Which two statements best describe elements of Continuous Delivery? (Choose two.)
The "3 Cs" is a popular guideline for writing user stories. What does each of the three Cs represent? (Choose three.)
The Scrum Master wants to establish a team's initial velocity. A team has two testers, three developers, one full-time Scrum Master, and a Product Owner split between two teams. What is their normalized velocity before calculating for time off?
James is a Product Owner. It is day seven of the Iteration and his team tells him that they may miss their Iteration commitment. What should James do?
Which of the following tools can be used to develop a deeper understanding of what customers are seeing, thinking, and feeling while interacting with the Solution?
The Scrum Master/Team Coach wants to establish a team's initial capacity. The team has two testers, three developers, one full-time Scrum Master/Team Coach, and a Product Owner split between two teams. What is their capacity before calculating for time off?
What is used to capture the current state of the Portfolio and provide input for defining the future state?
Which of the following aspects of the continuous delivery pipeline focuses on getting to production early for verification?
Which of the core competencies of the Lean Enterprise helps align strategy and execution?
Which basic Agile quality practice reduces bottlenecks & ensures consistency?
Which of the following activities occurs during the Inspect and Adapt workshop?
Which of the following principles includes "working software is the primary measure of progress"?
Which three questions should each team member answer during the daily stand-up? (Choose three.)
Are there any impediments that will prevent the team from meeting the Iteration goals?
Which SAFe Lean-Agile Principle includes an emphasis on "deliver early and often"?
Which of the following SAFe Core Competencies of Business Agility includes the Customer Centricity and Design Thinking dimension?
Why do Lean-Agile leaders try to connect the silos of business, software, test, and quality assurance?
Three members of Team C created a new workflow to speed up the testing process. They spent an entire Iteration designing the process but discovered, just before implementation, that the system could not support the workflow. The rest of the team was excited to hear what was learned from the failed experiment. Which of the following characteristics of a high-performing Agile Team is Team C demonstrating?
How does SAFe provide a second operating system that enables Business Agility?
What is typically included in the definition of done for the team increment?
Which of the following activities does SAFe recommend as the first activity of the Inspect and Adapt event?
What represents the workflow, activities, and automation needed to deliver new functionality more frequently?
Which of the following SAFe Agile Team types relies on a continually-refined Team Backlog as the primary input to drive value delivery?
The Lean Thinking principle, "make value flow without interruptions" means identifying what?
Which of the following types of information is shown in a cumulative flow diagram?
3- If the PI System Demo shows the current state of the Solution, then who is this demo intended for?
Which of the following work types is defined as "a short description of a small piece of desired functionality written in the user's language”?
Which team type is organized to assist other teams with specialized capabilities and help them become more proficient in new technologies?
Which of the following statements describes the Release Train Engineer role?
During which of the following PI Planning activities are Business Owners asked to accept the plans?
The analyzing step of the Portfolio Kanban system has a new Epic with a completed Lean business case. What best describes the next step for the Epic?
Which statement is true about the purpose of a work in process constraint?
On day two of PI Planning, management presents adjustments based on the previous day's management review and problem-solving meeting. What is one possible type of adjustment they could make?
A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
Which activity is key to successfully implementing the Scaled Agile Framework?
Which type of decision should remain centralized even in a decentralized decision-making environment?
The Release Train Engineer is a servant leader who displays which two actions or behaviors? (Choose two.)
Which core competency of the Lean Enterprise helps drive Agile Quality practices?