team velocity is very high and every sprint delivers less than committed. A new project lead with a strong technical background has been assigned to the project.

What should the project lead do?

Options:

A.  

Ask that estimations be provided only by senior developers.

B.  

Allocate more time for estimation in the sprint planning.

C.  

Review and update the estimations in the daily standup.

D.  

Recommend a different estimation method in the retrospective.

Discussion 0
Questions 242

A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.

What should the project lead do?

Options:

A.  

Register an issue and escalate it to the project sponsor.

B.  

Invite the stakeholders to discuss a new prioritization.

C.  

Estimate the management to replace the customer service manager.

D.  

Increase the team capacity to finish the project on time.

Discussion 0
Questions 243

There is frequent conflict between two project team members working on a project. This has caused a negative impact on the project.

How should the project manager handle this situation?

Options:

A.  

Counsel both team members and caution them with a final warning.

B.  

Escalate the issue to the human resources (HR) manager before a larger problem develops.

C.  

Help cultivate self-awareness between the two team members through emotional intelligence (El).

D.  

Relocate the two project team members into different project teams.

Discussion 0
Questions 244

In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in

a couple of months. The licensing cost is significant.

What should the project manager do next?

Options:

A.  

Evaluate the impact of nonrenewal of the license.

B.  

Escalate the licensing issue to the product owner.

C.  

Add a spike to the backlog for an alternative design.

D.  

Raise a change request to secure the renewal.

Discussion 0
Questions 245

Anew engineer was assigned to a project. Although the engineer has adequate skills for the job, they always wait for authorization from the

project manager before acting.

What should the project manager do?

Options:

A.  

Obtain related training for the new team member.

B.  

Determine the appropriate level of decision-making authority and empower the engineer.

C.  

Make all of the decisions for the engineer in order to keep the workflow on track.

D.  

Replace the resource with an experienced engineer.

Discussion 0
Questions 246

While a project manager is trying to build the first baseline for a project, a change request is being sent from one of the functional managers. What should the project manager do?

Options:

A.  

Discuss this with the functional manager and related parties.

B.  

Reject the functional manager's change request immediately.

C.  

Analyze the impact of the change request on the project.

D.  

Apply for a formal change control board (CCB) approval.

Discussion 0
Questions 247

A project manager for an agile project is concerned that the team has been losing momentum over the last iterations. Which two tools should the project manager use to

analyze team performance? (Choose two)

Options:

A.  

0Project schedule

B.  

Product backlog bumup chart

C.  

Work breakdown structure (WBS)

D.  

Cumulative flow diagram of completed features

E.  

Burndown chart

Discussion 0
Questions 248

A project manager is planning a project with multiple work packages. Each work package has its own defined scope, but funding will be at the project level.

How should the project manager determine if the allocated resource budget is sufficient to cover the resource costs of the project?

Options:

A.  

Divide the allocated budget by the number of work packages and verify that each work package can be completed within the allocated budget.

B.  

Estimate the costs at the work package level and add those costs to calculate the total cost of the project and compare it to the allocated budget.

C.  

Create a budget burndown and a scope burnup and then verify that the project scope is completed before the allocated budget is depleted.

D.  

Fund each work package in the order of its importance and shift any remaining scope from nonfunded work packages to funded work packages.

Discussion 0
Questions 249

During a project's execution phase, two team members are having conflicts with other team members within the team on technical and interpersonal levels. Which two actions should the project manager take first to address this conflict? (Choose two)

Options:

A.  

Ask human resources (HR) to intervene before it escalates and affects the team's performance.

B.  

Arrange individual meetings with the team members who cannot work together effectively.

C.  

Address the conflict during team meetings for the entire team to participate and find solutions.

D.  

Discuss the conflict early among the affected team members using a direct, collaborative approach.

E.  

Plan to resolve the team members' conflicts after the sprint and focus on achieving the goal.

Discussion 0
Questions 250

A company is implementing a growth strategy by constructing a new production facility, which will soon move into the operation phase. Although a governance policy was already in place, the company must comply with new financial regulations that have been recently implemented. Compliance with the regulations will cause a major change

in project scope.

How should the project manager respond to this requirement?

Options:

A.  

Proceed with the existing company governance policy.

B.  

Perform an analysis to assess the impact on the project.

C.  

Directly comply with the financial regulations.

D.  

Escalate the issue to upper management and let them decide.

Discussion 0
Questions 251

In a daily standup meeting, a developer indicates that a backlog item will not be delivered because they need to take an unexpected leave for the next couple of days. The backlog item is a prerequisite for a feature expected by users in the next sprint review.

What should the project lead do?

Options:

A.  

Ask the developer to postpone the leave until the backlog item is delivered.

B.  

Ask the development manager to provide a replacement for a couple of days.

C.  

Work with the product owner to change the priorities in the sprint backlog.

D.  

Work with the product owner to inform the users that the feature is delayed.

Discussion 0
Questions 252

A construction company is executing a building contract that includes firm milestones for replacing certain components of the building. During execution, the client complains that the new components do not meet the requirements.

What should the project manager have done to prevent this from happening?

Options:

A.  

Defined acceptance criteria in a quality checklist agreed upon before starting the build phase

B.  

Approved a detailed change management process before starting the build phase

C.  

Provided compensation for issues due to the variance in the agreed-upon requirements

D.  

Continuously communicated the changes in the work plan and the agreement to the client

Discussion 0
Questions 253

A project charter has been approved and the project manager has been assigned to the project. The project manager is currently working with the project team to subdivide the project work packages.

What is the project manager doing?

Options:

A.  

Network diagram

B.  

Decomposition

C.  

Work breakdown structure (WBS)

D.  

Resource leveling

Discussion 0
Questions 254

A junior project manager was recently hired to lead a complex project scheduled to kick off in 2 weeks. The junior project manager was introduced to another project

manager for mentoring.

Which two benefits will the junior project manager realize by being assigned to a mentor? (Choose two)

Options:

A.  

The junior project manager reports administratively to their mentor so that human resource (HR) questions can be answered quickly.

B.  

The junior project manager can discuss certain problems with their mentor without fear of retribution.

C.  

The mentor will be immediately available to take over the project if there are problems or project delays.

D.  

The mentor will be involved in the decision-making processes implemented by the junior project manager.

E.  

The mentor can provide past project documentation with early warning indicators that potential problems could occur.

Discussion 0
Questions 255

An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.

What should the project manager do?

Options:

A.  

Add 4 additional weeks to the schedule and request additional resources.

B.  

Ask the sponsor to obtain a special work permit to continue work.

C.  

Review the project management plan to see the impact of the possible delay.

D.  

Crash the resource management plan to keep the schedule on track.

Discussion 0
Questions 256

An agile team is developing a new content management system. Some of the team members are struggling to deliver certain features since they have never worked on this type of solution.

What should the project manager do?

Options:

A.  

Replace the members with new members who understand the system.

B.  

Encourage the team members to make changes directly in the system.

C.  

Ask the team to read through all of the available system documents.

D.  

Encourage the team to hold a knowledge-sharing session in each iteration.

Discussion 0
Questions 257

A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.

What should the project manager do?

Options:

A.  

Update the project management plan and adjust the project budget with this change request.

B.  

Raise a change request to the change control board (CCB) and inform the project sponsor about the change.

C.  

Ask the key stakeholder to take the lead in handling the request since they are more knowledgeable.

D.  

Request a meeting with the stakeholders and their team members to inform them about this change.

Discussion 0
Questions 258

A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses to approve the proposed project plan.

What should the project manager do to gain an understanding of the cause for the resource's refusal?

Options:

A.  

Speak directly with the resource.

B.  

Communicate with their supervisor.

C.  

Organize a team meeting.

D.  

Speak with their colleague.

Discussion 0
Questions 259

A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and

delay new feature development.

Which action should the project manager take to resolve the quality issues?

Options:

A.  

Plan for continuous validation of the product.

B.  

Discuss adding business scenario tests with the customer.

C.  

Discuss adding additional test cases with the product owner.

D.  

Add more test scenarios based on the issues found.

Discussion 0
Questions 260

A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.

What should the project manager do?

Options:

A.  

Study and determine the appropriate leadership style suitable for the team.

B.  

Hire a project team leader who can influence the project team members.

C.  

Schedule a meeting and communicate the performance concern to the team.

D.  

Apply an agile approach to help improve team performance.

Discussion 0
Questions 261

A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.

What strategy should the project manager use?

Options:

A.  

Focus on the implementation of a software as a service (SaaS) solution for the customer.

B.  

Specify the scope and features to be deployed in the contract clearly.

C.  

Work very closely with the customer and third parties to meet their needs.

D.  

Change the marketing and product management definitions to meet stakeholder needs.

Discussion 0
Questions 262

During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail

the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.

What should the project manager do next?

Options:

A.  

Escalate the issue to the engineer's functional manager.

B.  

Discuss the issue with the engineer and determine how to prevent another problem.

C.  

Document the task on the kanban board and make it the highest priority.

D.  

Assign another engineer to the task due to the urgency.

Discussion 0
Questions 263

An agile team is facing a challenge with the quality of its deliverables. Every time a feature is promoted to production, many defects arise, preventing the customers from properly using the solution.

What should the project manager do to avoid this situation in the future?

Options:

A.  

Create a team incentive program with prizes, allowing the team members to work overtime to find defects.

B.  

Reduce the release cycle and invest more time on stabilizing the current features instead of releasing new ones.

C.  

Hire a quality assurance specialist and integrate a second phase of testing into the current project life cycle.

D.  

Use the next retrospective to understand the root cause of the quality issues and have the team come up with an action plan.

Discussion 0
Questions 264

A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the

processes and procedures, the project manager notices similarities to a previous project that experienced similar roadblocks. The project manager

reviews the task schedule and finds that certain tasks are well behind expectations. In speaking with the project team, the project manager

confirms that the team is following the processes exactly.

What should the project manager do?

Options:

A.  

Update the schedule to account for the unexpected delays in the project tasks.

B.  

Review the resources allocated to the project and change accordingly.

C.  

Review and amend the processes to ensure only value-adding activities are present.

D.  

Update the variation register to account for the extended project time.

Discussion 0
Questions 265

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?

Options:

A.  

Select members for their skill or potential.

B.  

Establish the project scope and set clear team objectives.

C.  

Set performance standards and direction.

D.  

Hold early kick-off meetings and regular weekly meetings.

Discussion 0
Questions 266

During the execution phase of a project, a project manager notices that the project team is not motivated and performance is decreasing. The decision is made to invest in financial rewards for all of the Key team members. After the rewards are distributed, the team is still underperforming.

What should the project manager have done to avoid this situation?

Options:

A.  

Determined the appropriate type of incentive for key team members

B.  

Conducted frequent monitoring on key team members’ performance during project execution

C.  

Distributed the monetary incentive according to the team members’ individual performance

D.  

identified the underperforming team members and asked the human resources (HR) department to replace them

Discussion 0
Questions 267

A team member has very strong technical skills and is interested in a leadership role. A leadership position opens up outside of the team in the organization. The project manager has observed that the team member has a major gap in communicating in a professional manner.

What should the project manager do?

Options:

A.  

Suggest the team member focus on positions with technical aspects and possible technical career opportunities.

B.  

Recommend the team member for effective communication training and support their career development interests.

C.  

Encourage the team member to stay in their current role as they are important to the project.

D.  

Ask the team member to refrain from pursuing new opportunities as they are not a suitable fit for a leadership position.

Discussion 0
Questions 268

A key team member informs the project manager that they have been accepted to a master’s degree program. The team member explains that the first semester of the master's program will coincide with the last phase of the project.

What should the project manager do?

Options:

A.  

Ask the team member to delegate some of their tasks to another colleague during the last phase of the project.

B.  

Suggest the team member postpone their enrollment in the master's program until the project is completed.

C.  

Ask the team member to inform human resources (HR) about their enrollment in the master's program.

D.  

Assess the team member's commitment to the master's program and its impact on project performance.

Discussion 0
Questions 269

A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.

What should the project manager do first?

Options:

A.  

Formalize the product owner assignment.

B.  

Review similar projects in the company.

C.  

Set the project's purpose, mission, and vision.

D.  

Carry out the product backlog creation.

Discussion 0
Questions 270

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of

risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk

mitigation plan.

What should the project manager do?

Options:

A.  

Submit the new response plan to the stakeholders for their review.

B.  

Obtain management approval prior to implementing the new risk response.

C.  

Use the management reserve to mitigate the risk.

D.  

Implement the new response to address the risk.

Discussion 0
Questions 271

During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.

A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.

How should the new project manager address these concerns?

Options:

A.  

Allow the agile team to decide what they are able to deliver in each iteration

B.  

Ask the team for additional feedback and add tasks to the task board,

C.  

Hold a brainstorming session to identify the root cause of the complaints.

D.  

Document the customer's complaints and critical issues in the issue log.

Discussion 0
Questions 272

A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made a recommendation regarding the project. The project charter was recently approved.

How should the project manager address the employee's request?

Options:

A.  

Evaluate the employee's recommendation by reviewing the lessons learned from a similar project.

B.  

Create a salience model to determine if the employee will have influence on the project.

C.  

Ask the project sponsor to revisit the project charter to consider the employee's recommendation.

D.  

Assess the influence and power of the employee to see if the employee will add value.

Discussion 0
Questions 273

During a project's initiation phase a lessons learned sharing session was held with the team from another project Low construction productivity was discussed as a potential delay to project completion

What should the project manager do next?

Options:

A.  

Discuss this issue with the project sponsor to request additional funding to implement mitigation

B.  

Hire a construction management consultant to develop a comprehensive site execution plan

C.  

Prequalify contractors with proven track records to eliminate productivity concerns

D.  

Add construction productivity to the risk register and develop a mitigation strategy for site execution

Discussion 0
Questions 274

A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of

the team. What should the project manager do?

Options:

A.  

Move the task to the next sprint.

B.  

Ask the team member to bring up the concern in the next daily meeting.

C.  

Send an email explaining the issue to all team members.

D.  

Reassign the task to another team member.

Discussion 0
Questions 275

A project manager works in an organization that embraces using different project approaches. The project manager's current project uses a

predictive approach with clear requirements. A few months following the kickoff, the project manager notices that the virtual development teams

are not communicating enough, and coordination is becoming an issue. The teams are not aligned on the tasks being done or the current

impediments.

What should the project manager do?

Options:

A.  

Ask the members to be more proactive and share ideas with each other.

B.  

Set up a daily virtual meeting with the development team.

C.  

Plan a monthly virtual meeting to align and to review the plans.

D.  

Review the issue with the project sponsor and ask for support.

Discussion 0
Questions 276

During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component

managed by an external vendor. How should the project manager address the team member's concern?

Options:

A.  

Ask the team member to resolve the issue independently to minimize further delays.

B.  

Ask the team member to provide details to address the issue with the vendor.

C.  

Implement fast tracking to reduce the impact of the delay on the sprint.

D.  

Update the communications management plan to prevent future reoccurrence.

Discussion 0
Questions 277

An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience

performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.

How should this situation be handled?

Options:

A.  

Use a robotics vendor company to develop the interfaces so the team will not be held back by a lack of expertise in this type of work,

B.  

Add an experienced professional to the team to reinforce knowledge sharing and help grow team expertise in the new product

C.  

Create a separate team with experienced members who understand the technology and split the product backlog according to team specialization.

D.  

Hire a consulting company to address the robotic interface questions, when necessary, and to help avoid delays and quality issues.

Discussion 0
Questions 278

During execution of an agile project, a project manager realizes the budget is almost completely used, but the project is not close to being completed. What should the project manager do to address this concern?

Options:

A.  

Review the project time line and find opportunities to reduce the project schedule.

B.  

Review the budget with the project sponsor and ask for an increase to the budget

C.  

Review the backlog and find opportunities to reprioritize the work and reduce the project scope

D.  

Review the resource management plan and find opportunities to reduce project costs.

Discussion 0
Questions 279

In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the project vulnerable.

What should the project manager do?

Options:

A.  

Ensure the activities of this team member are distributed across the project team.

B.  

Assess a mechanism for knowledge transfer among the team members.

C.  

Motivate the team member to stay by providing them with incentives.

D.  

Ask human resources (HR) to counsel the team member to balance the workload.

Discussion 0
Questions 280

In an agile project, some stakeholders are asking to have a meeting with the team every 2 weeks in order to understand project progress. What

should the project lead do next?

Options:

A.  

Invite the stakeholders to the retrospective meetings.

B.  

Invite the stakeholders to the sprint review meetings.

C.  

Hold a meeting every 2 weeks with the stakeholders.

D.  

Negotiate by sending an informative email to stakeholders.

Discussion 0
Questions 281

In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope.

What should the project manager do?

Options:

A.  

Organize a meeting with the team and update the work breakdown structure (WBS).

B.  

Raise this issue, and review and update the progress report for the next monthly project meeting.

C.  

Start the organization's change control process via a change request.

D.  

Communicate with an officer in the environmental protection department to check if it is necessary.

Discussion 0
Questions 282

A project manager is assigned to a project to develop a mobile app. The sponsor explains that the application should do better than their closest competitor's app. The sponsor's expectation is that the team can be put together and start work immediately.

What should the project manager do?

Options:

A.  

Start working on the resource management plan in order to identify the best team for the project.

B.  

Utilize expert judgment and organizational process assets (OPAs) to estimate the effort and budget.

C.  

Review the competitor's app to understand the functionalities that the project scope should consider.

D.  

Define the project scope with the stakeholders and determine how formal acceptance will be obtained.

Discussion 0
Questions 283

A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved.

How should the project manager proceed?

Options:

A.  

Proceed with both the prefeasibility and feasibility studies in parallel while waiting for (he final approvals

B.  

Include the feasibility activities in the prefeasibility study and apply for a change of scope and budget.

C.  

Obtain approval to proceed with the feasibility study as a parallel activity while the prefeasibility study is approved

D.  

Secure approval of the prefeasibility study before proceeding with the feasibility activities.

Discussion 0
Questions 284

In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in

conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?

Options:

A.  

Anticipate, alert, and follow the risk management process.

B.  

Detect, track, and follow the issue management process.

C.  

Promote, inspire, and follow the stakeholder engagement process.

D.  

Discuss, educate, and follow the communications management process.

Discussion 0
Questions 285

A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the increment is ready to be delivered to the customer.

What conclusion should the project manager come to with regard to the product owner's statement?

Options:

A.  

The product owner does not have visibility into what the team has done in the product increment.

B.  

The product owner trusts the team and is marking the product as complete.

C.  

The product owner has evaluated the product against the definition of done (DoD).

D.  

The product owner will release the product to customers without showing them a demo.

Discussion 0
Questions 286

A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.

What should the project manager do?

Options:

A.  

Review the requirements of the report with the team member to redefine its purpose.

B.  

Escalate to the team member's functional manager that the report was not submitted as requested.

C.  

Instruct the team member to provide the report and document this in the performance review.

D.  

Reassign the report to another team member to prepare and submit it as requested.

Discussion 0
Questions 287

A few new team members working on a public housing project are unfamiliar with the system. They do not understand how to evaluate residents applying for a subsidy to build a house, including the rules and criteria for applicant approval.

What should the project manager do?

Options:

A.  

Plan a training session for the new team members not familiar with the system.

B.  

Communicate the rules and criteria to the team members through email.

C.  

Work only with the team members familiar with the system

D.  

Document which rules and criteria the new team members are not familiar wit

Discussion 0
Questions 288

A project manager has recently taken over a project and notices that a client team member often halts progress due to a lack of understanding of some project elements.

The former project manager gave the new project manager a complete list of people to communicate with, and this client team member is not on it.

What should the project manager do?

Options:

A.  

Update the communications matrix to ensure that client team member is included.

B.  

Submit a change request to cover extra hours associated with project meetings.

C.  

Increase the project meeting frequency and duration to allow for the extra work required.

D.  

Speak with the client team member about the continuous delays during project meetings.

Discussion 0
Questions 289

An agile team wants to maximize the work delivered for the upcoming project that involves considerable product complexity. What should the

project manager do to help improve the team's collaboration approach?

Options:

A.  

Meet with the human resources (HR) department to ask for team support.

B.  

Follow the process of the most successful team in the organization.

C.  

Compare the team's velocity with other teams in the organization.

D.  

Focus on the team's engagement during the next retrospective meeting.

Discussion 0
Questions 290

The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could

resolve the bottleneck, and the project manager has been informed.

What should the project manager do next?

Options:

A.  

Add developers to remove the backlog.

B.  

Escalate the issue with the product owner.

C.  

Reduce the testing scope of the backlog.

D.  

Enroll team members in training on the tool.

Discussion 0
Questions 291

A project manager has taken over a project that has been without a project manager for the last couple of weeks. The team is feeling lost and there are a few team

members who are confused about the next steps and the final outcome of the project.

What should the new project manager do?

Options:

A.  

Avoid conflict and let the team self-organize on how they want to work on the project tasks.

B.  

Ask the project sponsor to provide team members with a project direction regarding outcomes.

C.  

Set short-term goals in order to create a winning culture internally and praise team members for achieving them.

D.  

Escalate the situation to the steering committee and request that more time be allotted to the project.

Discussion 0
Questions 292

The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team

Which two actions should the project manager take? (Choose two)

Options:

A.  

Review the issue with project sponsor and submit a change request

B.  

Report the issue to the product manager and business segments

C.  

Analyze the business benefits criteria and assumptions

D.  

Discuss the issue with the operations team to assess expense overruns

E.  

Schedule a project review meeting to analyze the root cause

Discussion 0
Questions 293

A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.

What should the project manager do next ?

Options:

A.  

Use the team's connections with international colleagues to get early warnings on future changes.

