Planning & Scheduling Professional (PSP) Exam
Last Update Sep 23, 2025
Total Questions : 163
We are offering FREE PSP AACE International exam questions. All you do is to just go and sign up. Give your details, prepare PSP free exam questions and then go for complete pool of Planning & Scheduling Professional (PSP) Exam test questions that will help you more.
If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?
As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?
When resource leveling craft labor for a critical path schedule, the scheduler
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using
Using the normal schedule, what is the early finish date and total float of Activity 10002?
At the end of month one, did the delay to the parking structure foundation delay the project?
During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?
SUBCO is a potential concrete bridge contractor based in a metropolitan area 300 miles away from your project. They have offered to supply manpower and equipment t BILCO at a per diem rate of $3,000 above their direct labor and equipment rates. In doing a cost benefit analysis, which of the following is NOT a consideration?
Who will receive the most benefit from a master schedule of the Spring Highway project?
Which of the following are NOT considerations or constraints of the planning process for construction scheduling?
Determine the correct formula and date for the late start for the Activity 11001:
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
Which of the following parties is NOT a stakeholder of the Spring Highway project?
Under which circumstance should one perform resource-leveling calculations?
What owner action could have mitigated the late completion of the project?
Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?
Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
For activity 11001. why would the crashed direct cost be greater than the direct cost of the normal schedule?
What day would Activity C complete if the duration of Activity A was reduced by five days?
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?
Which of the following phases does NOT describe the commonly accepted construction life cycle?
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?
Determine the correct formula and date for the late finish for Activity 2002.
When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?