Professional Scrum with Kanban (PSK 1) Exam
Last Update Oct 16, 2025
Total Questions : 73
We are offering FREE PSK-I Scrum exam questions. All you do is to just go and sign up. Give your details, prepare PSK-I free exam questions and then go for complete pool of Professional Scrum with Kanban (PSK 1) Exam test questions that will help you more.
A service level expectation (SLE) consists of which two items?
(choose the best two answers)
What is true about the Sprint Goal if the Developers reserve capacity for unplanned work during
an upcoming sprint?
(choose the best answer)
A Scrum Team's service level expectation (SLE) is an input into the various Scrum events. In
which event will SLE provide the most benefit towards maintaining good flow?
(choose the best answer)
True or False: Limiting Work in Progress (WIP) will likely reduce the amount of collaboration in
the Scrum Team.
Which of these statements about Sprints and Kanban is NOT correct?
(choose the best answer)
Which statements best describe the purpose of a Scrum Team’s Definition of Workflow?
(Choose the best three answers)
True or False: If Scrum is used with Kanban then having a Scrum Master is optional.
When using Kanban, it is useful to have explicit policies. What existing elements in the Scrum Guide might be used as explicit policies?
Upon which of the five Scrum Values does Professional Scrum with Kanban build?
(choose the best three answers)
Which of the following are flow metrics needed when doing Scrum with Kanban?
(choose the best four answers)
What does it mean when a Scrum Team chooses to communicate an 85% 5-day service level expectation (SLE)?
In the context of Scrum, which of the following statements about Cycle Time are true?
(Choose the best two answers)
How do Work in Progress (WIP) Limits relate to self-management?
(choose the best two answers)
You still need a Scrum Master when applying Kanban practices in the Scrum framework.
(choose the best answer)
The Cycle Time metric for a certain Work Item cannot be used:
(choose the best two answers)
What are the two things that constitute a Kanban board?
(Choose the best two answers)
Which of the following is NOT a Kanban for Scrum Teams practice?
(choose the best answer)
True or False: The Scrum framework already contains elements that create a pull system.
Which of the following are lagging indicator metrics?
(choose the best three answers)
When using Kanban in a Scrum environment, some resistance toward introducing Work in Progress (WIP) Limits may be encountered. What is an alternative to introducing WIP Limits in Kanban?