B.  

Keep the focus on the priority items while the change goes through the change control process.

C.  

Reject the change request since it may negatively impact the project's performance.

D.  

Implement the change request as soon as possible to avoid accumulating new scope.

Discussion 0
Questions 294

A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.

What should the project manager do?

Options:

A.  

Assign a development team member to have the responsibility of managing dependencies.

B.  

Suggest that each project develops a high-level plan to monitor the dependencies

C.  

Recommend switching to a predictive approach to have detailed plans to manage the dependencies

D.  

Continue the project with 2-week iterations as dependencies will be managed individually

Discussion 0
Questions 295

A project manager is managing a complex project with a high number of artifacts. Some of the stakeholders are having issues accessing the artifacts. How should the project manager address this situation?

Options:

A.  

Ensure that the project artifacts are kept up-to-date and shared with the stakeholders.

B.  

Invite the stakeholders to the daily standup to clarify any questions about the project artifacts.

C.  

Escalate the stakeholders' project artifacts concerns to the project management office (PMO) for resolution.

D.  

Send an agile report to the stakeholders, which includes the list of the project artifacts.

Discussion 0
Questions 296

A project manager is working with several junior engineers on a project. The project manager noticed that when the junior engineers are asked questions, they defer te more senior team members on the team for answers. Having worked with the junior engineers on another project, the project manager knows they are capable of making these minor decisions correctly.

This uncertainty from the junior engineers is now slowing progress.

‘What should the project manager do?

Options:

A.  

Update the risk register to reflect the possible impact of the projects slower progress,

B.  

Ensure the junior engineers make decisions within a certain responsibility level and commit to it,

C.  

Remove the junior engineers from any decision-making activity until further trained.

D.  

Pair senior engineers to shadow the junior engineers and correct them throughout.

Discussion 0
Questions 297

A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.

Which action should the project manager take to address the sponsor's request?

Options:

A.  

Work with the organization's real estate department and reach out to the local government to identify the best location for the store.

B.  

Work with the local government to build the profiles of employees that will be working in the store.

C.  

Work with the organization's legal department to identify local regulations to ensure project compliance.

D.  

Work with the organization's project management office (PMO) to build a project team of residents located in the city.

Discussion 0
Questions 298

A project team member informs the project manager that a stakeholder is contacting the team member to request status updates. The team member is being distracted by these repeated requests, which are interfering with the completion of assigned tasks.

What should the project manager do?

Options:

A.  

Increase the frequency of updates given to this stakeholder.

B.  

Inform the team member to stop sending any further updates to the stakeholder.

C.  

Raise this issue to the project sponsor in the next project status review meeting.

D.  

Review this stakeholder's communication requirements.

Discussion 0
Questions 299

A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The

project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another.

What should the project manager do?

Options:

A.  

Ask the experienced members to lead the junior members to facilitate skill transfer.

B.  

Encourage team members to focus on delivering results with their specialized skills.

C.  

Organize networking sessions to allow the team members to get to know one another.

D.  

Ask the team to self-organize and escalate any issues to the project manager.

Discussion 0
Questions 300

A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to

ensure the community members are up to date on project progress?

Options:

A.  

Share project updates when requested by the stakeholders.

B.  

Share project updates through regular community meetings.

C.  

Share the annual reports virtually and in the local newspapers.

D.  

Share the project reports with the sponsor to inform community members.

Discussion 0
Questions 301

A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.

What should the project manager do next?

Options:

A.  

Foster knowledge sharing and coaching among team members.

B.  

Arrange for external training amid the tight project schedules.

C.  

Add new members for the underperforming team.

D.  

Seek an external expert to review the framework.

Discussion 0
Questions 302

A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the

project manager ensure that the needs of stakeholders are consistently met?

Options:

A.  

Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.

B.  

Add more iterative techniques to improve stakeholder learning.

C.  

Identify all the critical stakeholders during the project initiation.

D.  

Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.

Discussion 0
Questions 303

During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain

feedback from on project deliverables. What should the project manager do?

Options:

A.  

Share a template with the stakeholder to receive feedback on deliverables.

B.  

Ask the project sponsor to arrange a meeting with the stakeholder.

C.  

Use networking skills to approach the stakeholder.

D.  

Update the stakeholder engagement plan for the stakeholder.

Discussion 0
Questions 304

A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist

from the team was average.

What should the project manager do to help the new compliance specialist improve?

Options:

A.  

Escalate this situation to the manager of the area for a possible solution.

B.  

Provide time for the specialist to adjust to the pace of the project.

C.  

Coordinate a one-to-one meeting with the specialist to assess the situation.

D.  

Contact the human resources (HR) manager about the team's feedback.

Discussion 0
Questions 305

A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed

for the product.

What should the project manager do to continue with the delivery plan and return to the expected velocity?

Options:

A.  

Use retrospectives to better understand the new technology's impact on the schedule, map the skill gaps, and adjust the team accordingly.

B.  

Reevaluate the backlog by looking for high-value/low-effort items, and negotiate a new minimum viable product (MVP) strategy with key stakeholders.

C.  

Seek sponsor approval for additional funding to hire new team members, increasing the capacity of the team and compensating for the productivity lost with the new technology.

D.  

Replace poorly performing team members with more experienced members, setting an example of accountability for the team.

Discussion 0
Questions 306

A project manager just completed the planning phase when a new stakeholder was assigned to the project. The deliverables were discussed with the customer, but the new stakeholder is still concerned about the benefits of two of the deliverables.

What should the project manager do next to address this stakeholder’s concerns?

Options:

A.  

Review the benefits realization plan with the stakeholder.

B.  

Provide the stakeholder with regular updates on project progress.

C.  

Add the stakeholder to the stakeholder engagement plan.

D.  

Review the prior analysis results with the stakeholder.

Discussion 0
Questions 307

A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.

What should the project manager do next?

Options:

A.  

Add the new requirements to the project scope immediately since they are mandatory changes.

B.  

Review the new requirements with the compliance department to determine if a change request is needed.

C.  

Ignore the new requirements as the current budget and schedule do not allow for any changes.

D.  

Proceed with the defined project requirements and delay implementing the new requirements.

Discussion 0
Questions 308

A product owner has added new high-priority work to the backlog, A project manager is working with a dedicated agile team that does not specialize in this specific area of work. The team reviewed the work and wants to accept it but acknowledges it may not have the same level of efficiency as another team having specialization in this area.

What should the project manager do In this scenario?

Options:

A.  

Add temporary members with the specialized skill set to the team to accomplish the work with a high level of confidence.

B.  

Assess the impact of a possible delay to the project and encourage the team to take the work if the impact is tolerable.

C.  

Accept the work and outsource it to another team that has the specialized skill set; then integrate the solution,

D.  

Reject the work from this team's backlog and ask the product owner to add It to another team's backlog.

Discussion 0
Questions 309

A newly assigned project manager is reviewing the project management plan and realizes that the project is running behind schedule. What should the new project manager

do to address this situation?

Options:

A.  

Modify the project management plan and get approval from relevant stakeholders

B.  

Add more resources to recover the schedule without making changes to the baseline.

C.  

Issue a change order to the change control board (CCB) and rebaseline the schedule.

D.  

Negotiate with the project sponsor immediately and establish a new project charter.

Discussion 0
Questions 310

A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.

How should the project manager establish the delivery model for this project?

Options:

A.  

Organize the project into multiple subsets based on business functions and deliver each subset as a component of the final product.

B.  

Reestablish the project as a program with multiple small projects, as each project will be delivered as a product of its own.

C.  

Communicate the latest status to the steering committee and provide a demo of the features completed.

D.  

Schedule routine demos on features completed and deliver a single product once all features are completed.

Discussion 0
Questions 311

A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide.

What should the project manager do?

Options:

A.  

Invite the sales manager to the next sprint meeting to clarify requirements.

B.  

Create a new item in the sprint backlog to determine the appropriate algorithm.

C.  

Ask the scrum master to choose an algorithm based on the pros and cons of each option.

D.  

Request a meeting with the product owner to help clarify the user story.

Discussion 0
Questions 312

An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is

informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.

What should the project manager do first?

Options:

A.  

Prioritize the upgrade of project machines with the IT department.

B.  

Inform the product owner and request more project resources.

C.  

Schedule a session with stakeholders to understand the impact.

D.  

Add product backlog items to prioritize operating system stories.

Discussion 0
Questions 313

A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?

Options:

A.  

Hold an emergency project team meeting to discuss the situation.

B.  

Ask the human resources (HR) manager for an external replacement.

C.  

Log the situation in the issue log.

D.  

Update the key stakeholders on the issue.

Discussion 0
Questions 314

A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.

What should the project manager do?

Options:

A.  

Adopt the same timeframe as the closed project for the current project.

B.  

inform the sponsor that the activity list is not adequate for creating a schedule baseline.

C.  

Create a draft schedule based on the activity list and the historical data from the closed project.

D.  

Evaluate each activity duration and build a new project schedule.

Discussion 0
Questions 315

A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule.

What should be me project manager's response?

Options:

A.  

Sprint plan and product roadmap

B.  

Product roadmap and sprint backlog

C.  

Product backlog and scrum board

D.  

Sprint backlog and scrum board

Discussion 0
Questions 316

An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project.

The team estimates the risk level as low.

What should the project manager do?

Options:

A.  

Capture all the backlog entries assessed by the development team to have evidence that risk management has been completed

B.  

Create a risk register to identify, capture, review, and manage risks using a risk management process.

C.  

Trust the development team's risk estimation and inform the project sponsor that the risks will be evaluated at a later time.

D.  

Create a risk register and include a single generic risk, set the level to low, and then close the risk at the end of the project.

Discussion 0
Questions 317

A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does

not have a requirement for it.

What should the project manager do?

Options:

A.  

Ask the team to collect the knowledge locally and share it at the end of the project.

B.  

Utilize the cloud wiki to collect the necessary knowledge.

C.  

Coordinate with the team and the project stakeholders to collect the knowledge.

D.  

Provide just-in-time knowledge to the client, upon request.

Discussion 0
Questions 318

A technology project is delivering new functionality on a new platform. Several team resources are starting to train their teams, but they are asking questions about the training that the project will provide.

What should the project manager's first action be?

Options:

A.  

Indicate that on the new technology is the functional manager's responsibility.

B.  

Review the project charter to determine if the training is in scope and, if not, put in a change request.

C.  

Consult with the organizational change management specialist as to what the training plan includes.

D.  

Document the skill requirements for the product to determine what training is needed.

Discussion 0
Questions 319

A project manager is reviewing the lessons learned for an historical project. The review identifies that the client's engineer was adamant that they review all changes, even those not identified in the contract.

How should the project manager deal with this when planning the project?

Options:

A.  

Ensure the change management plan highlights this requirement to prevent future issues.

B.  

Update the project charter with this information regarding change management.

C.  

Update the project risk register to identify this risk and describe how to mitigate the issue.

D.  

Talk with the client to ensure they are aware of the change management procedure.

Discussion 0
Questions 320

A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team members from different continents.

What should the project manager do to ensure a successful project execution?

Options:

A.  

invite all resources to the project manager's location to form a cohesive team until all deliverables are completed,

B.  

Send emails with information about the project deliverables on the first day of the project.

C.  

Connect with every location and check their preferred methods of communication.

D.  

Plan for a meeting with the project sponsor to discuss the possibility of utilizing only local colleagues.

Discussion 0
Questions 321

During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?

Options:

A.  

Keep activities as planned regardless of the resource change.

B.  

Update the burndown chart to reflect this resource's absence.

C.  

Have a meeting with the resource to understand the issue.

D.  

Request an additional resource to finish the project.

Discussion 0
Questions 322

Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information

should the project manager provide so that senior management can get a broader view of the project?

Options:

A.  

Risk register information

B.  

Higher-level activities completed

C.  

Milestones status report

D.  

Resource breakdown structure (RBS)

Discussion 0
Questions 323

A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget.

What should the project manager do?

Options:

A.  

Use the existing budget for executing the fallback plan and update the baseline.

B.  

Add additional resources to the project to fast track certain activities and reduce delays.

C.  

Evaluate the fallback plan proposed by the team and submit a change request, if required.

D.  

Communicate the delay to stakeholders and maintain the existing budget baseline.

Discussion 0
Questions 324

A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday

morning. Due to an unexpected issue, 50% of the team has to work from home. The bank's management directed the team not to have in-person daily standups. Various team members are complaining about this, stating that there is a lack of information sharing among the team

What should the project manager do?

Options:

A.  

Postpone the daily standups and ask the team members to update the project manager daily via messaging.

B.  

Hold virtual daily standups each workday morning and use collaboration tools to manage project updates.

C.  

Delegate authority to the team members and ask them to submit weekly status reports instead.

D.  

Ask senior management for permission to hold in-person team meetings once each week.

Discussion 0
Questions 325

While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because

of that, each feature is taking longer than initially estimated.

What should the project manager do to address the issue?

Options:

A.  

Escalate the issue to the project sponsor.

B.  

Address the issue during the next sprint planning meeting.

C.  

Initiate a change request to extend the project end date.

D.  

Extend the dates for future project milestones.

Discussion 0
Questions 326

An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?

Options:

A.  

Meet with the project team to develop a proper resolution to the issue.

B.  

Update the project artifacts to reflect the new deadlines reported.

C.  

Request approval from the project sponsor to add more resources,

D.  

Prepare documentation to explain the issue and communicate accordingly.

Discussion 0
Questions 327

A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done.

What should have been done to avoid this problem?

Options:

A.  

Included lessons learned from past projects

B.  

Used bottom-up estimating

C.  

Utilized three-point estimates

D.  

Validated the schedule performance index (SPI) to evaluate deviation

Discussion 0
Questions 328

A project manager holds meetings every Monday to review the team members' progress. The project sponsor is insisting on daily updates to ensure improved delivery on products developed by all of the teams, including this one. Some learn members indicate they are on a very light time line and would attend me Monday meeting, but not the daily update meetings.

What should the project manager do to ensure all team members participate in daily meetings?

Options:

A.  

Analyse the team members' influence levels and schedule a training on the importance of daily standups and the time-bound feature of the meetings.

B.  

Require all team members to attend the daily review meetings as they ate requested by the project sponsor.

C.  

Inform the functional manager and replace (earn members who cannot join the daily progress meetings.

D.  

Review the influence of each team member, call the team members with the highest influence to a meeting, and convince them to join the daily standups.

Discussion 0
Questions 329

A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a

previous project, the project manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

Options:

A.  

Ask the project team to review the lessons learned and have the team contact the stakeholder directly if there are any questions.

B.  

Recognize the stakeholders skills are important for the project and evaluate the possibility of the stakeholder supporting the project team.

C.  

Request the functional manager to assign the team from the lessons learned project to the current project to avoid a learning curve.

D.  

Send a request to the project sponsor to hire the stakeholder and have them become part of the project team.

Discussion 0
Questions 330

An IT company's office is closed abruptly due to a new government restriction. All employees are now working remotely. Project team A has a

critical project delivery due in 2 weeks. The project manager, apprehensive about this sudden change, instantly emails the customer explaining

that the project delivery will be delayed. The customer is unhappy with this and has escalated the issue to senior management.

What should the project manager have done differently?

Options:

A.  

Communicated a new delivery date to the customer along with the news about the delay

B.  

Disclosed to senior management in confidence, then communicated the delay to the customer

C.  

Assessed the situation with the project stakeholders first and communicated the impact to the customer

D.  

Spoken to the customer on the phone and explained the reason for the delay instead of writing an email

Discussion 0
Questions 331

A construction project for a nuclear power plant will reduce the region's energy dependence on external electricity supplies. The project manager has received support for

the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.

Which stakeholders should the project manager include in the stakeholder engagement plan?

Options:

A.  

Stakeholders who have been identified and who have needs and a potential impact on the project.

B.  

Stakeholders who are selected by the project sponsor who have a potential impact on the project.

C.  

Stakeholders who disagree with the project so as to proactively manage their expectations.

D.  

Stakeholders who are supporting the project in order to obtain additional resources.

Discussion 0
Questions 332

A newly commissioned project has had trouble recruiting team members because the turnover rate is high. The human resource (HR) manager

has conducted several exit interviews. Many team members have expressed that the project manager has inadequate relationship management

competencies. The project manager explains that the exiting team members were lazy.

What should the project manager do to prevent this high turnover rate from continuing?

Options:

A.  

Be more involved in the team member recruitment process to ensure qualified team members are chosen.

B.  

Develop relationship skills as a leader and also develop the teams’ emotional intelligence skills.

C.  

Avoid micromanaging the team, enforce stricter rules, and monitor employees.

D.  

Explain to the recruiting manager that a project is temporary in nature, making it different than an operational environment.

Discussion 0
Questions 333

A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The

procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses.

How should the project manager approach this project?

Options:

A.  

Apply a predictive project management approach.

B.  

Evaluate and decide on a phased project management approach.

C.  

Implement an adaptive project management approach.

D.  

Use a hybrid model to combine predictive and adaptive life cycles.

Discussion 0
Questions 334

A project manager is leading a project that will be delivered using a Scrum framework. The organization has an innovative project management office (PMO) that fully supports agile and also has a very friendly procurement team. A new vendor needs to be engaged to provide more developers for a new reporting platform.

What should the project manager do?

Options:

A.  

Use an agile approach and engage a vendor that delivered well in a previous organization.

B.  

Consult the product owner and engage a vendor that is recommended by them.

C.  

Consult the development team and engage a vendor that is recommended by them.

D.  

Use a formal approach using procurement policies, procedures, forms, and work instructions.

Discussion 0
Questions 335

During user acceptance testing (UAT), a manager declined a core application functionality that was originally requested by a subject matter expert (SME). Due to the manager's influence, the project team is concerned about the overall impact to the project.

What should the project manager have done?

Options:

A.  

Obtained a list of the critical stakeholders from the project sponsor

B.  

Consulted with the project sponsor on stakeholder roles and responsibilities

C.  

Identified and consulted stakeholders during requirements gathering

D.  

Requested stakeholders to participate in project initiation and planning phases

Discussion 0
Questions 336

A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.

What should the project manager do next?

Options:

A.  

Speak with the product manager to prioritize the compliance-related activities high enough in the backlog to submit a prototype to the regulatory body.

B.  

Identify the missing requirements, prioritize the missing compliance work directly into the backlog, and assign the work to the team.

C.  

Reschedule the launch of the product until the team can produce a prototype for inspection as required by the compliance team.

D.  

Create an MVP that contains the scope for the prototype and that will be prioritized with the compliance team.

Discussion 0
Questions 337

A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going

well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference

to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.

Which two things should the project manager do to help the teams collaborate better? (Choose two)

Options:

A.  

Schedule weekly progress meetings with all three teams and have them take turns as key players.

B.  

Plan for team members to temporarily work at each other's locations to better provide a sense of community.

C.  

Update the communications management plan and encourage the teams to review it promptly and proactively.

D.  

Create a status reporting template and share it with all team members before the day ends.

E.  

Schedule daily meetings with each team to understand their progress and concerns in detail.

Discussion 0
Questions 338

A project manager was notified about a new regulatory requirement that could impact the project schedule.

What should the project manager do first?

Options:

A.  

Increase the amount of slack in the critical path to reduce the impact of the regulatory requirement.

B.  

Update the schedule and project risk register according to the regulatory requirement.

C.  

Consult the project management plan for guidance on addressing the regulatory requirement.

D.  

Assess the impact of implementing the potential regulatory requirement on the project.

Discussion 0
Questions 339

A company is transitioning from using a predictive approach to using an agile framework on a project. The project sponsor is concerned about the level of uncertainty and how to determine the time and budget required to complete the scope.

What should the project manager do to address this situation?

Options:

A.  

Communicate to the key stakeholders that the project baseline could not be estimated due to the new framework being used.

B.  

Ask the project team to create a high-level budget baseline for the project and provide more detail only for the first project stages.

C.  

Review organizational process assets (OPAs) for similar projects to determine the schedule, costs, and resources required to execute them.

D.  

Refine the amount of work required for the project with the project team and perform a detailed project baseline accordingly.

Discussion 0
Questions 340

As part of planning activities for a new project, the project manager must develop a budget that encompasses the full project scope. What should the project manager do to build the project budget?

Options:

A.  

Reference the work breakdown structure (WBS) and project schedule to estimate costs associated with each WBS element.

B.  

Schedule a working session with the project sponsor to review the project charter and estimate the cost per project phase.

C.  

Review historical project files and lessons learned to identify a similar project and adapt the budget used in the historical project.

D.  

Ask key project stakeholders to estimate the cost of delivering the project, then calculate an average that can be used for the budget.

Discussion 0
Questions 341

During a discovery phase, a project manager coordinated a brainstorming event to determine the best strategy to meet the product release date. After the project overview,

the subject matter expert (SME) remained quiet during the call.

What should the project manager do next?

Options:

A.  

Cancel the meeting if team members do not have the skills to suggest a strategy.

B.  

Pose direct questions to the participants based on their area of expertise to start engaging them in the conversation.

C.  

Review the roles and responsibilities during the call to determine who is accountable for the strategy.

D.  

Create a strategy based on the project manager's experience and get approval during the call.

Discussion 0
Questions 342

A project team has difficulty understanding the relationship between functional requirements and their associated benefit to the business stakeholders.

How should the project manager improve the team's understanding?

Options:

A.  

Involve team members in stakeholder analysis and engagement.

B.  

Invite all stakeholders to progress meetings to avoid ambiguity.

C.  

Ensure team members have access to a well-written requirements traceability matrix.

D.  

Engage with the project sponsor and ensure the product backlog is correct and up to date.

