BICSI Registered Communications Distribution Designer – RCDDv14.1
Last Update Nov 30, 2025
Total Questions : 320
We are offering FREE RCDDv14.1 BICSI exam questions. All you do is to just go and sign up. Give your details, prepare RCDDv14.1 free exam questions and then go for complete pool of BICSI Registered Communications Distribution Designer – RCDDv14.1 test questions that will help you more.
Before working on equipment, what is the FINAL step in the lockout/tagout (LOTO) procedure?
A project's installation start involves a Kickoff Meeting and the General Contractor's Coordination Meeting. As part of the designer's responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)
During the program execution stage the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours. What should the program manager do?
A MINIMUM separation distance of ≈305 mm (12 in) between telecommunication cables and power cables with EMI exceeding 5 kVA is acceptable in which of the following cases?
After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.
What should the program manager do next?
The chief executive officer (CEO) informs the program manager that the delivery dale for protect A must be compressed by two months to accommodate market needs Project A relies upon deliverables from projects B and C.
Which of the following should the program manager do first?
Which two of the following items should be considered for inclusion in a comprehensive working outline of a SoW? (Select two options.)
When considering pathway types, the ICT distribution designer should consider the applicable MICE factors as defined in TIA 568 for structured cabling systems and components MICE 3 relates to
A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.
Which of the following deliverables captures these items?
A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete The program manager can select a design-build option to optimize the construction schedule to 1 5 years However heavy demand for steel is causing price increases and delivery delays. II this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1 25 years
What is the expected time of delivery?
What is the MAXIMUM number of work areas served by a single Multiuser Telecommunications Outlet Assembly (MUTOA)?
During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized the program manager was asked to transition the program into operations.
At this stage, what is expected during the post-review session organized by the program manager?
A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issue.
What should the program manager do NEXT?
A program is developing a next-gene ration product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet
What activity should the program manager perform next?
What category/class of cabling does BICSI recommend for the MINIMUM performance level of horizontal balanced twisted-pair cabling?
An ICT distribution designer is estimating the installation of five units of 1.5 m (5 ft) tong channel basket trays connected together in the ceiling. The total length of the pathway needed is 7 5 m (25 ft). How many supports will be needed''
Which two of the following types of metallic conduit REQUIRE threaded couplings? (Select two options.)
Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule
What should the program manager do?
A program manager concurrently implements a software program at four client locations. The client's objective is to maintain quality while shortening the software implementation timeline
What key elements should be included in the benefits register to achieve this goal?
Near the completion of a transformation program, the operations manager is concerned that their department failed lo be notified in advance of the new service being transitioned into operations. They claim that their department did not approve this service and is now unprepared and untrained to support the transformation.
What should the program manager have done first to prevent this?
A new program component provides an opportunity to enhance program outcomes. What does the program manager use to document and monitor the opportunity'?
A telephone facility and an electrical facility are required in a tunnel. To reduce the effects of EMI and eliminate the need for additional shielding of the cables, where would each facility be placed?
Which two of the following are means in which radiated interference primarily enters electronic devices? (Select two options.)
The MINIMUM required for backbone floor to floor pathways is five (5) sleeves each being 103 mm (four trade size) in diameter What increase in usable floor space should another 103 mm (four trade size) sleeve be added?
A sponsor decides that the business environment is unfavorable for continuation of a program.
The sponsor asks that the program be closed.
What items should be completed as part of the program's final report?
Which of the following is a method that an ICT distribution designer would use for clash detection with other disciplines?
A program manager is appointed to manage a new program. The organization's leadership has specified a list of benefits (hat the program should deliver and has requested that the program manager determine when incremental benefits can be realized.
What should the program manager do first?
A company initiates a program to reorganize its sales and production departments. Three production departments are located at the three production plants next to the company's headquarters Five regional sales departments are located at different locations around the world.
At this stage of the program, what is the first step?
The program director of a four-year program, estimated to require 600.000 person-days effort, notices that team morale has decreased over the last three months. The program is at a critical stage with 70% completion through the last phase. A number of defects are found that result in teams working additional hours. The program director requests that the program management office (PMO) gather metrics to monitor the situation
Which of the following metrics should the PMO capture on a monthly basis?
A company wants to perform a preliminary stakeholder analysis lo assess a new program's support. What should the program manager develop'?
Using an earth ground resistance tester, what is the recommended MAXIMUM value for resistance between any two points along the entire length of a bonding or grounding conductor (not including the earth electrode system)?
Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?
What is used to facilitate MINOR changes to the Project Requirements?
Request lot Information (RFI)
Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?
The program sponsor requests a weekly performance report. The tools and techniques to monitor and control program performance include which of the following?
In preparation for the development and submission of the program master schedule to a client, the program manager meets with (he component project manager and master program scheduler to discuss the work breakdown structure (WBS) During the meeting, the master scheduler indicates that the master program schedule should include which of the following?
Which type of protection for electrical power stations provide isolation against a rise in potential of station ground and also provide drainage protection against longitudinally-induced voltages?
In which of the following design phases does the ICT distribution designer perform coordination with stakeholders and other disciplines (e.g.. mechanical, architectural, electrical) to ensure that the design is constructive and that any conflicts are resolved early in the process?
Which of the following transmitter light sources has a MINIMUM bandwidth of 4700 MHz/km (EMB) at 850 nm">
One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set, if the tolerance range is too narrow on a program what effect will multiple minor changes have on the program?
Stakeholders ask the program manager to assess reasons for the project's delay and provide a report also, the program manager must identify steps to be taken to ensure the program will finish on time and within budget
The program manager distributes information in accordance with which of the following?