EXIN SIAM Professional Exam Question and Answers

EXIN SIAM Professional Exam

Last Update Sep 17, 2025
Total Questions : 56

We are offering FREE SIAMP Exin exam questions. All you do is to just go and sign up. Give your details, prepare SIAMP free exam questions and then go for complete pool of EXIN SIAM Professional Exam test questions that will help you more.

SIAMP pdf

SIAMP PDF

$42  $104.99
SIAMP Engine

SIAMP Testing Engine

$50  $124.99
SIAMP PDF + Engine

SIAMP PDF + Testing Engine

$66  $164.99
Questions 1

ZYX has implemented a SIAM structure, appointing SIAMRUS as the service integrator.

The SIAM strategy is to consolidate to a smaller number of service providers over time as existing contracts expire Until then. ZYX wants all current service providers to be part of the SIAM ecosystem.

What should ZYX do?

Options:

A.  

Communicate the SIAM strategy and instruct SIAMRUS to speak to all service providers to explain their role

B.  

Draw up a collaboration agreement across all service providers setting out how they will work together

C.  

Put a clause in service provider contracts that SIAMRUS is acting on behalf of ZYX or negotiate themselves

D.  

Write to all the service providers informing them that SIAMRUS has been appointed as the service integrator

Discussion 0
Questions 2

The ZYXS IT Director has proposed to the CIO that ZYXS should be the service integrator in the new SIAM model. The CIO wants to validate if the necessary capabilities exist in ZYXS. The CIO has asked SIAMRUS to perform the assessment.

What is the first activity that SIAMRUS should carry out?

Options:

A.  

Compare the ZYXS service integration capabilities with the SIAM objectives and the target SIAM model

B.  

Assess the existing capabilities of each team in ZYXS and determine if they are at the required maturity

C.  

Identify and then map the stakeholders, process owners and managers for all services across ZYX

D.  

Prepare a heat map to provide a graphical summary of capabilities and show it to the CIO

Discussion 0
Questions 3

ZYX has started the SIAM transition project The project team has recognized that a major factor to success will be managing people through the transition from the current operational model to the future SIAM model. It has been decided to create a dedicated consultation group to formulate the best approach to supporting the staff

Who should best be included in the consultation group?

Options:

A.  

People with HR expertise, and representatives from across ZYX and the providers with the skills and ability to 'sell the ideas' The group needs to represent multiple functions, and could be supplemented with specialist expertise from external contractors.

B.  

Senior representatives from the management boards of all ZYX organizations and their current service providers should form the consultation group This would ensure fair representation for all parties. They would cascade information to the affected staff.

C.  

There is not enough capability to form the group from the existing resources An external organization should be engaged to provide specialists in organizational change management. They would undertake all of the necessary activities throughout the transition.

D.  

ZYXS should be used to form the group as they have well documented processes, job descriptions and skills profiles. Using their expertise to define the future requirements for the SIAM model will enable all staff to understand what will be expected from them

Discussion 0
Questions 4

The SIAM Project Board has decided that the service integrator will be external. The external service integrator has been charged with establishing the governance framework to monitor and measure performance of the ZYX SIAM ecosystem

What will contribute most to the complexity of the governance framework??

Options:

A.  

ZYX's merger with a Japanese competitor

B.  

ZYXD's job descriptions and operating procedures

C.  

ZYXG's IT strategy and local service providers

D.  

ZYXUK’s lack of attendance at the Change Approval Forum

Discussion 0
Questions 5

-ZYX has selected OUTSCO to be the service integrator, provide hosting for the mainframes and servers, and the wide area network for ZYX - ZYXS will provide the service desk for the SIAM ecosystem.

-All other service providers with rolling contracts will continue to provide their services

-The CIO has asked for the development of a tooling strategy for the SIAM ecosystem.

-The CEO wants to achieve an optimum balance between cost and data integrity.

What tooling strategy should ZYX use?

Options:

A.  

All service providers use the OUTSCO toolset or integrate their own toolset with OUTSCO's toolset

B.  

All service providers use the OUTSCO toolset within six months after transitioning to SIAM

C.  