Discussion 0
Questions 343

An agile team is struggling to successfully deliver what they have committed. During the daily status meetings, the project manager notices that the most senior engineer is doing all of the talking, leaving little time for the other members to share their status. The team's performance is not good, and some team members want to leave the team.

How should the project manager approach this situation?

Options:

A.  

Measure the team's psychological safety.

B.  

Reschedule the team's retrospective meeting.

C.  

Coach the team to be more inclusive.

D.  

Rotate the team's daily meeting roles frequently.

Discussion 0
Questions 344

A project manager received several complaints from different project team members related to an unnecessary additional step the functional lead implemented as a preference. The project team members' work has been affected by this and they have missed a few deadlines.

What should the project manager do to address this concern?

Options:

A.  

Recommend the functional lead meet with the project team members to convince them to accept the change.

B.  

Document the additional step from the functional lead and adjust the timelines to accommodate the change.

C.  

Ask the functional lead to remove this additional step as it is not vital to the project.

D.  

Advise the team that the functional lead's preference should be taken into consideration.

Discussion 0
Questions 345

A project manager has taken over a project and realizes a number of the suppliers responsible for the delivery have not done an implementation as complex and large as this project. The project manager reviews the risk log and logs this as a risk. Three months later, two suppliers have missed key milestone dates and delivered substandard work.

What should the project manager do?

Options:

A.  

Support the suppliers by providing them with additional resources.

B.  

Execute the risk response plan and update the issue log.

C.  

Ask suppliers to submit a revised plan and schedule.

D.  

Execute the risk response plan and update the action register.

Discussion 0
Questions 346

A functional team member often becomes disruptive during status meetings and attempts to derail progress with the key stakeholders. This team member often discusses why the project will not be successful.

What should the project manager do?

Options:

A.  

Investigate alternatives for team member needs.

B.  

Evaluate the engagement needs for stakeholders.

C.  

Identify the root cause of the team member's misunderstanding.

D.  

Build trust and influence stakeholders.

Discussion 0
Questions 347

A project manager is facilitating meetings with a diverse team, considering that the team members come from different cultures and have different backgrounds. What should the project manager do to facilitate effective communication?

Options:

A.  

Create incentives to promote better communication among team members.

B.  

Assign the work packages based on geographical working groups.

C.  

Understand and consider the emotions of each team member.

D.  

Plan for communication training workshops for all team members.

Discussion 0
Questions 348

During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.

What should the project manager ask the team to do next?

Options:

A.  

Execute the smaller estimated activities.

B.  

Resize the story points.

C.  

Negotiate the estimation so it gets smaller.

D.  

Break down the larger activities into smaller ones.

Discussion 0
Questions 349

An investment company is interested in unifying direction and control criteria in one of its principal projects. The project manager was advised to enforce the main framework of this initiative.

What should the project manager do first?

Options:

A.  

Document the direction and control framework into the project charter.

B.  

Develop an engagement plan to achieve consensus.

C.  

Identify and interview all of the relevant stakeholders.

D.  

Get direction and control framework requirements from stakeholders.

Discussion 0
Questions 350

A project manager is reviewing the team's Kanban board for an iteration with 16 tasks in progress. All the tasks are equally sized with an estimate of 8 man-hours of effort needed to complete each task. The team is made up of five cross-functional members. The normal working calendar is 8 hours per day; however, two of the team members will only work at 50% capacity. The project manager has a maximum of one week to deliver these tasks in progress due to government regulations.

Will the project manager meet this objective?

Options:

A.  

Yes, it will take 4 working days to complete these tasks based on the estimate.

B.  

No, it will take 6 days to complete all these tasks based on the estimate.

C.  

No, it will take 7 days to complete all these tasks based on the estimate.

D.  

Yes, it will take 5 working days to complete these tasks based on the estimate.

Discussion 0
Questions 351

A project manager is assigned to a research project. The project team has been selected and has worked together on other projects. Based on the project documentation, team members seem to be working at their own pace and have had little interaction with the project manager.

What should the project manager do to have a high-performing team?

Options:

A.  

Set up regular project status meetings and invite all team members.

B.  

Encourage the team to define the ground rules for performance.

C.  

Set up individual calls to follow up on each team member's progress.

D.  

Invite team members to an informal meeting to get to know one another.

Discussion 0
Questions 352

A project manager is in the middle of executing the construction of a high-rise plaza when the government regulatory agency announces an increase in the price of fuel. The project still has seven months left on the schedule.

What should the project manager do first?

Options:

A.  

Meet with the vendors to evaluate the impact on the budget.

B.  

Implement crashing to mitigate the impact on the budget.

C.  

Review the organizational process assets (OPAs) as a reference.

D.  

Request the release of management reserve for the project.

Discussion 0
Questions 353

During a project planning meeting, a product manager and team are finalizing the project deliverables and notice that a key feature has a dependency from another team. A team member suggests removing the feature from the scope.

What should the project manager do?

Options:

A.  

Advise the team not to reduce the scope of the feature because the product manager originally included that requirement.

B.  

Discuss the issue with the team so the product manager can understand the trade-offs.

C.  

Suggest the team and product manager go with the faster approach, reducing the scope.

D.  

Prepare a presentation for the project sponsor with the team that includes both solutions and seek the sponsor's guidance.

Discussion 0
Questions 354

To limit the amount of time and cost of using a contract programming firm, a product manager announces that the developers will not be paid for unrequested embellishments to the product. What should the development team and scrum master do to ensure they are paid for all their work?

Options:

A.  

Have the product manager work with the scrum master to assign specialists to user stories to meet the requirement.

B.  

Convert the story points on user stories to hours to provide estimates of the potential costs to the product manager.

C.  

Ensure that the task board is used as an information radiator and all stories have enough detail to build the required feature or function.

D.  

Refine the definition of done (DoD) for user stories to ensure that part of the completion is a verification review of the code.

Discussion 0
Questions 355

A project team has obtained additional team members from different time zones. As a result, there are full-day delays in the work being completed because there are questions from team members from opposite time zones.

What should the project lead do?

Options:

A.  

Meet each team member during their work hours to ensure all questions are answered in a timely manner.

B.  

Inform all team members that they are required to check for messages every few hours to ensure fast response times.

C.  

During daily check-ins, compile questions, coordinate with all team members, and agree to meet.

D.  

Escalate to the project sponsor and request to replace certain team members so the time zones are aligned.

Discussion 0
Questions 356

An agile project is completing its second sprint and products are being finished. However, two groups with different levels of expertise disagree on the backlog priority.

What should the project manager do first to resolve this dispute?

Options:

A.  

Escalate to the project sponsor to provide a solution to the conflict.

B.  

Interpret the source and stage of the conflict and select a resolution approach.

C.  

Apply a compromising resolution approach, involving both groups.

D.  

Ask the functional managers of both groups to help find a workable solution.

Discussion 0
Questions 357

A project team has not been meeting its deliverables because they are not receiving adequate resources to do their job. What should the project manager do for the team to meet the upcoming deliverables?

Options:

A.  

Ask the team to adapt based on their current resources.

B.  

Plan a meeting with the stakeholders to get more resources.

C.  

Replan the upcoming deliverables based on the available tools.

D.  

Ask the project sponsor to provide the needed resources.

Discussion 0
Questions 358

A project manager has been assigned a project team with members in two different locations. The project manager noticed that the productivity of a senior team member in the other location is much lower than the local junior team members.

What should the project manager do to address the issue?

Options:

A.  

Share a work performance report with the team member's supervisor.

B.  

Assign a mentor to work with the senior team member.

C.  

Speak with the senior team member to identify the difficulties.

D.  

Collect feedback from all team members about team performance.

Discussion 0
Questions 359

The project team is conducting iteration planning and having difficulty evaluating a new technology that will be used in this iteration. What should the project lead do?

Options:

A.  

Hire an external subject matter expert (SME) to help with design and implementation.

B.  

Coach the team to determine a path forward to achieve an efficient solution.

C.  

Provide technical guidance on complexity assessment.

D.  

Guide the team with estimating the time required.

Discussion 0
Questions 360

Customers are concerned about the quality of an interim software system for a project. The quality control team has approved the software, but the customers are complaining that some functions do not comply with the requirements.

What should the project manager do to prevent this from happening again?

Options:

A.  

Review the risk impact of quality nonconformance.

B.  

Review the communications management plan.

C.  

Revise the quality management plan.

D.  

Revise the product acceptance specifications.

Discussion 0
Questions 361

A project lead with a strong technical background oversees a project using agile delivery. The product owner asked the project lead to assist with ensuring the benefits of functionality that are built in the sprint are tracked.

What should the project lead advise?

Options:

A.  

During the sprint review, ensure that the completed items deliver business benefits.

B.  

Present in detail the business benefits delivered in the sprint during the sprint retrospective.

C.  

During the daily standup, ensure that each item meets the definition of done (DoD) before accepting it.

D.  

Review in detail the criteria for the definition of done (DoD) for each item during the sprint planning.

Discussion 0
Questions 362

During a business review meeting, a key stakeholder raised a concern on the quality of deliverables and has now escalated the concern.

What should the project manager do first?

Options:

A.  

Schedule a meeting with all team members to clarify and plan next steps.

B.  

Discuss with the stakeholder and share a report on the deliverables.

C.  

Discuss with the team and check all reports on the deliverables.

D.  

Schedule a meeting with the stakeholder to clarify and plan next steps.

Discussion 0
Questions 363

A project manager is leading a project with a team that is comprised of both experienced and inexperienced team members. What should the project manager do to ensure an effective project team?

Options:

A.  

Ask the least experienced team members to work as assistants to the more experienced team members so they can gain some project experience.

B.  

Ask the project sponsor to replace the least experienced team members with more experienced ones.

C.  

Identify how the team members with no experience can contribute according to their capabilities and provide training if needed.

D.  

Assign critical project tasks to the most experienced team members as they are the only ones with the knowledge.

Discussion 0
Questions 364

Due to an anticipated expansion, a company procured new technology. The project team responsible for using this technology does not have experience with it.

What should the project manager do?

Options:

A.  

Assess the benefit of using new technology versus old technology.

B.  

Hire project resources with experience using the new technology.

C.  

Propose training for the project team in batches on the new technology.

D.  

Request incentives for the team to use the new technology.

Discussion 0
Questions 365

A project manager has just been assigned a major, ongoing project. The project team is not working in harmony and their performance is decreasing. Some team members are autocratic in their approach whereas others are in avoidance mode.

How should the project manager proceed?

Options:

A.  

Emphasize their autonomy as project manager, implying that they will not allow team disunity.

B.  

Appeal for cooperation from all of the team members, emphasizing the benefit of the project outcome to the company.

C.  

Assess the various team behaviors through the use of personality indicators to appropriately deal with each personality type.

D.  

Request for removal of the autocratic members who obviously are not interested in the project.

Discussion 0
Questions 366

A product owner is complaining about the team's performance. The developers are highly skilled, and most of the issues were caused by dependencies. The developers provide a formal status report every day, but it is clear that the other team members are not satisfied with this.

What should the project lead do?

Options:

A.  

Ask the developers to use peer programming.

B.  

Build a task board on a large wall using sticky notes.

C.  

Build a detailed schedule and describe each task in detail.

D.  

Ask the product owner to reprioritize the backlog.

Discussion 0
Questions 367

A project team is struggling to meet the project deadline due to a reoccurring conflict between two team members. What should the project manager do?

Options:

A.  

Hold the team collectively responsible for their actions.

B.  

Explore the possibility of reshuffling the team.

C.  

Introduce training sessions to improve the team's performance.

D.  

Schedule team-building activities as required.

Discussion 0
Questions 368

A project sponsor is replaced during a hybrid project closure. The new project sponsor wants to change all of the project documentation to reflect a fully predictive approach.

What should the project manager do next?

Options:

A.  

Review the key existing project documents with the new project sponsor.

B.  

Ask the team to estimate the time it will take to update the documentation.

C.  

Address the issue during the lessons learned session of the closing phase.

D.  

Set up a meeting with the new project sponsor to understand their concerns.

Discussion 0
Questions 369

A project is in the execution phase and there are disagreements between two key stakeholders about the project's scope. One stakeholder is adamant about expanding the scope and the other stakeholder is content with the current arrangement.

What should the project manager do?

Options:

A.  

Escalate the stakeholder's conflict to senior management so they can resolve the issue.

B.  

Schedule a one-on-one discussion with each stakeholder to understand their concerns.

C.  

Schedule a meeting with both stakeholders to encourage dialogue and reach a decision.

D.  

Suggest that the two stakeholders meet together to agree upon a project scope.

Discussion 0
Questions 370

A project manager is leading a team and wants each team member to produce their deliverables and be held accountable for the work product. What should the project manager do first?

Options:

A.  

Engage with each project team member to explain the individual consequences of late delivery.

B.  

Establish a daily standup meeting where each project team member reports their progress.

C.  

Create a plan of action and milestones (POAM) to detail the deliverables for each project team member.

D.  

Empower each project team member with ownership of a particular aspect of the project.

Discussion 0
Questions 371

A project team is defining the ground rules during their first meeting as a team. During this session, only a few of the team members suggested and approved the ground rules while most remained silent. As a result, the team's ground rules favor those few team members.

What should the project manager do?

Options:

A.  

Conduct a round table and ask the team to share their opinions one by one.

B.  

Propose new team ground rules and communicate them to all.

C.  

Ask the silent team members to share their opinions via email.

D.  

Perform focus group interviews based on the new team ground rules.

Discussion 0
Questions 372

A team is performing above expectations, and the sponsor wants to expand the project scope to benefit the organization. However, there are only a few team members with the needed leadership experience.

What should the project manager do?

Options:

A.  

Communicate the risks and propose hiring members with leadership experience before continuing with the request.

B.  

Decline the scope expansion until the team members get appropriate leadership opportunities within the project.

C.  

Implement the scope expansion and suggest the team members get a mentor due to their lack of leadership experience.

D.  

Recognize each team member for their contributions and recommend them to the leadership development program.

Discussion 0
Questions 373

An organization is undergoing an agile transformation and migrating most of its projects from a predictive approach. The CFO expressed a concern that predictability on both costs and scope will be lost with the new agile approach.

What should the project manager do?

Options:

A.  

Provide mentoring to the CFO, who is a key stakeholder in the project, and clarify the benefits of an agile approach.

B.  

Ask the CEO to intervene by asking for support from the executive board to accelerate the company's transformation.

C.  

Apply influence with other key stakeholders on the board to mitigate any risks that may be generated by the CFO's position on the matter.

D.  

Submit a report to all key stakeholders on the cost-benefit analysis of the new approach and detail how the company will save money.

Discussion 0
Questions 374

A team member on an important company project mistakenly caused significant cost overruns. The sponsor informed the project manager and expects the project manager to take action within 1 week. This team member has always been an outstanding performer.

What should the project manager do first to address the sponsor's concerns?

Options:

A.  

Document the team member's mistake in the lessons learned.

B.  

Train the team member to improve their performance to avoid future mistakes.

C.  

Talk with the team member to identify the reason for the mistake.

D.  

Relocate the team member to another project due to the mistake.

Discussion 0
Questions 375

A project team is working on a critical release and the customer wants this feature to be made available as early as possible. The business owner suggests an enhancement during the product demo.

How should the project manager address this request?

Options:

A.  

Determine the additional funding needed and seek the sponsor's guidance.

B.  

Support value-based delivery that is aligned with the project objectives.

C.  

Follow the project change control process to formalize the change.

D.  

Estimate the additional funding needed and seek the client's approval.

Discussion 0
Questions 376

A company is experiencing a high rate of rejected project deliverables. The project manager is requested to suggest a solution to improve quality.

What should the project manager suggest?

Options:

A.  

Request that all team members receive the newest quality standards training and review one another's work.

B.  

Request that a quality specialist be assigned to the project to check the final product at the end of the project.

C.  

Break down the project into several iterations and incorporate a quality check by a quality auditor in each iteration.

D.  

Break down the project into several iterations and incorporate automatic testing and quality improvement sessions.

Discussion 0
Questions 377

During a risk review meeting early in a project, the project team flags the possibility that a key team member might be away during the implementation of a key work package. Unfortunately, this team member is currently the only resource with the knowledge to perform this work, although it is possible someone else could do it with training.

What should the project manager do?

Options:

A.  

Establish a long-term training program for the junior team members.

B.  

Reassign the tasks among team members to allow them to split the workload.

C.  

Ask team members to document knowledge assets for all the tasks.

D.  

Ensure team members collaborate throughout the project to share knowledge.

Discussion 0
Questions 378

A government approved the construction of a river dam to enable year-round farming in a community. At the project kickoff meeting, a key stakeholder in the community disagrees with the location of the dam.

What should the project manager do first?

Options:

A.  

Review the stakeholder engagement plan to confirm that all key stakeholders were consulted.

B.  

Explain to the key stakeholder that final approval has already been obtained.

C.  

Meet with the key stakeholder to review the stakeholder engagement plan.

D.  

Schedule a meeting with all stakeholders to discuss the view of this key stakeholder.

Discussion 0
Questions 379

A newly assigned team member immediately begins questioning operating procedures. This new team member wants the team to follow operating procedures that the team member had used previously. During assignments, the new team member begins using some of those processes and procedures and suggests these practices to other team members.

What action should the project manager take?

Options:

A.  

Organize a training for the new team member on the processes the team is currently using.

B.  

Speak with the new team member at the retrospective and discuss potential improvements.

C.  

Formalize the new processes and implement the team member's proposed changes.

D.  

Hold a team meeting on governance, operating policies, procedures, and practices.

Discussion 0
Questions 380

During a contract renewal meeting, an organization's commercial team and the customer are disagreeing and negotiations are failing. What should the project manager do to reach an agreement that will satisfy all parties?

Options:

A.  

Reinforce the initial rules of the negotiations.

B.  

Engage a facilitator to support the negotiations.

C.  

Concentrate on meeting the customer's requests.

D.  

Set clear expectations among the participants.

Discussion 0
Questions 381

A project manager is managing a project with a cost performance index (CPI) of 1.05 that is trending downward. To maintain on-time completion, the scrum master needs to add 30 additional team members in the next month to enable more sprints. The project manager is concerned because the schedule performance index (SPI) is 1.0.

What is the first step the project manager should take?

Options:

A.  

Meet with the project team to forecast the SPI trend to determine if there are funds available to pay the 30 team members.

B.  

Quantify the cost for the 30 team members and determine if there is budget available to fund the expanded team.

C.  

Inform the project team that since the CPI is trending downward, there are funds available to expand the team.

D.  

Engage with the human resources (HR) representative to begin selecting candidates for the 30 open positions.

Discussion 0
Questions 382

A project manager's project relies on services from a department that has a new leader. Since the new leader was appointed, the services from their department have been slow which threatens the project's delivery deadline.

What should the project manager do?

Options:

A.  

Add the issue to the issue log and communicate the issue in the next regular report to project stakeholders.

B.  

Escalate the issue to the project sponsor notifying them of the slow services from the department.

C.  

Send all service requests to the department earlier in the project to lessen the impact on the delivery date.

D.  

Arrange a meeting with the leader to explain the project's needs and understand the leader's perspective.

Discussion 0
Questions 383

A project manager is creating the quality management plan for deliverables with very precise requirements. The project manager is uncertain about how to create quality standards so the suppliers can show conformity when delivering the product.

Which two actions should the project manager take first? (Choose 2)

Options:

A.  

Review the conformity management plan to ensure the requirements are clearly defined.

B.  

Reference the quality management plans from old projects to determine if they apply to these deliverables.

C.  

Add a conformity team member to inspect each deliverable upon receipt from the supplier.

D.  

Evaluate industry standards of similar products to determine which apply to this project.

E.  

Ask the suppliers to create a statement of conformity when the product is delivered.

Discussion 0
Questions 384

A project manager found a repeated defect in a junior developer's code. The code is due in 2 days and a severe fine will be incurred if it is not fixed by then. The project manager wants to reassign the assignment to a more senior developer, but the junior developer is strongly opposed to the reassignment.

What should the project manager do?

Options:

A.  

Assign the issue to a senior developer and schedule training for the junior developer after the due date.

B.  

Assign the rework to the junior developer after consultation with the senior developer.

C.  

Reassign the issue to the senior developer and assign the junior developer to assist in fixing the issue.

D.  

Reassign the issue to the senior developer after explaining the situation to the junior developer.

Discussion 0
Questions 385

A project team member who has the expert knowledge necessary for the project is often absent from meetings. The team member sends a message to the project manager questioning them about the rationale behind some decisions made on the project.

How should the project manager handle the situation?

Options:

A.  

Inform the team member that decisions were already made and feedback should have been provided in the past.

B.  

Schedule a meeting to review the team member's concerns and revisit the decisions if required.

C.  

Explain to the team member that it is mandatory that they increase their participation in project meetings.

D.  

Add the team member's concerns to the risk register and discuss them during the next regular meeting.

Discussion 0
Questions 386

An organization is implementing a solar power system at its production plant. During the execution phase, one of the key stakeholders noticed and communicated that authorities are developing solar power regulation, which might impact the overall feasibility of the project.

What should the project manager do first?

Options:

A.  

Collect and analyze information about the new regulation.

B.  

Put the project on hold and wait for the regulation information to be confirmed.

C.  

Proceed with the project as long as the regulation is not yet finalized.

D.  

Meet with the sponsor to discuss the regulation issue and determine the proper action.

Discussion 0
Questions 387

A project manager is working on a software development project. Software development will be carried out through a partnership with a vendor based on a list of initial requirements not yet completely defined.

What type of contract and project approach should the project manager consider?

Options:

A.  

Time and materials (T&M) with an agile approach

B.  

Cost reimbursable contract with a predictive approach

C.  

Fixed-price contract with a predictive approach

D.  

Memorandum of understanding (MOU) with an agile approach

Discussion 0
Questions 388

A project manager has developed a communications management plan. A junior team member asks why they are duplicating efforts by producing different versions of the same newsletter.

How should the project manager respond?

Options:

A.  

Explain that each stakeholder expects a different customized newsletter, ensuring it complies to all of their requirements.

B.  

Explain that to prepare for all situations and as part of risk mitigation, many different newsletters are created just in case they are needed.

C.  

Explain that customized newsletters are part of the organizational culture and that following this step-by-step process is of utmost importance.

D.  

Explain that each individual newsletter is based on specific categories of communication for the intended audience.

Discussion 0
Questions 389

A project manager has an engineering team mostly comprised of new hires. The project manager has to carefully predict in which stage of the project they will need to spend most of their time to ensure the team is properly integrated and performing well.

In which stage of the project would the project manager need a greater effort to lead them?

Options:

A.  

Performing

B.  

Storming

C.  

Norming

D.  

Forming

Discussion 0
Questions 390

A project manager is planning a project to build a research center with the installation of scientific equipment. Since the research topic is new and unfamiliar, the equipment required might change during project execution.

How should the project manager plan this project?

Options:

A.  

Use a different project life cycle approach for the different parts of this project by adopting a hybrid approach.

B.  

Separate the tender into two parts, one for the building and one for the equipment, with careful selection of contractors.

C.  

Lock down the requirements for the equipment early and avoid any changes during further phases of the project.

D.  

Put a fixed price contract out to tender for the research building and issue a cost-reimbursable contract for installing the equipment.

Discussion 0
Questions 391

During a sprint planning, the development lead highlights the importance of working on technical debt tasks that are critical for the product performance. However, the tasks will consume most of the team's capacity and they will not be able to work on product feature development.

What should the project manager do?

Options:

A.  

Invite technical stakeholders for backlog prioritization.

B.  

Work on the features already prioritized by the product owner.

C.  

Ask the sponsor for more resources to continue at the same pace.

D.  

Add the technical debt tasks to the sprint backlog.

Discussion 0
Questions 392

During project execution, a key stakeholder approaches the project manager and questions the business value of the project. What should the project manager do?

Options:

A.  

Explain to the stakeholder that it is up to the project sponsor and the client to determine if the project still has the perceived business value.

B.  

Inform the stakeholder that the project will still proceed to completion because the project charter has already been approved.

C.  

Consult the remainder of the stakeholders and the sponsor to determine if they have the same concern.

D.  

Validate the business value with the stakeholder by ensuring each requirement is still aligned to the business and project objectives.

Discussion 0
Questions 393

A team member has escalated an issue to the project manager, stating that they have done their part of the job. Their concern is that there is still no response from the other party in the service level agreement (SLA). The team member is eager to find a resolution for the reported issue.

What should the project manager advise the team member to do to ensure that the project escalation mechanism is effective?

Options:

A.  

Involve all of the stakeholders in the escalation by setting up a conference call.

B.  

Escalate to the other party's management and inform the steering committee.

C.  

Reach out to peer managers for similar escalation situations and follow past experiences.

D.  

Review the established project escalation process and take the appropriate action.

Discussion 0
Questions 394

A project manager with agile experience is part of an organization that is transitioning to agile. The project manager was assigned to the first agile project by the project management office (PMO). The PMO manager asked the project manager if an existing governance from a previous project would be suitable to use in the current agile project.

How should the project manager respond?

Options:

A.  

This framework is not appropriate for agile.

B.  

This is a learning experience for the agile team.

C.  

An agile approach is easily adaptable.

D.  

An agile approach is different.

Discussion 0
Questions 395

A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?

Options:

A.  

Add more items to the sprint backlog that will add value.

B.  

Complete the sprint and seek a waiver from the regulator.

C.  

Complete the sprint, but do not release the deliverable.

D.  

Perform a sprint risk assessment and analyze challenges.

Discussion 0
Questions 396

A project manager is facilitating an iteration retrospective. The iteration did not go well and the committed functionality was not delivered to users. The project involves a vendor team for the build and an internal quality assurance (QA) team. In the past, there were tensions between the vendor and the internal team.

What should the project manager do?

Options:

A.  

Hold separate retrospective meetings for both the vendor team and the internal team.

B.  

Schedule a preliminary meeting with the account manager from the vendor and the test manager.

C.  

Establish a clear agenda for the meeting and remind the vendor and internal teams that the scope is to improve the process.

D.  

Invite the procurement manager and a representative from the vendor to manage the current tense relationship.

Discussion 0
Questions 397

A project manager just took over a construction project which was already in its execution phase. Labor union representatives of the construction workers ask to revise the overtime per hour rate, as wage per hour have increased across the industry.

What should the project manager do first?

Options:

A.  

Obtain approval from sponsors to increase the rates because it can affect project due to lack of resources.

B.  

Carefully read the agreements and see if there was any clause if the per hour rate could be increased.

C.  

Assign a team member to negotiate the increased wage per hour with the labor union representatives.

D.  

Negotiate with the labor union representatives if the clause about increased wage per hour meets their requirements.

Discussion 0
Questions 398

A team member mentions to the scrum master that the user stories are too long. The team member believes this may be the cause of the team's inability to deliver value for stakeholders.

What should the scrum master do?

Options:

A.  

Review the user stories with the team and ask the product owner to break them down into more manageable units.

B.  

Review the user stories with the stakeholders and ask the product owner to break them down into more manageable units.

C.  

Ask the team member to suggest using shorter user stories to the product owner so that the next sprint can move faster.

D.  

Ask all the team members for their views about using shorter user stories so that value can be created for stakeholders.

Discussion 0
Questions 399

Presented with flowcharts of the organization's operations, stakeholders are unfamiliar with several recorded processes, and others note that some recorded processes were discontinued. The project sponsor notices that the chart is several years old and wants an updated version immediately.

What should the project manager do?

Options:

A.  

Assemble the entire project team to produce new flowcharts from current versions.

B.  

Assemble and create teams of experts and stakeholders to update flowcharts to reflect current conditions.

C.  

Raise a change request and ask the project sponsor to approve it so the flowcharts can be updated.

D.  

Work with a consultant and the project sponsor to produce new flowcharts.

Discussion 0
Questions 400

During a sprint retrospective, the project manager notices that one of the team members does not achieve the sprint objectives on a regular basis. This team member is an experienced resource.

How should the project manager properly address this situation?

Options:

A.  

Align the project goals with the team member.

B.  

Reassign the team member to another project.

C.  

Nominate the team member to receive agile training.

D.  

Allocate another resource to support the team member.

Discussion 0
Questions 401

A project's planning process is finished, and all resources were budgeted for and approved by senior management. Just before the kickoff meeting, a member of the production department realizes that the plan does not meet the requirements for their area.

What should the project manager have done during the planning process?

Options:

A.  

Monitored the budget variations during the planning process

B.  

Developed a good resource estimation in the planning process

C.  

Included all functional managers in the planning process

D.  

Distributed the resource estimates to all areas during the planning process

Discussion 0
Questions 402

In an organizational upper-level management meeting, the CEO shows interest in a project of which they were not previously aware. After the meeting, what should the project manager do to ensure the CEO's support?

Options:

A.  

Update the stakeholder engagement plan to include the CEO.

B.  

Meet with the CEO to review the current deliverables for the project.

C.  

Identify the CEO's preferred method of communication.

D.  

Send the updated project management plan and documents to the CEO.

Discussion 0
Questions 403

The team's work assignments have been generically distributed. A new team member is performing slower than expected.

What should the project manager do?

Options:

A.  

Extend the project timeline to allow the new team member to work at their own pace.

B.  

Have all of the other team members retrain the new team member to improve team performance.

C.  

Change the way the work assignments are distributed to facilitate new team member development.

D.  

Assess the new team member's skills in order to determine additional training needs.

Discussion 0
Questions 404

A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.

What should the project manager do first to get the team energized and performing efficiently?

Options:

A.  

Seek to understand the sentiments of each team member and then work with them to address their concerns.

B.  

Bring the team together on a phone call to explain the criticality of the project and the impact of schedule delays.

C.  

Contact the functional manager to request a replacement for team members who are not able to meet the schedule.

D.  

Begin holding daily meetings and ask each team member to share their status and demand that they remain on schedule.

Discussion 0
Questions 405

A project manager works for an IT consulting firm that has submitted a bid during the request for proposal (RFP) process for a contract that focuses on data center migration and optimization. However, the consulting firm has little experience in data center optimization.

What should the project manager do?

Options:

A.  

Send the team to a data center optimization training workshop.

B.  

Partner with a company that is an expert in this area.

C.  

Outsource the data center optimization work to a vendor.

D.  

Request a budget to build this competency among project team members.

Discussion 0
Questions 406

A virtual project team has members located on four continents. The project director is concerned about the declining motivational levels of team members and feelings of noninclusion by other team members. The project director has tasked the project manager with finding a solution.

What should the project manager do?

Options:

A.  

Develop a plan for individual team members' growth and organize more team-building events.

B.  

Recommend that the project director appoint project managers for each continent.

C.  

Set up ground rules for team engagement, taking into consideration different cultures.

D.  

Take differences in time zones into consideration when scheduling team meetings.

Discussion 0
Questions 407

A project manager is leading a highly visible project with a critical time constraint. Frequent scope changes have been well-managed with change control, but there have been misunderstandings among project team members.

What should the project manager do?

Options:

A.  

Communicate to the team the need to organize common ground rules.

B.  

Organize training sessions and bonding activities for all team members.

C.  

Communicate changes regularly to ensure all team members are aligned.

D.  

Introduce new products and team support tools during project preparation.

Discussion 0
Questions 408

A Scrum team has information radiators but must also keep stakeholders aware of their progress. In addition, the project management office (PMO) has specific templates for status reporting to management. The project lead realizes that a variety of reporting will be needed to satisfy enterprise and stakeholder needs.

What should the project lead do?

Options:

A.  

Determine the minimum communications needed for the project, and adapt the communication plans as needed.

B.  

Document only the plan for written communications, and send meeting invites for verbal communication sessions.

C.  

Follow the project management office (PMO) guidelines for communications instead of generating a project communications management plan.

D.  

Create a communications management plan informing all project team members and stakeholders who will receive what type of communication.

Discussion 0
Questions 409

Two project team members are having difficulty communicating updates and issues. One team member prefers telephone calls for any kind of urgency, whereas the other team member prefers email communication. This difference results in a lack of understanding between the team members and sometimes hinders timely communication.

What should the project manager do?

Options:

A.  

Ask the team members to resolve this issue themselves.

B.  

Provide these team members with feedback that this issue is causing a delay.

C.  

Ask the team members to follow the ground rules in the project management plan.

D.  

Provide guidance to the team members to resolve the conflicts.

Discussion 0
Questions 410

A project manager is preparing a large and complex international project. In order for the team to work well together in a virtual environment, the project manager needs to set up ground rules for good communication.

What should the project manager do first?

Options:

A.  

Establish a communication channel.

B.  

Create a communication protocol.

C.  

Develop the stakeholder analysis.

D.  

Distribute the risk register.

Discussion 0
Questions 411

A transformation project that is composed of agile streams has come to an end.

How should the project manager collect the experience gained during this project?

Options:

A.  

Organize a lessons learned session with the team.

B.  

Create a document with the information from the last sprint retrospective.

C.  

Ask for feedback during the next standup meeting.

D.  

Conduct a session with the members of the project steering committee.

Discussion 0
Questions 412

A project manager who has been working on an ongoing volatile project is retiring. A new project manager is collaborating with the retiring project manager to ensure a smooth transition.

What should the new project manager first discuss, review, and clarify during the transition meetings?

Options:

A.  

Resource management plan

B.  

Change management plan

C.  

Lessons learned log

D.  

Risk register

Discussion 0
Questions 413

A project is in the start-up phase of the project life cycle. The project team consists of 20 people from five different countries. The project team is scheduled to have quarterly face-to-face meetings. However, due to unforeseen circumstances, no face-to-face meetings can occur. The project manager is concerned that the team may not be able to fulfill their individual roles without face-to-face meetings.

What should the project manager do in this situation?

Options:

A.  

Review the risk register for this unforeseen circumstance.

B.  

Utilize virtual teams for meetings and deliverables.

C.  

Use the contingency reserve and subcontract the work.

D.  

Ask for an extension of time on the project deliverables.

Discussion 0
Questions 414

During a daily meeting of a challenging project, two team members started to argue on the preferred solution based on their assumptions. The situation prevented the progress to the next phase of development, which could impact the finish date of the project.

What should the project manager do next?

Options:

A.  

Divide the team into small groups to avoid future arguments and delays.

B.  

Ask the human resources (HR) department to replace the team members.

C.  

Make a decision based upon the project manager's knowledge and expertise.

D.  

Meet with the team members to discuss the priority of the project schedule.

Discussion 0
Questions 415

An experienced project manager is in a meeting with project key stakeholders when they are informed that a senior manager with extensive experience on similar projects will join the project steering committee. The project kick-off meeting is scheduled for the following week.

What should the project manager do next?

Options:

A.  

Have the kick-off meeting as scheduled and capture any new requirements raised in the meeting.

B.  

Have a one-on-one interview with the new senior manager before the kick-off meeting.

C.  

Ask the new senior manager to send any new requirements before the kick-off meeting.

D.  

Ask the project sponsor to hold the kick-off meeting after the new senior manager has onboarded.

Discussion 0
Questions 416

During the initial phase of a construction project, the team is confused about the safety requirements it needs to consider during implementation. The project manager recently met with the client to define the project scope. How should the project manager share this information?

Options:

A.  

Distribute the safety requirements during the project execution phase

B.  

Modify the project charter by including the safety requirements

C.  

Send an email to the team with the details of the safety requirements

D.  

Meet with the team and present the scope of the safety requirements

Discussion 0
Questions 417

It is taking several additional iterations for a project team to complete planned backlog items. The project manager notices that some features are not meeting the iteration-level definition and must be placed back into the backlog. What should the project manager do?

Options:

A.  

Address the required changes in the next release

B.  

Review and update the acceptance criteria

C.  

Put more emphasis on the definition of done (DoD)

D.  

Extend the iterations to complete the items

Discussion 0
Questions 418

An organization is about to start a time-critical project and has decided to use an agile approach for the first time. However, stakeholders are worried they will not be able to verify project status because they believe their usual governance model will not work for an agile project. What should the project manager do?

Options:

A.  

Discuss using a hybrid governance structure with stakeholders

B.  

Meet with stakeholders to discuss and review the governance structure

C.  

Recommend following the existing governance structure with the project team

D.  

Review the governance structure to reflect scope changes

Discussion 0
Questions 419

A project manager has recently been appointed to lead a critical software development project in a hybrid environment. What should the project manager do first to understand the project quickly and manage the project effectively?

Options:

A.  

Identify key stakeholders and hold a project kickoff meeting to engage the stakeholders and obtain commitment.

B.  

Assess the project management plan for dependencies and possible risks then validate stakeholder understanding.

C.  

Review the project charter to understand the objectives, high-level scope, and business need.

D.  

Share project objectives and scope with the team to ensure it understands the project value.

Discussion 0
Questions 420

A project to develop an enterprise resource planning (ERP) system for a university is ongoing. The system should improve business processes through digitalization and elimination of human errors, and also provide end users with simplified and easily accessible services. What should the project manager do to ensure achievement of the intended business value?

Options:

A.  

Evaluate each change request and review the business case each time

B.  

Evaluate deliverables against the business case continuously

C.  

Evaluate deliverables against the business case at the end of the life cycle

D.  

Evaluate customer feedback and review the business case each time

Discussion 0
Questions 421

A project to develop a new service is initiated by a telecommunications operator. The project management plan was developed, approved, and shared with respective stakeholders. What should the project manager do next?

Options:

A.  

Define deliverables, activities, and scheduling information.

B.  

Estimate activity durations and list resource requirements.

C.  

Incorporate the project's scope baseline in the scope statement.

D.  

Start execution of the work packages according to the plan.

Discussion 0
Questions 422

Shipping problems are impacting the supply chain worldwide, and the project's primary vendor has indicated potential delays in supplying certain equipment that will be ordered later in the project. What should the project manager do with this information?

Options:

A.  

Note the information but refrain from recording it as an issue because the project has not yet placed the order.

B.  

Request the procurement team to find another vendor that has available stock of this equipment.

C.  

Update the risk and continue to monitor developments by keeping in touch with the vendor.

D.  

Request the vendor to provide specific information about the delivery delays before taking any action.

Discussion 0
Questions 423

One of the main deliverables of a project is delayed due to a problem with a key provider. What should the project manager do?

Options:

A.  

Create a change request to replace the provider with a more responsible one from the provider list

B.  

Schedule a meeting with all relevant stakeholders to determine the best approach to resolve the issue

C.  

Discuss with the sponsor and seek guidance to impose the penalty stipulated in the agreement

D.  

Schedule a meeting with the provider to review impacts to the project timeline and deliverables

Discussion 0
Questions 424

After finishing the planning session for a new project, the team agrees that the project duration needs to be 12 months. However, the project sponsor asks to release the product before the end of the project. What should the project manager do first?

Options:

A.  

Update the risk register and escalate it to the sponsor

B.  

Assist the team in proposing a minimum viable product (MVP)

C.  

Request the stakeholders to reduce the project backlog to finish on time

D.  

Ask to increase the capacity of the team to deliver the project on time

Discussion 0
Questions 425

Three months after creating a project schedule, the scope of a project significantly changed, resulting in a schedule rebaselining. One month after rebaselining, the project is two weeks behind schedule with a cost performance index (CPI) of 0.93. What should the project manager do to help get the project back on schedule?

Options:

A.  

Crash the project with two additional contract resources for the newly identified tasks.

B.  

Meet with the project stakeholders and inform them that the project is going to be delayed.

C.  

Manage the schedule’s critical path, as this was an approved scheduling change.

D.  

Review the project schedule and find ways to fast-track the overall project schedule.

Discussion 0
Questions 426

Near the closing stage, a project is delayed due to staff shortages. In order to meet the mandatory deadline, additional resources are necessary, but there is no additional budget. What should the project manager do first to obtain the funding to hire the needed resources?

Options:

A.  

Ask the sponsor for additional financial resources

B.  

Introduce a change request

C.  

Use management reserves

D.  

Update baselines to accommodate the delay

Discussion 0
Questions 427

A new project manager has been assigned to a recently approved project. The project has a multimillion-dollar budget and will require the purchase of expensive equipment. The project manager is aware that some purchase amounts require higher levels of approval. What should the project manager do to properly manage the purchase of equipment?

Options:

A.  

Agree on a purchasing approval escalation method according to organizational governance

B.  

Replace the most expensive equipment with cheaper ones to allow easier purchase approval

C.  

Ask the organization to allow the project manager to approve all purchases

D.  

Propose that the project sponsor approve all equipment that needs to be purchased

Discussion 0
Questions 428

A project manager is leading the construction of a high-rise mall for a customer in an emerging competitive market. Some customers want to move in as soon as the ground floor is completed. What should the project manager do to deliver business value to the client?

Options:

A.  

Use management reserve and crash the schedule

B.  

Implement an agile project delivery approach

C.  

Explain the need to follow the quality assurance (QA) schedule to the customer

D.  

Adopt an incremental project delivery approach

Discussion 0
Questions 429

A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification from the local community is received demanding the project be stopped. What should the project manager do first?

Options:

A.  

Meet with project stakeholders to define a mitigation plan

B.  

Register the issue and escalate it to the project sponsor

C.  

Estimate the cost of changing the project location

D.  

Execute the contingency plan defined in the risk management plan

Discussion 0
Questions 430

The project team has reviewed the requirements and identified some concerns. The project sponsor has asked the team how they will handle each concern. What should the project manager do next?

Options:

A.  

Work with the project team to assess the severity of each risk.

B.  

Collaborate with the stakeholders on the communications management plan.

C.  

Consult with team members to produce a Monte Carlo simulation diagram.

D.  

Develop a mitigation strategy for each risk and update the risk register.

Discussion 0
Questions 431

A project manager is working on an agile project. The organization does not have experience with agile delivery. During business case development, the new product owner asks when project deliverables are considered complete. How should the project manager respond?

Options:

A.  

At the end of each sprint, the outcome is considered ready for production

B.  

The scrum master will approve the user stories that are complete

C.  

Backlog items are considered complete when the product owner approves the demo

D.  

Items are considered complete when they satisfy the definition of done (DoD)

Discussion 0
Questions 432

A project manager has been assigned to a new agile project with rapidly changing knowledge areas. How should the project manager manage knowledge transfers on this project?

Options:

A.  

Require stakeholders to fully document all domain knowledge before starting

B.  

Mentor the team and stakeholders to ensure domain knowledge is exchanged during sprints

C.  

Ask the team to set up initial sprints for knowledge transfer before focusing on deliverables

D.  

Work with QA to ensure domain knowledge is transferred properly among stakeholders

Discussion 0
Questions 433

A project manager notices a product owner has been unresponsive over the last few weeks. During one-on-one sessions, the product owner is unable to provide complete information, leading to rework of the project stories. What should the project manager do first?

Options:

A.  

Increase the sprint duration to accommodate the additional work

B.  

Conduct a root cause analysis before addressing the issue

C.  

Escalate the issue to the stakeholder's functional manager

D.  

Cancel the one-on-one sessions and obtain the information via email

Discussion 0
Questions 434

A project team member finishes all assigned tasks in the middle of a sprint. The team member wants to plan tasks for the next sprint to deliver business value earlier. The team member has the abilities and knowledge to execute tasks not yet started by other team members in the current sprint. What should the project manager do?