All service providers use the ZYXS toolset or integrate their own toolset with the ZYXS toolset.

D.  

All service providers use their own toolsets and integration will be achieved through re-keying

Discussion 0
Questions 6

ZYX decides to go with SIAMRUS as the service integrator.

The SIAM Project Board has recognized there will be challenges to making the changes required to the attitude and behavior of individuals and the culture of the ZYX companies that are necessary for a successful transition to a SIAM model

What is the best approach that should be taken to ensure success with organizational change management (OCM)?

Options:

A.  

a ngid governance structure should be enforced from the onset of the transition to the SIAM ecosystem to create awareness and to solve the existing problems with service providers having goals or interests that are in conflict with those of ZYX

B.  

As SIAMRUS holds the primary responsibility for OCM on behalf of ZYX, SIAMRUS should actively engage in ADKAR activities from the beginning of the Discovery and Strategy stage. This will avoid organizational uncertainties in the Implementation stage.

C.  

ZYX and SIAMRUS should both focus their OCM activities on relationships and interfaces with new and existing service providers from the beginning of the transition in order to ensure a smooth transition of the service providers into the SIAM ecosystem

D.  

ZYX should commence OCM activities as part of the Plan and Build stage, specifically focusing on weak or missing ADKAR elements This will reduce the nsk of resistance to change and employees reverting to undesired behavior

Discussion 0
Questions 7

The transition to SIAM was completed 12 months ago using a big bang approach. ZYXS is the service integrator

The ZYX Board of Directors set a strategic vision for SIAM to gam control over changes to all IT services within 2 years This is not being achieved and there are issues with the performance of several service providers.

Who should be in the service review board?

Options:

A.  

. The ZYX CEO (chair) and the ZYXS IT Director

B.  

The service delivery directors from each of the service providers

C.  

. The ZYXS service improvement manager (chair)

D.  

The service improvement process owners from each of the service providers

E.  

. The ZYXS IT Director (chair)

F.  

The senior representative from each of the service providers

G.  

. The CAF and the ZYXS Service Management and Service Desk Lead (chair) - The change managers from each of the service providers

Discussion 0
Questions 8

There are many factors that can influence the design of a SIAM model

Which factor will most influence the choice of the SIAM structure for ZYX?

Options:

A.  

Capabilities of the staff working in the ZYX organizations

B.  

Multiple geographical locations of ZYX companies

C.  

The report and proposed SIAM strategy from SIAMRUS

D.  

Willingness of service providers to be part of the SIAM model

Discussion 0
Questions 9

The CEO of ZYX has commissioned SIAMRUS to assess the readiness of ZYX to adopt SIAM. She knows that in order to get approval for the SIAM business case from the Board of Directors, she will have to be able to demonstrate that SIAM will make a significant contribution to the corporate strategic objectives. There is no appetite from the Board for ZYX to use any ZYX staff to provide the service integration capability

Which ZYX strategic objective can SIAM contribute to most for ZYX?

Options:

A.  

Control headcount

B.  

Ensure delivery against contracts

C.  

invest in their people

D.  

Retain existing business

Discussion 0
Questions 10

Project NEWGEN was completed against demanding timescales Because of time pressures, ZYX reduced the scope for testing of the end-to-end processes.

-SIAMRUS is the service integrator and also provider of the service desk for the SIAM ecosystem

-ZYXS is the internal service provider for NEWBNK, which is hosted by OUTSCO

-NETSCO provides the wide area network connecting the OUTSCO data center to the banks using NEWBNK.

Since the transition to SIAM, users of NEWBNK have experienced a significant increase in the time taken to fix incidents The ZYX sales team is now experiencing resistance from customers who were expected to migrate to NEWBNK This is affecting the planned rollout of the new application The ZYX sales team has told the customers that the issues were caused by the providers to ZYX not working together, and not the NEWBNK application itself.

What is the best approach for SIAMRUS to improve the situation?

Options:

A.  

Design and implement a program of organizational change management and skills training with each service provider and measure the success of it

B.  

Implement a new customer marketing campaign focusing on the benefits of NEWBNK and stress that the issues are temporary and will be resolved M|

C.  