Options:

A.  

Validate completeness of the tasks delivered in the current sprint

B.  

Increase team velocity to execute tasks for the next sprints

C.  

Reassign the team member to other tasks in the current sprint

D.  

Encourage the team member to execute the next sprint tasks

Discussion 0
Questions 435

A project manager is working on a large event and developing budgets for sign-off. The stakeholders and project sponsor are all working remotely using various tools to ensure that all documentation is tracked and handled discretely and appropriately. The primary stakeholder has missed several deadlines for the milestone sign-offs, resulting in the project manager being forced to find alternative suppliers for items, now at higher costs. When questioned regarding the delays, the stakeholder says the notifications hadn’t appeared in their email inbox. How should the project manager proceed?

Options:

A.  

Escalate the issue to the IT department and request they check the software on the stakeholder's computer.

B.  

Request human resources (HR) intervene and send the stakeholder to appropriate technical training.

C.  

Assess whether the communications channels are appropriate for the primary stakeholder and amend accordingly.

D.  

Request the primary stakeholder be replaced to avoid any more delays and budget issues.

Discussion 0
Questions 436

A project team completed sprint planning, but at the end of the session the project lead receives a message from a stakeholder about a legislative change that requires a new validation rule in one backlog item committed for the sprint. What should the project lead do?

Options:

A.  

Remove the current backlog item from the sprint and replace it with defect fixing

B.  

Remove the current backlog item from the sprint and replace it with a similar item

C.  

Update the backlog and advise the team to add this to the acceptance criteria

D.  

Update the product backlog and include the change as a high priority for the next iteration

Discussion 0
Questions 437

A project team member tells the project lead that expecting a similar delivery output for every day of the sprint is not realistic. The project lead reports this to the project management office (PMO). What should the project lead do?

Options:

A.  

Discuss the issue with the product owner

B.  

Discuss this with the project team in the next sprint retrospective meeting

C.  

Discuss this with the project team in the next sprint planning meeting

D.  

Discuss this with the PMO manager

Discussion 0
Questions 438

A project manager is hired to work on a very large, complex project that requires the team to complete a significant number of specialized tasks. What strategy should the project manager incorporate to help organize, assign, and monitor these tasks?

Options:

A.  

Create a list of the tasks and send it to the project sponsor for review and approval.

B.  

Develop a work breakdown structure (WBS) that decomposes the project deliverables into work packages.

C.  

Schedule a meeting with the stakeholders to determine which tasks can be eliminated.

D.  

Prepare a resource management plan that details all the resources needed to complete the tasks.

Discussion 0
Questions 439

A project manager has just started a new project for an organization that dislikes budget and schedule deviations. The project stakeholders are very engaged and want to ensure there is clear visibility of the project’s risks and progress. How should the project manager handle stakeholder expectations?

Options:

A.  

Discuss the risk response strategies with the stakeholders

B.  

Add buffers to the schedule to accommodate unforeseen changes

C.  

Ensure the risk register includes all identified risks

D.  

Develop a communications management plan to share updates with stakeholders

Discussion 0
Questions 440

During the project planning phase, the customer explained the importance of delivering the project results proposed in the scope as soon as possible. What should the project manager do first to address this?

Options:

A.  

Assess the opportunities to deliver project value incrementally

B.  

Gather all the requirements’ details and schedule a refinement meeting

C.  

Prepare a project management plan for the full scope using an agile approach

D.  

Approve a change request to change the project approach to agile

Discussion 0
Questions 441

A project manager is leading a project with a risk management plan detailing strategy and actions if any identified risks become an issue. One of the identified risks becomes an issue, but the project manager believes the planned response may not be the best. What should the project manager do?

Options:

A.  

Meet with the project team and sponsor to reevaluate all issue responses registered in the risk management plan

B.  

Escalate the issue to the sponsor and register the new risk response in the project documents

C.  

Adopt the action prescribed in the risk management plan since it was agreed to beforehand

D.  

Submit a change request to perform a different issue response than what is registered in the risk management plan

Discussion 0
Questions 442

A project manager has been tasked with developing a project schedule with fully detailed requirements. The project manager reaches out to subject matter experts (SMEs) for their initial thoughts on task duration. The project manager is concerned when these estimates appear to differ significantly. What should the project manager do to help with the estimate development?

Options:

A.  

Ask the SMEs to hold up cards that show their estimate, discuss the highest and lowest estimates, and then estimate again.

B.  

Recommend using an iterative approach, with a focus on estimates, that the SMEs agree with.

C.  

Use historical information to help guide the estimates that were proposed by the SMEs.

D.  

Escalate to the project sponsor and explain the differences in the estimations coming from the SMEs.

Discussion 0
Questions 443

A product is facing performance issues that will significantly decrease the manufacturing yield expected, increasing the cost. This will be an issue as it will limit one of the high-margin contracted goals. Because it is a breakthrough development, the speed to market is key. What should the project manager do?

Options:

A.  

Negotiate with operations to absorb the cost while the product is launched and remediate the issue.

B.  

Engage with the sales team to increase the sales price since it is a breakthrough product.

C.  

Evaluate the most cost-effective containment action and use their influence to implement it.

D.  

Assess what corrective action is appropriate and use their influence to implement it.

Discussion 0
Questions 444

A project lead accepted an assignment for a project that is still in the feasibility study phase. There are many uncertainties about project specifications, including poor alignment among the project sponsors on the final targets of the project. Which approach should the project lead choose to deliver business value?

Options:

A.  

Subdivide project tasks to find the minimum viable product (MVP)

B.  

Identify and communicate clear risk mitigation plans

C.  

Recommend predictive project management to the sponsors

D.  

Ensure commitment from sponsors on executing the project until it ends

Discussion 0
Questions 445

A project manager is assigned to lead a team comprised of business executives. After several roadmaps were denied by the sponsor, the project manager asks to be removed from the project. The sponsor urges the project manager to find a solution as the sponsoring organization requested their assignment. What should the project manager do?

Options:

A.  

Emphasize to the executives that the project manager was specifically requested for this project

B.  

Schedule deliverables solely based on priorities and must-have-by dates, and gauge responses

C.  

Hold a team meeting emphasizing existing governance policies and procedures

D.  

Adopt a project framework aligned to the executives’ availabilities and then evaluate the risks

Discussion 0
Questions 446

A new stakeholder is unaware of the existence of the project a few weeks before the final deliverable and project completion. What should the project manager do first?

Options:

A.  

Escalate this issue to the project sponsor.

B.  

Communicate the full details of the project activities to the stakeholder and solicit input.

C.  

Analyze this stakeholder’s interest and impact.

D.  

Share the summary of the project activities with the stakeholder and conclude the project.

Discussion 0
Questions 447

A project manager is presented with a roadmap that excludes most of their recommendations. The content source of the roadmap is an influential stakeholder who disagrees with the use of specific procedures and practices. The project sponsor deems the roadmap acceptable. Which two actions should the project manager take first? (Choose 2)

Options:

A.  

Align the roadmap within the project framework and perform a risk analysis.

B.  

Align deliverables based on the roadmap and documented results.

C.  

Request to have the roadmap reviewed by the project management office (PMO).

D.  

Request reassignment to another project to avoid conflict with the stakeholder.

E.  

Discuss the reasoning behind the roadmap with the stakeholder.

Discussion 0
Questions 448

The execution stage of a construction project is beginning. There are many areas and phases to be built. The project team wants to review the relationships between the most important tasks to ensure that major items are executed properly during this stage. What project artifact should the project manager review with the team?

Options:

A.  

Project milestone chart

B.  

Project schedule management plan

C.  

Project statement of work (SOW)

D.  

Project program evaluation review technique (PERT)

Discussion 0
Questions 449

Two project managers are competing to assign a key subject matter expert (SME) to their concurrently scheduled projects. Work requiring constant physical presence means the SME can serve on only one project at a time. What should the project managers do first to facilitate allocation of the resource?

Options:

A.  

Calculate the schedule performance index (SPI) based on the SME assignment

B.  

Assess both projects to determine the business benefits based on the SME assignment

C.  

Evaluate the associated budget and schedule based on the SME assignment

D.  

Determine the cost performance index (CPI) based on the SME assignment

Discussion 0
Questions 450

A project manager has recently been assigned to a construction project. The project has hundreds of stakeholders and three stages. The project manager recognizes that many steps have already been started, including risk identification. The project sponsor asks the project manager to rank the risks contained in the register. How should the project manager respond to the request?

Options:

A.  

Execute a qualitative analysis to provide identified risks prioritization.

B.  

Inform that a quantitative risk prioritization was completed using Monte Carlo simulation.

C.  

Inform that a qualitative analysis has already been completed.

D.  

Perform a quantitative analysis to provide identified risks prioritization.

Discussion 0
Questions 451

A product owner asks a project manager for details about products that were added during the last iteration. What should the project manager do to gather this information and send it to the product owner?

Options:

A.  

Evaluate the sprint backlog

B.  

Evaluate the product backlog

C.  

Evaluate the sprint increment

D.  

Evaluate the product development cycle

Discussion 0
Questions 452

A project management plan needs to be updated due to recent product requirements changes, but the latest version of the document is missing. What should the project manager do to prevent this from happening again?

Options:

A.  

Improve the configuration management process

B.  

Register an issue for the missing documents

C.  

Ensure the lessons learned register is up to date

D.  

Review the quality assurance (QA) processes

Discussion 0
Questions 453

After a project review meeting, a key stakeholder tells another stakeholder they do not trust the project status report. The second stakeholder approaches the project manager and mentions the conversation. What should the project manager do?

Options:

A.  

Request the sponsor ask the key stakeholder to be attentive during the project review meeting

B.  

Schedule a meeting with the key stakeholder to address the issue and obtain direct feedback

C.  

Email the status report to all stakeholders and ask them to review and provide feedback

D.  

Present the status report in a chart and assume everyone understands the report

Discussion 0
Questions 454

A project team is continually being asked by stakeholders to perform rework on their deliverables. The project manager discovers that this is due to poor initial quality. What should the project manager do?

Options:

A.  

Host a team meeting and ask the team to fix any quality issues immediately since the stakeholders’ needs are the main focus.

B.  

Request a subject matter expert (SME) from the project sponsor to identify and address the quality issues with the team.

C.  

Facilitate a discussion and come to an agreement about what quality means for both the team and the stakeholders.

D.  

Schedule a quality retrospective and discuss the challenges that resulted in poor initial quality with the team.

Discussion 0
Questions 455

A new project manager has been hired at a company that has suffered many project failures. The project manager has been tasked with delivering a software product for the company’s biggest customer. The customer has not been able to articulate how a major piece of functionality should work. The project manager wants to deliver value immediately. How should the project manager approach the software development life cycle with this customer?

Options:

A.  

Assign a business analyst to build detailed requirements so the project manager can estimate the project duration

B.  

Explain that the team will build a production prototype model to help the customer visualize how the features should work

C.  

Add extra time and resources to the estimating phase to accommodate the lack of requirements

D.  

Raise a risk that scoping and estimating will be delayed if the customer cannot approve requirements

Discussion 0
Questions 456

A project manager has been assigned to a project. The project deadline has been established but, based on the number of stakeholders to engage and interview, it will be difficult to complete the project within the timeline. How should the project manager address this challenge?

Options:

A.  

Commit to completing the deliverables associated with only the engaged parties.

B.  

Submit a change request to extend the time needed to engage all of the parties.

C.  

Request that the product owner define which parties should be engaged first.

D.  

Prioritize the engagement of parties who are most impacted to minimize project risk.

Discussion 0
Questions 457

An experienced project manager has recently joined a troubled project. The project is impacted by multiple delays caused by a vendor’s late delivery of new servers. Due to budget restrictions, the project manager cannot switch vendors, and the project must be completed within a maximum of 90 days as agreed. What should the project manager do?

Options:

A.  

Request the vendor to provide the servers on time as penalties may be applied

B.  

Wait until the project deadline is reached in order to use contingency funds

C.  

Reach out to the vendor to determine a plan to get the project back on track

D.  

Review lessons learned from previous projects and take action accordingly

Discussion 0
Questions 458

A construction project is in its final stage when the owner of a private property where the pipeline is routed refuses to collaborate. The lack of collaboration causes a project delay, but the client insists that the project must be completed as per the contract. What should the project manager do next?

Options:

A.  

Request additional budget from the project sponsor and raise a dispute with the property owner to force them to collaborate.

B.  

Use the contingency reserve, add more resources, and reroute the pipeline to complete the project as per the contract timeline.

C.  

Escalate the routing pipeline issue to the project change control board (CCB) and wait for a resolution to the conflict.

D.  

Review the agreement with the property owner, schedule a meeting with them to discuss their concerns, and inform the client.

Discussion 0
Questions 459

A project manager is leading a hybrid project. A project team member has not been delivering on time; as a result, the project is about to be delayed. What should the project manager do?

Options:

A.  

Revise the project schedule with the customer

B.  

Schedule a meeting with the project team to address timelines

C.  

Negotiate revised timelines with the project sponsor

D.  

Discuss the situation with the project team member

Discussion 0
Questions 460

A key stakeholder asks the project manager to complete all deliverables sooner than the agreed-upon schedule. The project is halfway complete and currently has a schedule performance index (SPI) of 0.9 and a cost performance index (CPI) of 1. What should the project manager do first before committing to the stakeholder?

Options:

A.  

Add more resources to complete the remaining deliverables early.

B.  

Review and analyze the risks associated with compressing the schedule.

C.  

Prioritize critical activities and skip noncritical activities.

D.  

Perform several activities in parallel to compress the schedule.

Discussion 0
Questions 461

Five vendors are contributing to a project with an impending deadline. Two vendors are behind on their deliverables and rarely provide status updates. What should the project manager do?

Options:

A.  

Begin daily check-ins with the two vendors to recover time at their own expense

B.  

Extend the project schedule and inform the vendors it was due to their poor performance

C.  

Find replacements for the two vendors to complete the project in a timely manner

D.  

Reduce the two vendors’ pay due to poor performance and lack of communication

Discussion 0
Questions 462

A project manager is assigned to an IT project to deliver a new accounting system. Some managers at the company do not see the value of this project and say they will not use the new system. What two actions should the project manager take? (Choose 2)

Options:

A.  

Review the list of stakeholders that will be affected by starting this business initiative.

B.  

Continue with the project the way it was planned and validated by the sponsor.

C.  

Describe the outcome of the project and business value to all company stakeholders.

D.  

Add this issue to the risk register and monitor stakeholder engagement at the next milestone.

E.  

Modify the project management plan and scope of work to avoid future difficulties.

Discussion 0
Questions 463

A project is being planned with two hardware deliverables and one software deliverable that will be used to monitor the operation of the two hardware deliverables. When preparing the consolidated project schedule, what should be the top priority for the project manager?

Options:

A.  

The interdependencies between the deliverables

B.  

The business continuity plan of the deliverables

C.  

The stakeholder engagement plan

D.  

The user stories and story points

Discussion 0
Questions 464

A project is in its first of six iterations. The project team realizes that a key deliverable is dependent on the acquisition of a new device. The vendor is new to the organization and does not have a long history in the market. What should the project manager do first?

Options:

A.  

Register the risk and provide appropriate response options.

B.  

Register the risk and prioritize the implementation strategy.

C.  

Register the risk and escalate it to the procurement team.

D.  

Register the risk and escalate it to the project sponsor.

Discussion 0
Questions 465

A project manager recently took over an ongoing project. Within a few weeks on the project, the project manager discovers that there are continuous change requests from different project end users. What is the probable cause for this?

Options:

A.  

Undefined change control process

B.  

Unidentified project risks

C.  

Improper work breakdown structure (WBS)

D.  

Incomplete requirements

Discussion 0
Questions 466

A project manager is leading a project with a negative risk that has just become an issue. The risk was recorded and a response plan was set. However, a project team member proposes a response that differs from the response recorded in the risk management plan and believes it will be cheaper and equally effective. What should the project manager do?

Options:

A.  

Evaluate the new proposal with the project team to determine if it is a more beneficial alternative

B.  

Adhere to the issue response in the risk management plan as it is the agreed-on solution

C.  

Implement the new proposal as soon as possible since it is cheaper and equally effective

D.  

Ask the team member to write a formal email explaining the proposal and send it to the change control board (CCB)

Discussion 0
Questions 467

During project implementation, a critical performance issue is identified by team members. What should the project manager do?

Options:

A.  

Submit a change request to handle the performance issue

B.  

Review the tender requirements related to the performance issue

C.  

Pass the performance issue to subject matter experts (SMEs) to handle

D.  

Work with the project stakeholders to address the performance issue

Discussion 0
Questions 468

A project sponsor is transitioning their division to an agile environment and has emphasized that project team members and stakeholders should collaborate to achieve deliverables. On a few occasions, progress has been interrupted by one stakeholder who is unfamiliar with agile approaches. What should the project manager do first?

Options:

A.  

Report the behavior to the project sponsor and find a replacement.

B.  

Note the stakeholder’s attitude as a risk and continue development according to the plan to deliver value.

C.  

Consider using a predictive project management framework and report the results to the project sponsor.

D.  

Address the stakeholder’s behavior directly and provide feedback.

Discussion 0
Questions 469

A project manager is assigned to a large complex project with cross-functional dependencies. The project enters a new phase requiring new stakeholders to be added with conflicting priorities. How should the project manager ensure successful engagement with the stakeholders?

Options:

A.  

Invite all stakeholders to status meetings.

B.  

Identify and categorize the stakeholders.

C.  

Interact individually with the stakeholders.

D.  

Recognize the diversity of the stakeholders.

Discussion 0
Questions 470

Two days before the end of a sprint, a team member updates the team lead that they will not be able to complete their tasks for the sprint due to a technical difficulty. What should the agile team lead do?

Options:

A.  

Inform the product owner of the issue and request that they reprioritize the delayed task.

B.  

Suggest the team member get more technical training in the next quarter.

C.  

Update the risk register to reflect the possible risk of a schedule delay.

D.  

Raise this issue during the daily meeting to determine a possible solution with the team.

Discussion 0
Questions 471

In a fixed time and budget project, the customer wants development of a core component to be based on agile practices because the final scope has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact project profitability. Which two controls should the project manager incorporate into the contract to address development of the core component? (Choose 2)

Options:

A.  

Establish a governance committee to review contract delivery

B.  

Require that only internal resources be utilized for this project

C.  

Provide alternatives to scope change at specific project phases within the contract

D.  

Tier the contract for fixed and agile components

E.  

Limit the number of iterations for development in the contract

Discussion 0
Questions 472

During daily team coordination meetings, team members constantly ask which tasks they should focus on first. How should the project manager ensure the team is fully productive?

Options:

A.  

Work with the product owner to ensure the product backlog is prioritized

B.  

Review the project backlog during the team’s coordination meeting

C.  

Encourage team members to prioritize the product backlog

D.  

Ensure team members are working according to the project management plan

Discussion 0
Questions 473

An agile team of specialized engineers has completed some tasks later than planned and with a lower quality than expected. The situation is limiting the value the team is creating for the business. What should the project manager do next?

Options:

A.  

Execute the next iteration planning considering the quality issues.

B.  

Schedule quality reviews to obtain stakeholder approvals and feedback.

C.  

Confirm the right quality tests are applied before moving to the next iteration.

D.  

Include all the quality problems found in the technical debt backlog.

Discussion 0
Questions 474

A project is in its fourth iteration out of eight with a delivery performance of 95%. A project stakeholder asks the project manager about the status of a specific deliverable not visible in the status report. What should the project manager do?

Options:

A.  

Include the deliverable in the status report and resend it to the stakeholder

B.  

Invite the stakeholder to the next iteration review

C.  

Invite the stakeholder to the next daily meeting

D.  

Schedule a meeting with the stakeholder to review the status report

Discussion 0
Questions 475

A team identifies a critical set of tasks that have not been included in the Kanban board, and there is not enough budget for the work hours needed to complete the activities. What solution should the agile project manager implement?

Options:

A.  

Review alternatives with the product owner and agile team.

B.  

Involve stakeholders and ask them to descope some features.

C.  

Ask the sponsor for additional resources to hold the schedule.

D.  

Increase productivity and modify the schedule as needed.

Discussion 0
Questions 476

An increment was delivered to the customer at the end of a sprint. The customer complains that the product does not meet the expected quality and will require some rework. What should the project manager do next?

Options:

A.  

Review the evidence of the quality assurance (QA) activities performed.

B.  

Perform an analysis of the impact caused by the required rework.

C.  

Include time in the next increment for quality assurance (QA) inspections.

D.  

Confirm with the customer the expected quality in the next increment.

Discussion 0
Questions 477

A complex project is being developed in phases as per the original plan. Half of the systems have been handed over to the customer for operational use. There is no delay in the schedule. However, the customer is still not happy because some of the systems handed over are no longer useful due to changes in the environment. What should the project manager have done to avoid this?

Options:

A.  

Asked the customer to participate in project status meetings to better understand the progress

B.  

Informed the project team to closely monitor the deliverables and keep the customer informed

C.  

Reviewed benefits realization with the customer regularly and constantly aligned expectations

D.  

Explained to the customer that the project is in good shape as the system is operational

Discussion 0
Questions 478

During a status meeting, a project manager reported that a project is on track. However, the project sponsor thinks the project is behind schedule because a few tasks have already passed their planned finish dates but are still in progress. How should the project manager revise the report and demonstrate the project is on schedule?

Options:

A.  

Use a network diagram to show that the delayed tasks are not on the critical path.

B.  

Use a network diagram to show the task duration and dependencies among tasks.

C.  

Use a Gantt chart to compare the actual schedule with the planned project schedule.

D.  

Use a resource histogram to show that the resources are adequate to complete all tasks on time.

Discussion 0
Questions 479

A project team has deployed an email marketing campaign across different countries. In one country, the end users have been opting out of the campaign because they think the email is spam. What should the project manager do first?

Options:

A.  

Conduct a retrospective meeting to identify what went well and what went wrong.

B.  

Review the email marketing standards of that country with the stakeholders.

C.  

Schedule a meeting with project team members to identify the root cause.

D.  

Schedule additional country-specific user testing to reduce email opt out.

Discussion 0
Questions 480

A company started a project to create a new product that will be delivered in iterations. The artwork development plan included extensive consultation and validation before the build. The company changed the focus of the project to speed to market because one of their competitors announced the launch of a similar product. What should the project lead do?

Options:

A.  

Work with the product owner to assess the impact and reprioritize the product backlog.

B.  

Schedule a meeting with the project sponsor to identify and allocate additional resources.

C.  

Submit a formal change request and obtain approval from the change control board (CCB).

D.  

Meet with the Scrum Master to determine if the development cycle can be reduced.

Discussion 0
Questions 481

During a blueprint review meeting, the finance department representative is not comfortable with a proposed solution that favors another department. As a result, document approval is delayed and impacts the project schedule. What should the project manager do?

Options:

A.  

Work with the project team to find a compromise solution that suits both departments

B.  

Schedule a meeting with the project sponsor to seek advice on the approach of both departments

C.  

Arrange a meeting with the two departments to understand their differences and address their needs

D.  

Assess the risk of postponing this specific solution and advise both departments of the delay

Discussion 0
Questions 482

A project manager is leading a contract for a new market that was awarded to their company. The client has the desire to jump-start the market with informal sector traders. What should the project manager do?

Options:

A.  

Plan the project in phases, starting with the informal sector, to deliver business value quickly

B.  

Divide the project team into groups to execute as small parallel projects, including the informal sector

C.  

Gather requirements and convert them into backlog items to quickly deliver value

D.  

Execute the projects simultaneously following the project schedule and the communications management plan

Discussion 0
Questions 483

An organization that is running several simultaneous projects suddenly experiences a surge of resignations, leading to a lack of talent. Consequently, some of the projects have been missing key milestones. What should the project manager do to recover from the delays?

Options:

A.  

Reduce the projects’ scope to meet the upcoming target dates.

B.  

Crash the schedule from the delayed projects to meet upcoming target dates.

C.  

Fast-track the delayed projects so they can meet upcoming target dates.

D.  

Ask for project sponsor approval to revise the upcoming target dates.

Discussion 0
Questions 484

A project manager is leading a software development project with agile practices and has outsourced work to three well-qualified subcontractors. Over time, problems arise related to supply-chain management, and the project manager considers replacing the subcontractors with new suppliers. What should the project manager have done to avoid this problem?

Options:

A.  

Hired more Scrum Masters so every Scrum Master manages one supplier.

B.  

Escalated the issue to the product owner to seek possible solutions.

C.  

Engaged the suppliers by category and validated the strategy with stakeholders.

D.  

Created user stories for the suppliers and saved their qualification records to the backlog.

Discussion 0
Questions 485

A project sponsor is upset that a vital project might miss an agreed-upon delivery deadline. The sponsor asks the project manager to check whether the project team can do anything to deliver on time. What should the project manager do first?

Options:

A.  

Increase project team resources to maintain the timeline

B.  

Conduct simulations to determine the best way forward to ensure timely delivery

C.  

Reduce scope to deliver on time

D.  

Work with the team to ensure the project is delivered on time

Discussion 0
Questions 486

During a sprint planning meeting, a project team analyzes the effort required to complete some of the tasks before aligning on a sprint commitment. The project team faces issues when trying to estimate the testing effort for the tasks. What should the project manager do first?

Options:

A.  

Obtain the acceptance criteria from the product owner.

B.  

Encourage the team to do pair programming to reduce testing.

C.  

Ensure the definition of done (DoD) is understood by all team members.

D.  

Involve a quality assurance (QA) expert to support the testing estimation.

Discussion 0
Questions 487

A project manager is leading a complex project. The team is being challenged with frequent, incremental, and uncontrolled changes to the project. What should the project manager do?

Options:

A.  

Establish a detailed quality management plan.

B.  

Establish a detailed risk management plan.

C.  

Establish a detailed scope management plan.

D.  

Establish a detailed schedule management plan.

Discussion 0
Questions 488

An ongoing project is facing a challenging situation where the customer is not satisfied. The team is new to agile development and frequently communicates with the customer and gives regular status reports. What should the project lead do to satisfy the customer?

Options:

A.  

Reduce frequent communication and improve the status report format to include team progress

B.  

Schedule a meeting with the customer and explain the team is new to agile and the situation will improve

C.  

Review the situation with the customer and make the required adjustments with the team

D.  

Review project progress with the customer and modify the frequency of sprint review

Discussion 0
Questions 489

A project manager is executing a project on time and on budget. Before a stage gate review, the project manager receives the regular business management report, but this time it indicates a negative impact on the project success factors. What should the project manager do?

Options:

A.  

Continue with execution since the project was successful up to this phase

B.  

Call for business development to revalidate inputs at the next stage gate

C.  

Provide the necessary analysis to enable examination of the business value

D.  

Request a delay to the stage gate until business development provides the next update

Discussion 0
Questions 490

A project manager is working on a multinational project with stakeholders from different regions. What should the project manager do first to ensure there is effective stakeholder collaboration?

Options:

A.  

Review the stakeholder engagement plan with all of the stakeholders.

B.  

Schedule regular virtual coordination meetings and invite all stakeholders.

C.  

Request budget to invite all stakeholders to in-person team meetings.

D.  

Analyze stakeholder interest levels to develop an engagement strategy.

Discussion 0
Questions 491

A project manager is working on a project. A few months after the project has launched, the project manager starts receiving complaints from business unit managers about the lack of updated project information. What should the project manager do?

Options:

A.  

Run a Monte Carlo simulation to identify any flaws in the communication matrix

B.  

Request that the business unit managers attend weekly review meetings

C.  

Check the organizational responsibility of functional managers in the project

D.  

Review the communications management plan and stakeholder register

Discussion 0
Questions 492

A project manager is in the beginning stages of delivering a project and is assessing and prioritizing identified risks. What should the project manager do next?

Options:

A.  

Plan the risk responses and assign risk response owners.

B.  

Start monitoring and controlling the identified risks.

C.  

Proceed with executing the risk management plan.

D.  

Spend the contingency budget on the identified risks.

Discussion 0
Questions 493

A project manager presents the project schedule to the customer, including the detailed phases for the whole project. The customer complains that the project timeline is longer than expected and does not want to wait until the end to see results. What should the project manager do first?

Options:

A.  

Adjust the project schedule to include additional resources for all project tasks.

B.  

Submit a change request to extend the project timeline.

C.  

Evaluate the impact of changing the project framework to an incremental approach.

D.  

Apply crashing techniques to all activities in the project schedule.

Discussion 0
Questions 494

A project team has been tasked with delivering robotics to automate a manufacturing line. The technical teams are all in place and have the technical information needed to build and install the robots. What other factors should be considered when planning this project?

Options:

A.  

Software, security, and infrastructure.

B.  

Industry standards and research.

C.  

Safety and organizational culture.

D.  

Financial and market conditions.

Discussion 0
Questions 495

There are several dependent work streams in a project. Some project stakeholders feel that coordination among team members and progress visibility are lacking. What should the project manager do?

Options:

A.  

Discuss the concerns with the project sponsor

B.  

Organize a team meeting to review the project status

C.  

Review and update the communications management plan

D.  

Escalate the concerns to the project steering committee

Discussion 0
Questions 496

Which three of the following scenarios are impediments to which a scrum master should pay attention? (Choose three)

Options:

A.  

A team member talking about a user story that is not on the Scrum board

B.  

A team member talking about a user story that is on the Scrum board

C.  

A technology that blocks agile capabilities

D.  

A lack of team empowerment and an inability to self-organize

E.  

A review of the backlog at daily standup meetings

Discussion 0
Questions 497

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?

Options:

A.  

Meet with the project team to decide how the remaining budget will be spent.

B.  

Keep the extra budget as management reserve until project closeout

C.  

Give the team extra time to finish tasks within the original timeline

D.  

Follow the project escalation policy and communications management plan

Discussion 0
Questions 498

A project manager is implementing a new software system Some department staff members are questioning the necessity of the change and feel the new system will impede their current processes

What should the project manager have done at the start of the project to prevent this resistance?

Options:

A.  

Created a communications management plan that outlined the method of communicating to stakeholders.

B.  

Ensured that the company culture encourages changes before accepting the project

C.  

Encouraged leadership to discuss the change with departments that are typically resistant to change

D.  

Involved stakeholders from all levels of the company so everyone understands the change

Discussion 0
Questions 499

A company recently used desktop research for a feasibility study, which showed that the project is behind schedule The project team also has concerns about the impact of scope changes on the project schedule

What should the project manager do to keep the project on schedule while still meeting project objectives'?

Options:

A.  

Collaborate with the change control board (CCB) to review the scope and submit any change requests

B.  

Submit a change request to the CCB and update the schedule

C.  

Update the scope and add more resources to the project

D.  

Update the scope and move on to the next project milestone

Discussion 0
Questions 500

A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals

What two options will help the team initially address this obstacle? (Choose two)

Options:

A.  

Escalate the issue to the project sponsor.

B.  

Review and update dependencies

C.  

Schedule a retrospective.

D.  

Conduct a root cause analysis.

E.  

Create a risk management plan.

Discussion 0
Questions 501

An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)

Options:

A.  

Ask the stakeholders about the priority of this change

B.  

Ask the product owner to review the product backlog

C.  

Ask the team members to analyze the impact of this change

D.  

Ask the sponsor to approve the change request

E.  

Ask the team members to include the change in the next iteration

Discussion 0
Questions 502

A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?

Options:

A.  

Probability assessments

B.  

Collaborative discussions

C.  

Workshops for risk avoidance

D.  

Interview with the project champion

Discussion 0
Questions 503

Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings

What should the project manager do?

Options:

A.  

Schedule a meeting for the project team to review the communications management plan.

B.  

Tell the rest of the project team to continue discussions with the new team member

C.  

Send an email to the project team outlining the communications strategy.

D.  

Mentor the new team member on the methodology the project team is using

Discussion 0
Questions 504

A project manager is leading a large-scale project that involves 70 stakeholders The project manager has heard various comments and expectations from the customers, some of which are contradictory Consequently, some requirements are not clear.

What should the project manager do to build consensus regarding the requirements?

Options:

A.  

Escalate the issue to the management team for their review and guidance

B.  

Create a survey template to collect feedback from stakeholders to reach an agreement

C.  

Organize a face-to-face meeting with all stakeholders to understand their interests and concerns.

D.  

Leverage expert judgment to determine the requirements that should be considered

Discussion 0
Questions 505

During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team

How should the project manager handle this situation?

Options:

A.  

Implement crashing to compress the schedule and improve the schedule performance index (SRI).

B.  

Implement fast-tracking to compress the schedule and improve the SPI

C.  

Perform conflict management using the project's resource management plan.

D.  

Review the risk management plan to evaluate the probability and impact of these delays

Discussion 0
Questions 506

In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1 25 The project manager must provide the first project status review soon and wants to emphasize that the project is under control

How should the project manager report the project status to key stakeholders?

Options:

A.  

Prepare a detailed presentation for stakeholders on earned value including how it is calculated and the project's current earned value results

B.  

Report that the project is behind schedule but that an additional experienced resource can be added to stay within schedule and maintain the budget.

C.  

Perform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to demonstrate that the project is under control.

D.  

Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away

Discussion 0
Questions 507

A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts

What should the project manager do next?

Options:

A.  

Raise the issues in the retrospective and propose solutions

B.  

Inform management that commitments will not be met.

C.  

Involve management to help resolve the conflicts

D.  

Coach the team both as a whole and individually

Discussion 0
Questions 508

An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right

Options:

Discussion 0
Questions 509

During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.

What two actions should the project manager take to prevent the team from being unqualified? (Choose two)

Options:

A.  

Exclude the activities from the roadmap

B.  

Encourage working in pairs and knowledge sharing

C.  

Teach the entire team the new skill.

D.  

Facilitate a training event with an external trainer

E.  

Increase the time estimates on the activities that require such abilities

Discussion 0
Questions 510

A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints However the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion

What are two issues that these actions by the project manager could cause? (Choose two)

Options:

A.  

A lot of discussions that yield no results or possibly too many results

B.  

A lack of direction and motivation for the team in the workshop

C.  

Lessons learned from other teams to not be considered

D.  

Time management plan for the retrospective workshop to not be updated

E.  

A focus on the negative and a disinterest in further improvements

Discussion 0
Questions 511

A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders The project manager has been assigned and is now in the project planning phase

What item(s) should the project manager develop first?

Options:

A.  

A product backlog and identification of the features to be delivered

B.  

A business case and scope document

C.  

A communications management plan that addresses the team's needs

D.  

A risk management plan to incorporate known risks

Discussion 0
Questions 512

The project sponsor recently requested that a vendor begins working toward adopting a hybrid approach. In response, the vendor hired a project manager experienced in agile for the project.

What does that project manager need to do to make the team work in a collaborative way?

Options:

A.  

Request the project management office (PMO) for a team of mentors.

B.  

Allocate time to mentor the team.

C.  

Update the issue log.

D.  

Identify any training gaps

Discussion 0
Questions 513

A project manager meets with external stakeholders to explain the objectives and outline expectations for a new project. A key stakeholder appears to support the project, with the condition that other unrelated projects will receive financial support Due to cultural sensitivities the project manager is reluctant to be direct with the key stakeholder on this matter The project cannot proceed without the support of this stakeholder.

What should the project manager do?

Options:

A.  

Proceed with the project without allowing scope creep to occur

B.  

Use the contingency funds to provide support for the requested projects

C.  

Cancel the project since the stakeholder's request is out of scope

D.  

Inform the sponsor and document the request in the stakeholder engagement plan

Discussion 0
Questions 514

During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting The ongoing conflict is preventing tasks and deliverables from being completed The project manager contemplates changing their leadership style

What should the project manager do?

Options:

A.  

Review the set of responsibilities with the team member

B.  

Avoid the team member to prevent further conflicts

C.  

Escalate the situation to the project sponsor

D.  

Review the personnel skill documents

Discussion 0
Questions 515

During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule What should the project manager do first?

Options:

A.  

Update the issue log and act to minimize the impact

B.  

Update the schedule to include the delay

C.  

Add the risk and the delay to the risk register

D.  

Escalate to the management team for delay approval

Discussion 0
Questions 516

An agile project is running its fifth iteration out of eight After the last iteration planning the team was informed that there is a new competitor in the market and it is necessary to move faster to ensure market share is not missed What should the project manager do?

Options:

A.  

Add the competitor's functionalities to the product backlog to improve the product

B.  

Ask the sponsor to add more people to the team

C.  

Help the team to find a new approach to launch the product as soon as possible

D.  

Ask the team to increase the velocity to launch the product as soon as possible

Discussion 0
Questions 517

To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations

What should the project manager do?

Options:

A.  

Review the organizational process assessment to determine if a contingency reserve was considered in the budget estimate

B.  

Review the historical information and lessons learned from last year’s project to justify the new budget estimate

C.  

Change the budgeting technique to a more accurate, bottom-up cost estimation.

D.  

Use soft skills to convince the project sponsor to approve the new budget estimate

Discussion 0
Questions 518

Drag the communication event on the left to the mam subject discussed during the event on the right.

Options:

Discussion 0
Questions 519

A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint

What should the project manager have done to avoid this situation?

Options:

A.  

Involved the key stakeholders in the decision-making process

B.  

Customized stakeholder communications based on the stakeholders’ needs

C.  

Analyzed the changes in stakeholder attributes

D.  

Documented the project vision and objectives

Discussion 0
Questions 520

A project manager led the implementation of an electronic invoicing project that has just been completed. The financial manager communicated that the team discovered three invoices with errors.

Which two documents should the project manager update as soon as possible? (Choose two)

Options:

A.  

Issue log

B.  

Risk register

C.  

Stakeholder register

D.  

Change log

E.  

Backlog register

Discussion 0
Questions 521

During the course of the project several obstacles are identified that are preventing the project from moving forward. What should the project manager do to remove the obstacles?

Options:

A.  

Have the project team work on other activities

B.  

Implement plans to remove the obstacles

C.  

Escalate to the project steering committee

D.  

Prioritize the obstacles for resolution

Discussion 0
Questions 522

During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications

The team is confused by the product owner's statement

What should the project manager do when using a hybrid approach?

Options:

A.  

Escalate the matter to the executive board so they can decide on next steps

B.  

Prioritize the project backlog and ask the development team to fix the issues

C.  

Review the project's benefits management plan with the product owner.

D.  

Ask the product owner to terminate the project as it is no longer aligned to the expected benefits

Discussion 0
Questions 523

One of the main inputs required for a deliverable is missing due to a miscommunication between the vendor and project manager Because of the missed deliverable, the critical path of the project is extended

What should the project manager do next?

Options:

A.  

Start an audit of the vendor's processes and procedures

B.  

Review lessons learned from previous projects with this vendor

C.  

Make a detailed analysis on vendor issues during the project

D.  

Execute a contingency plan to address the issue with the vendor

Discussion 0
Questions 524

During the course of a project, the project manager wants to ensure that the work carried out and the product being created do not deviate from the prescribed business value.

What should the project manager pay special attention to in order to achieve this goal?

Options:

A.  

Reviewing and updating the requirements management plan

B.  

Carrying out quality audits and failure analyses

C.  

Monitoring the work breakdown structure (WBS)

D.  

Monitoring and updating the benefits realization plan

Discussion 0
Questions 525

A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.

What should the project manager have done to avoid this?

Options:

A.  

Used communication tools, such as video conferencing so different offices could communicate.

B.  

Learned more about how each team member prefers to communicate before assigning project work

C.  

Planned and scheduled tasks and work packages to overcome geographical and time zone challenges

D.  

Ensured that the project would be the highest priority for all team members

Discussion 0
Questions 526

During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting

What should the project manager do?

Options:

A.  

Call for a change control board (CCB) meeting, and inform the stakeholder about the outcome

B.  

Update the communications management plan and implement the change

C.  

Meet with the project sponsor to discuss how to address the situation.

D.  

Meet with the stakeholder prior to the meeting to obtain their opinion

Discussion 0
Questions 527

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?

Options:

A.  

Increased bum rate

B.  

Increased cost

C.  

Increased technical debt

D.  

Decreased efficiency

Discussion 0
Questions 528

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME) The SME refuses to accept this rejection and does not want to continue the project without the change

What should the project manager have done to avoid this situation?

Options:

A.  

Requested that the sponsor approved the change request first.

B.  

Assessed the change's overall impact to the project before submission

C.  

Ensured that the change request was aligned with the project scope

D.  

Submitted the change request directly to the CCB

Discussion 0
Questions 529

A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points

Which team is performing better?

Options:

A.  

Team A as they have calculated fewer story points than team B.

B.  

Team B as they have calculated more story points than team A

C.  

The team that completes the most stories selected from the sprint backlog

D.  

The team with the least amount of defects in their deliverables

Discussion 0
Questions 530

During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible

What approach should be used in this situation?

Options:

A.  

The team facilitator gets support from external team members.

B.  

The team members bring in a specialist to help them

C.  

The product owner moves it to the product backlog.

D.  

The cross-functional team member work together to complete the activity

Discussion 0
Questions 531

A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer

What should the project manager do?

Options:

A.  

Register starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve

B.  

Develop the quality management plan, as quality is as equally important as cost and schedule management.

C.  

Get confirmation from management that the team member has enough experienceto build software without quality control

D.  

Ask the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project

Discussion 0
Questions 532

A company is changing their current business model The change requires implementing a complex project using multiple agile teams.

What three options should the project manager have the testing team adopt as testing mechanisms? (Choose three)

Options:

A.  

Independent personal testing

B.  

Security and performance testing

C.  

An experimental approach to cover all possible choices

D.  

Story testing

E.  

Tests based on behavior and test-driven development

Discussion 0
Questions 533

At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining What will help the project manager understand why this has occurred?

Options:

A.  

Project audit

B.  

Lessons learned

C.  

Organizational process assets

D.  

Procurement audit

Discussion 0
Questions 534

A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status

What should the project manager do?

Options:

A.  

Update the stakeholder engagement assessment matrix

B.  

Update the communications management plan to include informal requests

C.  

Ask the team member to develop a dashboard to fulfill the request.

D.  

Tell the team member to route the request through the project manager

Discussion 0
Questions 535

The rollout of a new finance system is in the execution phase. A number of issues have surfaced in the last month that are slowing the project down A new project sponsor has recently started with the company but has not had time to meet the project manager The project is at the point where the issues are significantly impacting delivery of the project

How should the project manager alert the new project sponsor about these concerns?

Options:

A.  

Send an email invitation to the project sponsor to attend all of the project team's weekly meetings, and hope the sponsor will find time to attend

B.  

Send an email to the project sponsor summarizing the project status and key concerns, and request an immediate face-to-face meeting to discuss them

C.  

Continue emailing updated project status reports highlighting the key risks andissues, and wait for the project sponsor to request a meeting

D.  

Complete a risk analysis outlining the delays and impacts, and email a copy of the risk register, urging the project sponsor to respond

Discussion 0
Questions 536

During the course of a project, the team develops negative group behaviors and becomes unmotivated and unproductive. What should the project manager do to improve the project team's performance?

Options:

A.  

Define and analyze performance metrics

B.  

Escalate poor performance to functional managers

C.  