Implement Lean systems thinking in each provider to review and optimize the procedures, eliminating waste within the internal activities of the providers

D.  

Use the process forums to mao analyze and improve the end to end processes assigning specific activities to appropriate mdividuals

Discussion 0
Questions 11

The outline SIAM model has been determined.

-ZYXS will be the service integrator

-The development teams from ZYXS and ZYXUK will merge to provide application development and support services

-OUTSCO will provide a centralized service desk the wide area network and local area networks

-ZYXD will provide hosting services

-MAILSCO will provide e-mail services

-MOBSCO will provide desktop support for all users

The strategy is to transfer the current services to these named service providers as the legacy contracts expire The CIO wants to ensure that the tooling strategy supports the corporate strategy

What would be the most appropriate tooling strategy*?

Options:

A.  

The service providers and ZYXS interface their tool with OUTSCO

B.  

The service providp-s .isp the QI .'W.C; tool exr iisivpIv

C.  

The service providers use the ZYXS tool exclusively

D.  

The service providers use the ZYXS tool or use an interface with it

Discussion 0
Questions 12

ZYX has decided to create an internal service provider for application development and support This new service provider is formed by merging relevant staff from every ZYX company with the necessary capabilities and skills.

This internal service provider will operate from multiple locations, which enables the provision of year-round 24-hour support.

A capability framework for application development and support is drawn up for the new internal service provider

What will the development of the capability framework help to address?

Options:

A.  

Establish a process forum for application development and support

B.  

Map skill levels for application development and support roles

C.  

Support effective working between staff in the different locations

D.  

Understand the boundaries and interactions with other service providers

Discussion 0
Questions 13

ZYX has experienced a failure in their finance system leading to the delay of an invoicing run, a resulting temporary cash flow problem, and a breach of the service level for the end-to-end service.

Investigations show that this was caused by a change implemented by NETSCO A change request had been raised but not yet authorized As the NETSCO engineer thought it was urgent, they implemented the change without following the appropriate change processes to obtain authorization.

What is the most appropriate course of action the service integrator should take?

Options:

A.  

Create a service improvement initiative for the treatment of emergency changes

B.  

Impose service credits on NETSCO to compensate for the service level failure

C.  

inform the management of NETSCO and let them deal with it as an operational matter

D.  

introduce a service level target on changes implemented outside of the change control process

Discussion 0
Questions 14

The CEO has asked the IT Director to create a SIAM strategy for ZYX that aligns with the mandate for change and the corporate strategy The CEO wants it as soon as possible.

What should the IT Director do?

Options:

A.  

Adopt the SIAM strategy proposed by SIAMRUS for ZYX

B.  

Adopt the SIAM strategy proposed by SIAMRUS for ZYXUK

C.  

Design a new SIAM strategy ignoring the report from SIAMRUS

D.  

Design a new SIAM strategy using the report from SIAMRUS as input

Discussion 0
Questions 15

ZYXS has been selected as the service integrator. The ZYXS Service Management and Service Desk Lead is the process owner of the change management process. Service providers are allowed to develop their own procedures. The IT Director has asked for a metric for the change management process that aligns with the SIAM principles of measurement

Which is the best metric?

Options:

A.  

Amount of changes not submitted to the CAT on-time

B.  

Consistent achievement of high-quality service provider changes

C.  

Number of normal changes not recorded by the service provider

D.  

Percentage of approved changes achieving the stated outcomes

Discussion 0
Questions 16

OUTSCO is in the final 12 months of their contract with ZYXUK, but they would like to be part of the new SIAM model. However, the quality and performance of services ZYXUK receives from OUTSCO is decreasing

In the new SIAM model, service credits will apply to all service providers ZYXUK has never applied service credits to OUTSCO before

What is the best way to increase the performance of OUTSCO?

Options:

A.  

Apply service credits for the breached SLAs, even though service credits were not previously applied

B.  

Appoint a ZYXUK project manager to take ownership for resolving the provider s performance issues

C.  

Hold reviews between OUTSCO and the ZYXUK service delivery managers to address causes of failure

D.  

Make ZYXUK develop an improvement plan with target dates and measures for OUTSCO to follow

Discussion 0