Update the stakeholder engagement plan

D.  

Conduct a root cause analysis session

Discussion 0
Questions 537

A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned The SME asks the project manager to write, document and include it in the lessons learned register

What should the project manager do?

Options:

A.  

Assign the documenting task to a project team member

B.  

Ask the SME to document and capture the occurrence.

C.  

Request the SME to wait until the project closure phase.

D.  

Take ownership of documenting this information

Discussion 0
Questions 538

During the retrospective ceremony, the agile team is talking about the product owner’s expectations not being met What should the project manager have done at the beginning of the project?

Options:

A.  

Defined the expected agile team contribution in the creation of the backlog.

B.  

Assessed the capabilities of the agile team and planned for the required training

C.  

Defined the team ground rules and shared project vision.

D.  

Communicated project vision and sprint goals clearly to the team

Discussion 0
Questions 539

A new project manager is planning an information security project for a company that resides in different countries. What is the first step the project manager should take to gather customer requirements?

Options:

A.  

Conduct a stakeholder analysis to identify how regional policies may influence needs

B.  

Request relevant stakeholders to conduct an analysis and reach consensus independently

C.  

Conduct a project scope review workshop with relevant stakeholders.

D.  

Conduct project planning meetings in one location with relevant stakeholders

Discussion 0
Questions 540

A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The project manager starts to present the budget but the CEO suddenly asks to end the meeting

What should the project manager have done to avoid this situation?

Options:

A.  

Reviewed the communications management plan before inviting an external client representative to the meeting

B.  

Reviewed the cost management plan with internal participants and CEO prior to inviting an external client representative to the meeting

C.  

Performed a root cause analysis with the external client representative and documented the findings in the lessons learned register

D.  

Sent the presentation slides to internal participants first and then to the external client representative prior to the meeting

Discussion 0
Questions 541

A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.

Which action should the project manager take to improve the team's performance?

Options:

A.  

Set up a training session for all project team members

B.  

Reach out to the functional managers for support

C.  

Speak individually with each project team member about making the needed updates

D.  

Send an email asking all project team members to complete updates at the end of the day

Discussion 0
Questions 542

A project manager at a company is considering a high-performing junior member of the organization to be the new project manager for a current project. What should the project manager do to prepare for a recommendation to senior management?

Options:

A.  

Compile key highlights featuring the team member from the meeting minutes.

B.  

Ask the team member to write a short biography listing their qualifications

C.  

Gather project artifacts that demonstrate the team member's high performance

D.  

Calculate the health of the projects on which the team member has worked

Discussion 0
Questions 543

After the second iteration of a component development project, the project team conducts a retrospective It shows that in the initial phase the project has failed to comply with a product functionality. The planning for this product has a predominantly predictive approach.

Which technique will help the project manager to accelerate the deliverable?

Options:

A.  

Impact mapping

B.  

Rolling wave planning

C.  

Collective code ownership

D.  

Scrum of Scrums

Discussion 0
Questions 544

A project manager for a maintenance project has a contract that is renewed annually The project started 6 years ago After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year

What has happened in this situation?

Options:

A.  

The contract has not been appropriately reviewed by the project team

B.  

The stakeholder engagement plan has not been correctly implemented

C.  

The legal department has not disseminated the law correctly to all staff.

D.  

The project manager does not have enough knowledge on this legal matter

Discussion 0
Questions 545

A project manager is assigned to a project in a company that is transitioning to agile Not all stakeholders believe in the project, and some stakeholders would like the entire project defined and planned out early in the project However the project sponsor needs a quick win to ensure the continuation of the project.

What approach should the project manager use?

Options:

A.  

An agile approach as this would provide working functionality earlier

B.  

A predictive approach as this would please the senior stakeholders

C.  

A hybrid project as this will mitigate stakeholders' concerns.

D.  

A predictive approach as this will show benefits for all stakeholders

Discussion 0
Questions 546

During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope The project manager decided to update the risk register and escalate the opportunity to a higher level

What should the project manager do next with this opportunity?

Options:

A.  

Share this opportunity with another project

B.  

Establish a contingency reserve to support the opportunity

C.  

Further monitor the opportunity

D.  

No more action is required

Discussion 0
Questions 547

The project manager has learned that the project sponsor is unhappy with the development of the project requirements In order to realign the project with the sponsor's expectations, what should the project manager do?

Options:

A.  

Review the project goal diagram with the team.

B.  

Perform a stakeholder evaluation

C.  

Confirm which templates the team should be using

D.  

Review the risk management plan

Discussion 0
Questions 548

A team is currently working on a mobile app solution. During sprint execution, one of the developers requires clarification about the acceptance criteria for a particular task

What should the project manager do to obtain the information required by the developer?

Options:

A.  

Request direction from the project sponsor

B.  

Write an email to the client requesting clarification

C.  

Seek support from the development manager.

D.  

Work with the product owner to clarify the requirement

Discussion 0
Questions 549

A project team with members from many different countries is struggling to cooperate The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase The project is beginning to fall behind schedule

What can the project manager do to move the team to the norming phase?

Options:

A.  

Plan social activities to help foster stronger interpersonal relationships and identify shared goals.

B.  

Speak with the project sponsor about changing the team composition

C.  

Figure out who is behind the issues and apply progressive disciplinary techniques.

D.  

Show the team the schedule impact of their communication issues and encourage them to put their differences aside

Discussion 0
Questions 550

The sponsor is supportive in leveraging agile approaches The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders

What should the project manager do first?

Options:

A.  

Determine which agile software tools will be required to support agile delivery within the organization

B.  

Select a current predictive project define the approach, and provide agile training to execute the remainder of the project

C.  

Start with a pilot project of appropriate complexity and provide agile training to those who are impacted

D.  

Determine how to transform the organization using agile techniques, including organizational training and communications

Discussion 0
Questions 551

During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.

What should the project manager do next?

Options:

A.  

Discuss approval of the change request in the next project meeting

B.  

Perform a risk assessment on the required change request.

C.  

Evaluate the change request against the project scope statement

D.  

Ask the sponsor for more funds to cover the change request

Discussion 0
Questions 552

After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run. What two actions should the project manager take? (Choose two)

Options:

A.  

Prepare the lessons learned from the project phase.

B.  

Obtain official approval on the new process from the various countries

C.  

Send a questionnaire to the project participants and seek their feedback.

D.  

Refer to the communications management plan

E.  

Deliver the project materials to the users and see if they have any comments

Discussion 0
Questions 553

A large project is affecting the neighborhood in which it is located The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline

What two actions should the project manager take'? (Choose two)

Options:

A.  

Send letters to the neighbors and ask them kindly not to disturb the project.

B.  

Set up a meeting with neighborhood representatives to win their cooperation

C.  

Analyze the situation and find out what is causing the neighborhood's negative attitude.

D.  

Ask the customer to extend the project deadline to allow time for conflict resolution

E.  

Ask the mayor of the city to use their authority to stop neighborhood resistance

Discussion 0
Questions 554

A project manager has two projects that are being executed at the same time The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal In addition, the schedule does not have activities that can be overlapped

What should the project manager do?

Options:

A.  

Analyze both projects to determine the most effective use of common resources

B.  

Use resource optimization to justify requesting more resources for the critical project

C.  

Provide schedule optimization training to the project teams to improve their skills.

D.  

Apply fast-tracking techniques to compress the schedule of the critical project

Discussion 0
Questions 555

The project charter was just approved and the project sponsor has given permission to proceed with the project The program manager has confirmed that one of the requested key resources is also needed on another project at the same time This will affect project delivery

What should the project manager do?

Options:

A.  

Pay overtime to key resource to get the work done outside of working hours

B.  

Have a meeting with project manager of the other project to find a resource optimization solution that works for both projects

C.  

Speak with the client to see if the project delivery deadline can be delayed due to resource availability

D.  

Talk to the program manager and about prioritizing this project over other projects so the key resources are available

Discussion 0
Questions 556

Drag the to the correct scenario on the right

Options:

Discussion 0
Questions 557

An agile project team is looking to develop quality standards for a project How should the project manager coach the team?

Options:

A.  

Determine the tools and techniques suitable for the project and ensure that testing is done early and continuously.

B.  

Inform the team that user acceptance testing is required to ensure that the product owner accepts the solution

C.  

Insist that test-driven development is implemented along with the automated testing

D.  

Ensure that the definition of done (DoD) is provided when the product owner agrees that all acceptance criteria have been met for the user story

Discussion 0
Questions 558

During the last sprint review, the mam stakeholder complained that the product was missing many features they had been expecting The project team argued that every increment met the acceptance criteria and was approved by the mam stakeholder The cost performance index (CPI) of the project is 1 15 and the schedule performance index (SPI) is 1.43

What should the project manager do?

Options:

A.  

Ask the project team to perform the modifications since the project budget and schedule can support them.

B.  

Ask the stakeholder to submit a change request to increase the budget and time for the modifications requested

C.  

Explain to the stakeholder that since the acceptance criteria for every increment were met the project can be closed.

D.  

Analyze the reason for the gap in understanding with both sides and negotiate a solution

Discussion 0
Questions 559

The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.

What should the project manager do?

Options:

A.  

Support the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future

B.  

Coach the team on the decision-making process, assuming a risk-averse strategy towards product releasing

C.  

Assume the responsibility for product releases making the final call on when something is ready for customer launch

D.  

Escalate the issue to the sponsor questioning the authority of the key stakeholder regarding the product launch decision

Discussion 0
Questions 560

for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier To stay on schedule, the vendor proposed replacing the sub- supplier's component with a similar part that is different from the one that is stipulated in the project specifications.

What should the project manager do next?

Options:

A.  

Accept the proposed replacement in order to keep procurement activities on track

B.  

Insist on using the component per the project specifications and air freight the equipment to mitigate the delay

C.  

Instruct the vendor to use the part that is compliant with the project specifications and update the schedule

D.  

Consult with a subject matter expert (SME) to see if the proposed change isacceptable

Discussion 0
Questions 561

A project has a very tight delivery schedule. The project is approaching the delivery date, and the project sponsor often sends the project manager alerts to avoid any schedule slippage . The project team has performed at an acceptable level until new, but the project manager wants to ensure that team’s performance level is performance is maintained until the end.

What action should the project manager take to motivate the project team's performance?

Options:

A.  

Award certificates of appreciation to encourage the team

B.  

Inform the team about the delivery pressure from the project sponsor

C.  

Send a formal notice to team members instructing them to maintain performance

D.  

Hire a few temporary team members to help with the additional work.

Discussion 0
Questions 562

During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy What should the project manager share with the key resource?

Options:

A.  

The updated benefits management plan

B.  

The updated scope management plan

C.  

The updated project management plan

D.  

The updated communications management plan

Discussion 0
Questions 563

A research and development department is planning to develop a product that will introduce a new line of business for the organization What should the project manager do to increase the project's chances of success?

Options:

A.  

Plan a working session focusing on the scope, vision, and mission of the initiative

B.  

Start developing the project management plan based on a previous project template from the project management office (PMO).

C.  

Conduct benchmarking to determine the business viability of the initiative

D.  

Conduct an impact analysis of the new initiative to determine how the project should be rolled out

Discussion 0
Questions 564

A project manager for a large multiyear industrial project has a project with diversified stakeholders from various geographical areas. Recently, the project manager encountered an issue with stakeholder engagement

Which two tools should the project manager use to determine the underlying reason for why engagement is not having the planned effect? (Choose two)

Options:

A.  

Five whys

B.  

Communications management plan

C.  

Ishikawa diagrams

D.  

Issue log

E.  

Open-space meetings

Discussion 0
Questions 565

The project manager just started leading a project team from which the previous project manager resigned After a quick evaluation of the project it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule

What should the project manager do?

Options:

A.  

Conduct a meeting with the project team to discuss and address the sources of disagreement

B.  

Inform the stakeholders that the project will be delayed due to previous team management

C.  

Crash the project timeline to ensure the project is back on schedule

D.  

Issue a change request to extend the project schedule based on identified delays

Discussion 0
Questions 566

A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing

What should the project manager review?

Options:

A.  

The project charter and scope statement

B.  

The requirements traceability matrix

C.  

The business requirement documents (BRD)

D.  

The WBS dictionary

Discussion 0
Questions 567

A company starts implementing Scrum About halfway through the first sprint, communication issues develop Some project team members are not in sync with other team members

What is the cause for this communication gap?

Options:

A.  

The project sprint board has not been updated

B.  

Daily standup meetings were not held or enforced

C.  

The project status dashboard has not been updated

D.  

The communications management plan has not been developed

Discussion 0
Questions 568

A new regulation has been approved that will impact the deliverables in the fourth phase of the project The delivery is following an iterative approach and is currently completing the second phase.

What should the project manager do next?

Options:

A.  

Consult with the project sponsor to discuss a cost increase

B.  

Acquire approval for an exception to the implementation of the new regulation.

C.  

Get approval for the additional budget from the steering committee

D.  

Meet with subject matter experts (SMEs) to assess the impact to objectives

Discussion 0
Questions 569

The resource management plan is already done, and the team is located in different countries around the world Team members are in multiple time zones and they use different languages for communication The project manager needs to keep the team organized and avoid misunderstandings and miscommunication that may produce a negative impact to the project

What should the project manager do to reduce negative impacts to the project?

Options:

A.  

Modify the communications management plan to account for regional differences

B.  

Conduct cultural awareness seminars

C.  

Hold a virtual meeting to discuss the political environment.

D.  

Conduct a multigenerational management training session

Discussion 0
Questions 570

A company is implementing a new system The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies The product owner is confused as to how to start delivering the functionalities required

How should the project manager assist the product owner?

Options:

A.  

Coach the product owner on how to create a product backlog

B.  

Encourage the team to subdivide the project tasks

C.  

Create a work breakdown structure (WBS) and explain the deliverables to the product owner

D.  

Discuss the product owner's responsibilities within the project team

Discussion 0
Questions 571

A project manager is in a learn meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change What should the project manager do?

Options:

A.  

Make the decision on behalf of the organization

B.  

Review the stakeholder map along with the organizational chart and delegate the most senior person to make the decision

C.  

Schedule a project decision meeting with all stakeholders to discuss the decision.

D.  

Follow the stakeholder engagement plan

Discussion 0
Questions 572

During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation How should the project manager respond?

Options:

A.  

Tell the junior team member that the information is available in lessons learned

B.  

Offer guidance and follow up with some developmental activity for the junior team member

C.  

Inform the junior team member that risk mitigation is not part of their work

D.  

Refer the junior team member to the senior team member who develops the risk mitigation strategy

Discussion 0
Questions 573

A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings

What is one of the key activities that the project manager should undertake to ensure company success?

Options:

A.  

Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables

B.  

Request more funding from the project sponsor to hire additional skilled resourcesand to incorporate additional quality in the project delivery approach and outcome

C.  

Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions

D.  

Create a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives

Discussion 0
Questions 574

A large corporation is transforming itself from a predictive to agile approach A project team with knowledge of agile practices is experiencing significant conflicts with the executives regarding the processes to be followed.

How should these conflicts be resolved?

Options:

A.  

Include the executives in team retrospectives

B.  

Train the executives on agile practices

C.  

Negotiate with the executives and agree on a process.

D.  

Request that the executives use agile practices

Discussion 0
Questions 575

In an industrial plant, the owner has decided to add more capacity to the plant by installing a new machine and updating the software used in production. This capacity enlargement will occur while the plant is still functioning and producing The software update will be accomplished using an agile approach in order to minimize risk The machine procurement, installation, and integration will be accomplished using predictive approaches

What types of communications will the project manager have to design into the schedule management plan to ensure the project will be on schedule'’

Options:

A.  

Weekly colocated meetings with the relevant stakeholders

B.  

Biweekly conference calls with the relevant stakeholders

C.  

Weekly one-on-one meetings with each of the relevant stakeholders

D.  

Biweekly written status reports from the relevant stakeholders

Discussion 0
Questions 576

An agile project is 25% complete when the product owner changes The new product owner does not show interest in the project s success, and one of the sprints 901 delayed as the deliverable was not approved on time

What should the project manager have done to avoid this delay?

Options:

A.  

Updated the stakeholder engagement plan to reflect a change in the product owner

B.  

Communicated the status of the project more frequently with the product owner

C.  

Updated the communications management plan to reflect a change in the communication needs

D.  

Reevaluated the new product owner's needs for better engagement

Discussion 0
Questions 577

A telecommunications company is doing a national network rollout involving continuously changing technical requirements. To address the situation the company has recently adopted a hybrid project life cycle. During a retrospective some team members complain that me majority of me stones are ready to test but have not advanced because they are waiting for the project manager's approval.

What should the project manager do?

Options:

A.  

Update the issue log and review the lessons learned register for options

B.  

Implement conflict resolution to accommodate the team's needs

C.  

Implement decision-making techniques to advance the stones

D.  

Empower the team to self-organize and make their own decisions

Discussion 0
Questions 578

A project manager is assigned to a project related to taxes, which will be managed

using an agile approach. By reviewing lessons learned from a previous project, the project

manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

Options:

A.  

Recognize the stakeholder's skills are important for the project and evaluate thepossibility of the stakeholder supporting the project team.

B.  

Request the functional manager to assign the team from the lessons learned project tothe current project to avoid a learning curve.

C.  

Ask the project team to review the lessons learned and have the team contact thestakeholder directly if there are any questions.

D.  

Send a request to the project sponsor to hire the stakeholder and have them becomepart of the project team.

Discussion 0
Questions 579

A project manager works at an organization that is transitioning to agile The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.

What should the project manager do to ensure effective communication throughout the project?

Options:

A.  

Advise the project management office (PMO) to use the burndown chart as the single communication channel.

B.  

Develop a communications management plan for each category in the stakeholder register.

C.  

Include the burndown chart in a monthly report that is distributed to all stakeholders.

D.  

Postpone the recommendation since the organization does not currently have a defined agile methodology.

Discussion 0
Questions 580

us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?

Options:

A.  

Review project cost because the project is over budget and ahead of schedule

B.  

Review project schedule and cost because the project is over budget and behind schedule

C.  

Review project schedule because the project is under budget and behind schedule

D.  

Review project scope because the project is under budget and ahead of schedule

Discussion 0
Questions 581

A project manager is executing a project where an external vendor will provide some deliverables Alter awarding the contract to the vendor the project manager is informed that the vendor is running behind schedule on a separate project Finding another vendor will exceed the budget

What should the project manager update first?

Options:

A.  

Issue log

B.  

Lessons learned register

C.  

Stakeholder engagement plan

D.  

Risk register

Discussion 0
Questions 582

A project manager has recently joined a small company. The company's chief

operating officer (COO) asked the team to skip some steps in the process in order to work

more quickly. The project manager wants to ensure that these steps are not skipped in the

future.

What should the project manager do?

Options:

A.  

Notify all team members that all steps in the process must be completed.

B.  

Escalate the issue to the other executive leadership members.

C.  

Schedule a review of the process steps with the team and the COO.

D.  

Redesign the process so the team can move more quickly.

Discussion 0
Questions 583

A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project

How should the project manager report this cost?

Options:

A.  

Estimate user story points and forecast a budget for that deliverable

B.  

Determine the control accounts and use a top bottom estimate

C.  

Consider the cost performance index (CPl) based on earned value (EV) divided by costs

D.  

Calculate the budget at completion (BAC) based on the completed and planned features

Discussion 0
Questions 584

An international client contacted a software development company to build out a

software product, and an agile project manager was assigned. At one of the review meetings,

the client complains that a feature mentioned at the initial debriefing was not implemented.

What should the project manager do?

Options:

A.  

Include the mentioned feature in the prioritized requirements list.

B.  

Assign a team member to immediately start working on that feature.

C.  

Review the original project documentation to confirm.

D.  

Treat it as a change request and assess the effect on the project's goals.

Discussion 0
Questions 585

Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?

Options:

A.  

Update the stakeholder register.

B.  

Refer to the resource management plan.

C.  

Consult the project sponsor.

D.  

Modify the statement of work (SOV).

Discussion 0
Questions 586

A project team Is working on a relative-weighting approach to assess product features. The product features will be prioritized to highlight the benefits and bring value to the customer.

What should the project manager ask the team to do?

Options:

A.  

Perform collaborative work that is coordinated by the project manager.

B.  

Rely on the expert judgment of the product owner.

C.  

Use a market-based strategy.

D.  

Engage the project sponsor.

Discussion 0
Questions 587

An organization's management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team's progress will be hindered by their lack of knowledge.

Which two project events will assist the project manager to ascertain if this is the case? (Choose two)

Options:

A.  

Requirements analysis

B.  

Retrospective

C.  

Sprint planning

D.  

Standup

E.  

Backlog refinement

Discussion 0
Questions 588

A subcontractor informs the project manager that they are unable to supply a key

component to the project. What should the project manager do?

Options:

A.  

Discuss the issue with the project sponsor and request extra time and budget to obtainthe component from a different supplier.

B.  

Raise a new risk in the risk register, perform a risk assessment, and convene SMEs and relevant stakeholders to plan a risk response

C.  

Submit a change request to the change control board (CCB) for changes to theperformance measurement baseline to obtain the component from a different supplier.

D.  

Raise a new issue in the issue log and convene subject matter experts (SMEs) andrelevant stakeholders to identify alternatives to address the problem.

Discussion 0
Questions 589

A developer who has almost completed a required product feature for a prototype

leaves the company in the middle of an iteration. What should the project manager do?

Options:

A.  

Review the backlog to reschedule the deliverable for a later iteration.

B.  

Engage with stakeholders directly to review the iteration process.

C.  

Determine whether other cross-functional team members are able to take over thework.

D.  

Go to management and ask to hire a new external developer.

Discussion 0
Questions 590

A team member has encountered a technical issue similar to the one faced in a successfully closed project However, the team member did not know about the previous project arte would like to resolve the issue on their own

What should the project manager do?

Options:

A.  

Improve the risk management strategy and risk monitoring

B.  

Reach out to the project manager of the previous project for assistance

C.  

Allow the team member to work through the issue as a training opportunity

D.  

Share the lessons learned from the previous protect with the team member

Discussion 0
Questions 591

A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late. Digress into solutioning. or skip the meetings altogether.

How should the project manager improve this situation with the project team?

Options:

A.  

Engage the project team In implementing and Improving key aspects of the standup meetings.

B.  

Ask the product owner to remove team members who do not comply with standup meeting rules.

C.  

Send a daily retrospective report to all team members instead of holding standup meetings.

D.  

Include a daily brainstorming session In the standup meetings to resolve pending Issues.

Discussion 0
Questions 592

A project manager is assigned to a new project and is allocated with virtual team

members. Later, two more members from a recently acquired company join as additional

resources to the project team.

In order to ensure that there are no potential misunderstandings, what should the project

manager do?

Options:

A.  

Send an email update to existing team members about the addition of the new teammembers.

B.  

Set up a weekly meeting with the new team members for a couple of months.

C.  

Request the transfer of the new members to another project, citing a risk of confusion.

D.  

Update and share the guideline document dealing with team communication.

Discussion 0
Questions 593

A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.

What should the project manager do to address this issue?

Options:

A.  

Negotiate the payments with the supplier and remind them of their long-term association

B.  

Penalize the supplier according to the contract's service level agreement (SLA)

C.  

Hire another information security supplier and incentivize them for speedy delivery

D.  

inform the relevant stakeholders of this challenge and seek their support

Discussion 0
Questions 594

A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days

What should the project manager do first to maintain the project team's performance level?

Options:

A.  

Initiate a performance-based bonus for the team members to provide them with a monetary incentive

B.  

Remind the team frequently that the project must be delivered on time and within budget

C.  

Invite the team to a team-building event to alleviate their stress while strengthening teamwork

D.  

Provide routine mentoring and coaching to the team members to identify any demotivating issues

Discussion 0
Questions 595

A project manager is establishing a project management office (PMO) for a

company-wide program to implement a software based on artificial intelligence (AI). As part of the PMO tasks, some stakeholders need help understanding how to deal with difficult situations.

Which activity should the project manager use to help train the stakeholders?

Options:

A.  

Contract negotiation

B.  

Team assessment

C.  

Mentoring and coaching

D.  

On-the-job training

Discussion 0
Questions 596

A company is moving to a hybrid approach and conducted capacity activities for all of the project managers. During these capacity-building activities, the focus was on agile approaches and team facilitation skills. When starting the implementation phase, the project managers faced issues motivating the newly hired agile staff.

Why are the project managers having issues motivating the agile staff?

Options:

A.  

The capacity building activities missed the servant leadership concept transfer.

B.  

Transitional periods normally cause this type of problem.

C.  

The agile staff is not used to being led by a project manager.

D.  

Project managers are expected to become coaches in agile teams.

Discussion 0
Questions 597

After difficult negotiations, a customer committed to pay the cost for changes to the

project scope. The team seems unhappy as the project completion time will take longer than

previously scheduled.

How should the project manager support the outcome of the new agreement?

Options:

A.  

Motivate the team and deploy the necessary resources.

B.  

Find a way to maintain the project schedule.

C.  

Impose authority on the project.

D.  

Request additional resources from the sponsor and motivate the team.

Discussion 0
Questions 598

A project team has been formed and the tasks have been assigned to each team member All team members have agreed to follow a hybrid protect approach. What should the project manager do to ensure the team performs as an organized unit?

Options:

A.  

Advise the team to adjust their work habits and behaviors to allow for better conflict resolution

B.  

Call a team meeting to discuss team members' strengths and weaknesses

C.  

Establish rules and regulations for team members with consequences if the goals are not reached

D.  

Establish team behavior and develop an understating of how to work together

Discussion 0
Questions 599

A company is conducting a digital transformation project that has a hard deadline.

The marketing team wants to combine this implementation with a new product, and the newly

assigned project manager is not aware of all the dependencies.

Using a hybrid approach, what should the project manager do to ensure the dependencies are

taken into consideration?

Options:

A.  

Implement a project newsletter so the different team members can be informed aboutthe progress of each project.

B.  

Combine all of the small projects into one big project so the team can collaboratebetter as one big team.

C.  

Facilitate communication promoting a Scrum of Scrums so the different teams areaware of the dependencies and progress.

D.  

Make sure that each individual project schedule is aligned with the common deadlines.

Discussion 0
Questions 600

A project manager has been assigned lo an important agile project During protect execution, a vendor was approved to produce the project deliverables. What should the project manager do to ensure project continuity between the vendor and the team?

Options:

A.  

Request that the vendor provides a manual with all required knowledge

B.  

Implement retrospectives with the vendor to gather the required knowledge

C.  

Submit a change request to extend the vendor's contract to provide formal training for the team

D.  

Conduct daily knowledge transfer standups to ensure that the team is properly trained

Discussion 0
Questions 601

Two learn members are consistently having misunderstandings and find it difficult to work together. How should the project manager handle this situation?

Options:

A.  

Remove one of the team members

B.  

Identify the issues between the team members and guide them toward a resolution

C.  

Warn the team members about their behavior

D.  

Train the team members on communication techniques and interpersonal behavior

Discussion 0
Questions 602

A project manager is leading the first agile project for the organization. During the

kick-off meeting, the project manager notices that the team does not have the same

understanding about agile approaches. The project manager is concerned about the impact of that confusion.

What should the project manager do to address this situation?

Options:

A.  

Evaluate the possibility of managing this project using a predictive approach.

B.  

Submit a change request for a new team that has agile experience.

C.  

Mentor the team to explain agile principles and create a shared understanding.

D.  

Hire a functional manager who is familiar with agile methodologies.

Discussion 0
Questions 603

A project has recently Kicked off. The project manager observes that thete are different expectations among the project team members. These growing misunderstandings are affecting team productivity.

Which document should the project managefve?

Options:

A.  

Project charter

B.  

Stakeholder register

C.  

Team charter

D.  

Project organization charts

Discussion 0
Questions 604

During the executing phase, a project manager is reviewing the issue log and finds

there are outstanding high-priority issues that are still open. Most of the open issues require

effort from external domain experts who are not on the project team.

What should the project manager do?

Options:

A.  

Ask the issue reporter to close the issues, because there are no project team memberswho have the required domain knowledge.

B.  

Review the open issues with the issue reporter and issue a change request to hire anexternal domain expert.

C.  

Request that the project team members learn the required domain knowledge andresolve the open issues in a short time.

D.  

Reduce the project scope to ensure that the project team has the knowledge to deliverthe system on schedule.

Discussion 0
Questions 605

A team Is experiencing difficulties and has decided to use a spike. Please click on the portion of the burndown chart that corresponds to the spike.

Options:

Discussion 0
Questions 606

A project manager is assigned to a digital transformation project for a bank. The company culture is conservative and resistant to transformation or innovation. What should the project manager do first to support the transformation''

Options:

A.  

Provide a digital transformation guide and explain that the change is unavoidable

B.  

Ask the bank executives to officially announce that the project manager is leading the project

C.  

Provide proper training sessions to the stakeholders so they understand the purpose of the change

D.  

Hire an expert in digital transformation and assign that person as the champion for the change

Discussion 0
Questions 607

A project manager is managing two integrated projects in a program A key integration point is misaligned, which has resulted in delays. One of the team's integration leads is a subject matter expert (SME) m this integration area. The other team's integration lead is not a SME but is more senior and has worked on the project longer Both team leads are blaming each other

What should the project manager do first to resolve this situation?

Options:

A.  

Assign the resolution of the issue to the senior integration lead who has worked on the project longer

B.  

Meet with both integration leads to understand the root cause and determine a resolution

C.  

Escalate the issue to the program architect who developed the integration plan

D.  

Assign the resolution of this issue to the integration lead who is a SME

Discussion 0
Questions 608

On a project with multiple international locations, a trend for delays has been

flagged. When looking into the issue, the project manager realized that some of the key

activities were scheduled over the holiday periods in the overseas offices.

What should the project manager do next?

Options:

A.  

Update the schedule to reflect the holidays and share the workload among offices tomitigate schedule slippage.

B.  

Hire additional personnel on a temporary basis to cover the extra workload during theholiday seasons.

C.  

Request that the offices in overseas locations work overtime to mitigate scheduleslippages.

D.  

Update the schedule to reflect the holidays and notify the project sponsor of thedelayed completion.

Discussion 0
Questions 609

A project manager submits several requests to purchase required hardware and

knows from previous experience that this kind of procurement usually results in disputes

between the company and its suppliers. How can the project manager mitigate this risk in the

request for proposal (RFP) with suppliers?

Options:

A.  

Ask the legal team to review the RFP.

B.  

Ask the project team to submit the RFP.

C.  

Request approval of the RFP from the project sponsor.

D.  

Request approval of the RFP from management.

Discussion 0
Questions 610

During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts

What should the project manager do?

Options:

A.  

Present brainstorming topics a day before the session so the team can reflect and contribute more fully during the session

B.  

Adjust the lighting and ambient sounds in the work and common areas to create a relaxing work atmosphere

C.  

Ensure the team understands that their input needs to be fully articulated and explained to all team members during daily standups

D.  

Require everyone to share personal details at the start of each team meeting to allow learn members to get to know one another

Discussion 0
Questions 611

One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.

What should the project manager do?

Options:

A.  

Assign this member to facilitate the next meeting to ensure project team collaboration.

B.  

Allow each team member to submit their required tasks on time and reduce the number of scheduled meetings.

C.  

Review and update the project ground rules to make meeting attendance mandatory.

D.  

Understand the reason for the team member's absence and encourage them to attend future meetings.

Discussion 0
Questions 612

A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project.

What should the project manager do to address this concern?

Options:

A.  

Ask human resources (HR) to coordinate another activity.

B.  

Reassess the team situation and provide a proper solution.

C.  

Inform HR about the situation and ask for support.

D.  

Meet with the team to explain that conflicts must be addressed and solved.

Discussion 0
Questions 613

The main project stakeholder was fired and replaced by another stakeholder. The

new stakeholder reviewed the project scope and requested numerous changes, arguing that

the stakeholder's team is unhappy with the results to date.

What should the project manager do?

Options:

A.  

Put the new requirements in the backlog with high priority and implement therequested changes.

B.  

Put the new requirements in the backlog and submit a formal change request forapproval.

C.  

Put the new requirements in the backlog and let the product owner check their valueand priority.

D.  

Put the new requirements in the backlog with low priority and implement the requestedchanges.

Discussion 0
Questions 614

A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?

Options:

A.  

Seek the sponsor's approval to extend the project schedule.

B.  

Set up a meeting to perform a root cause analysis.

C.  

Update the issue log and communicate it to the team.

D.  

Permanently colocate the team for better performance.

Discussion 0
Questions 615

A project leader is assigned to a new project and is asked to assemble an effective

five-member agile team. If the project leader has no restrictions, which team should they

choose?

Options:

A.  

A team whose members work independently and are the best subject matter experts(SMES)

B.  

A team whose members have more general aptitudes but like to work individually

C.  

A team whose members have different skill sets and are spread out geographically

D.  

A team whose members have more general aptitudes and can collaborate on different tasks

Discussion 0
Questions 616

A project manager is leading a project that is on time and under budget. In the

weekly meeting with the team, the project manager finds out that one of the tasks due next

week does not have an assigned resource available for it. The resource is currently assigned

to another project.

What should the project manager do to manage the situation?

Options:

A.  

Ask the procurement department to supply a different resource.

B.  

Change the schedule according to the availability of the resource.

C.  

Ask the sponsor to obtain the resource as originally planned.

D.  

Contact the other project manager to request the resource.

Discussion 0
Questions 617

In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet

What should the project team have done to avoid this issue?

Options:

A.  

Held a touchpoint with marketing before the demo to discuss any impediments

B.  

Scheduled a demo presentation of the product during the first reason

C.  

Asked the marketing team to start working on the product immediately

D.  

Confirmed marketing requirements and constraints when adding to the backlog

Discussion 0
Questions 618

A project team that is very experienced in enterprise resource planning (ERP)

systems implementation is currently planning the delivery of a new ERP project. There is a

requirement to reuse the client's security subsystem developed by a third party. The client

states that integration with the security subsystem must be done by the client's team. The

project manager does not want to have such an external dependency.

What should the project manager do first?

Options:

A.  

Plan the implementation of this integration in the first iteration to help reduce risks.

B.  

Record the issue in the issue log and closely manage this dependency.

C.  

Inform the client that the project team will take care of the integration.

D.  

Document the client's responsibility for the integration with the security subsystem.

Discussion 0
Questions 619

A retail company identifies that it is losing sales because customers are not promptly

informed about promotions and sales points. The company needs to react quickly. A project charter is created along with requests to develop a mobile application for the customer. The marketing department has a long list of features to add to the application, but there are no specifications.

Considering the objective to deploy customer value, which project life cycle approach should be chosen?

Options:

Discussion 0
Questions 620

A junior project manager is excited to start working on their first project with a telecommunications company, A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.

Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)

Options:

A.  

Organizational process assets (OPAs)

B.  

Lesson learned registers from past projects

C.  

Historical issue logs

D.  

Project scope statement

E.  

Project management plan

Discussion 0
Questions 621

A project manager is leading an automation project. The project team is colocated

and includes people from both the technical and business units. The project manager

discovers that personal differences and work styles are affecting the project negatively.

How should the project manager address this?

Options:

A.  

Develop a schedule that ensures people with personal differences work separately.

B.  

Use an approach to the project that does not involve colocation.

C.  

Meet with the team and agree on expectations from team members.

D.  

Invite the functional managers of the different units to address their personal differences.

Discussion 0
Questions 622

The marketing team is moving from predictive to hybrid approaches for their projects. The marketing director is not familiar with hybrid approaches and does not support the new direction. What should the project manager do?

Options:

A.  

Advise the marketing director to receive formal training.

B.  

Ask the marketing team members to coach their director.

C.  

Train the marketing team and keep their director informed.

D.  

Mentor the marketing director on the approaches.

Discussion 0
Questions 623

A project has been running successfully for 2 months. At a regular project meeting,

the team raises several potential obstacles to future progress. The obstacles include vendor

delivery performance, technical performance of a subsystem, and conflict with another division of the organization.

What should the project manager do next?

Options:

A.  

Work with the team and others in the network to assess and prioritize the obstacles.

B.  

Engage with the external stakeholders and the other division of the organization toresolve the issues.

C.  

Escalate the obstacles to the project sponsor for assistance with resolution.

D.  

Determine a change response to identify and resolve the obstacles to move the projectforward.

Discussion 0
Questions 624

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped

How should the project manager handle the situation?

Options:

A.  

Remove the items no longer applicable from the backlog and present the backlog to the project team

B.  

Continue working on the defined scope and review the risk matrix

C.  

Have a discussion with the project sponsor and cancel the project

D.  

Have a discussion with the sponsor and recommend the project business value be reassessed

Discussion 0
Questions 625

While working on a poorly defined internal project, a project manager receives

multiple change requests from senior management. What should the project manager do first?

Options:

A.  

Identify how the proposed changes will benefit the project in relation to the businesscase.

B.  

Ask for a temporary budget increase to avoid cost overruns.

C.  

Keep the team motivated and incentivized to avoid exhaustion from working on alengthy project.

D.  

Assess the schedule delay and begin implementation to avoid additional lags

Discussion 0
Questions 626

During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams. As a team facilitator, what should the project manager do to avoid this?

Options:

A.  

Identify the problem's root causes and define the ground rules with all project team members to minimize interferences.

B.  

Recommend to the project team members that they should improve their planning and make their stories smaller.

C.  

Reunite with the project team members affected and tell them not to reduce the team's capacity.

D.  

Hire a coach to help all project teams to improve their abilities to solve problems on their own.

Discussion 0
Questions 627

During the planning for a long project, the project manager recognized that several

members of the team are new to their roles. How should the project manager incorporate this

into planning?

Options:

A.  

Increase the overall project duration to account for the inexperienced team memberson the project.

B.  

Ensure planning has accounted for replacing team members in new project roles whodo not deliver on project goals.

C.  

Assess the training requirements and ensure time for professional developmenttraining by senior members.

D.  

Revisit the project resource allocation to remove the inexperienced team membersassigned to the project.

Discussion 0
Questions 628

A project manager who is working with a virtual team needs to mentor an entry-level colleague. This team member informs the project manager that they feel demotivated and excluded from the team

What should the project manager do first to solve the situation?

Options:

A.  

Speak with the team member about their engagement and contributions

B.  

Perform an assessment of each member of the project team

C.  

Assign the team member to a team where they can contribute more

D.  

Conduct a team building event to involve the team member

Discussion 0
Questions 629

A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.

What should the project manager do to address the concem9

Options:

A.  

Provide team-building activities so that the team can learn how to overcome disruptive behavior

B.  

Inform the disruptive team member's functional manager that the disruptive behavior should be stopped immediately

C.  

Request a meeting with the disruptive team member and help to resolve the issue

D.  

Encourage self-governance and ask the concerned team member to speak to the disruptive team member directly

Discussion 0
Questions 630

A project manager who Is new to an organization is given data that include information related to both project team members and stakeholders. Among other items, this information includes each stakeholder's current role, previous and current projects in which they participated, and their level of organizational influence.

In what type of analysis should the project manager use this information?

Options:

A.  

Regression analysis

B.  

Stakeholder analysis

C.  

Qualitative risk analysis

D.  

Decision tree analysis

Discussion 0
Questions 631

A project manager has been hired to help coordinate an ongoing project Historically the biggest problem as reported by the company's CEO is that the change request process has been handled by managers who did not have dear information on the project schedule and budget. This information has been inconsistent and handled by finance, risk. and functional subject matter experts (SMEs)

What should the project manager do to control this situation?

Options:

A.  

Redefine the communications management plan

B.  

Develop an integrated change management plan

C.  

Document the risk in the project risk register

D.  

Review the scope defined in the project charter

Discussion 0
Questions 632

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable

What should the project manager do to resolve this?

Options:

A.  

Meet with the stakeholder to discuss the impact of the deliverable

B.  

Consider the stakeholder as a risk and evaluate possible solutions with the project team

C.  

Improve communication with the stakeholder to obtain their assistance in the future

D.  

Escalate to the project sponsor due to the political nature of the issue

Discussion 0
Questions 633

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

Options:

A.  

Communicate the task assignments to the team members in a clear manner.

B.  

Verify that the product owner has made the task assignments clear.

C.  

Confirm that the agile coach has made the task assignments clear.

D.  

Verify that the team members have made the task assignments clear.

Discussion 0
Questions 634

A project with multiple teams recently transitioned from a predictive approach to agile

as requested by the product owner. Midway through implementation, a team member noticed

there was no technical capability to support the current business requirement; therefore, the

project will need to be reworked and the issue needs to be communicated to all stakeholders.

What should the agile project lead have done to avoid this situation?

Options:

A.  

Assessed the technical and organizational readiness for the project and identified risksat the beginning of the first iteration

B.  

Requested the product owner's approval to add an external expert to define theacceptance criteria

C.  

Defined a clear acceptance criteria at the initiation phase and continued with theproject

D.  

Increased the communications between the team member and the product owner

Discussion 0
Questions 635

A project manager for an iterative project received feedback from an on-site team member that the virtual team was not meeting the deliverables on time. The project manager gathered details on what the status report should contain m order to track deliverables

What is the remedial action the project manager should take?

Options:

A.  

Perform stakeholder engagement with the virtual team

B.  

Add status reports to the communications management plan

C.  

Convene an on-site meeting for both of the teams

D.  

Add status report creation as a product backlog item

Discussion 0
Questions 636

A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed

To what type of communication is the team member referring?

Options:

A.  

Mass communication

B.  

Push communication

C.  

Pull communication

D.  

Interactive communication

Discussion 0
Questions 637

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?

Options:

A.  

Include additional mitigation actions against feature defects and update the risk management plan.

B.  

Assess the relevance of the feature and then analyze the submission of a change request to descope it.

C.  

Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.

D.  

Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.

Discussion 0
Questions 638

A team member is openly criticized by others during a standup meeting for failing to

complete yesterday's tasks. What should the agile coach do first to address the situation?

Options:

A.  

Emphasize the ground rules and then focus on today's activities and impediments.

B.  

Let the discussion go on as it is important that the team is clear on priorities for theday.

C.  

Address the team members involved during the next sprint retrospective.

D.  

Avoid the discussion by referring to the team charter.

Discussion 0
Questions 639

A project manager is leading a project at a contracting company, and the project

team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.

What should the project manager do to avoid this situation in the future?

Options:

A.  

Manage the scope baseline to influence the factors that drive change.

B.  

Follow the proper change control process and evaluate the change for further impact.

C.  

Work with the customer to ensure the feature adds value.

D.  

Perform frequent reviews with the customer to ensure that the product is working asexpected.

Discussion 0
Questions 640

During the setup of an agile project, the product owner expressed clear interest in

having features released during product development over having the product completed in

one year. What should the project manager do?

Options:

A.  

Promote a productive environment where everybody can work without interruptionsfrom the rest of the team members.

B.  

Create a reward system recognizing group contributions to get people motivated andimprove performance.

C.  

Facilitate sprint planning sessions with a focus on defining the minimum viable product(MVP).

D.  

Design a set of metrics including velocity, which is a good measure of value delivered.

Discussion 0