Weekend Special 75% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 75brite

ExamsBrite Dumps

PMI Risk Management Professional (PMI-RMP) Exam Question and Answers

PMI Risk Management Professional (PMI-RMP) Exam

Last Update Aug 24, 2026
Total Questions : 333

We are offering FREE PMI-RMP PMI exam questions. All you do is to just go and sign up. Give your details, prepare PMI-RMP free exam questions and then go for complete pool of PMI Risk Management Professional (PMI-RMP) Exam test questions that will help you more.

PMI-RMP pdf

PMI-RMP PDF

$26.25  $104.99
PMI-RMP Engine

PMI-RMP Testing Engine

$31.25  $124.99
PMI-RMP PDF + Engine

PMI-RMP PDF + Testing Engine

$41.25  $164.99
Questions 1

At the beginning of a small project, the risk manager facilitates workshops to identify and analyze risks. At the end of the sessions, a stakeholder says that there should be no need to meet again about the risk register now that it ' s complete since it is such a short and simple project.

How should the risk manager respond to this comment?

Options:

A.  

The risk register must only be updated if a change is approved during the project.

B.  

Agree on the condition that the risk register be updated if the project environment changes.

C.  

Compromise by updating the risk register at the end of each phase only.

D.  

Insist on continuous review and updating of the risk register during the project.

Discussion 0
Questions 2

The trigger for a highly categorized threat has occurred. The risk has a set response plan.

Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?

Options:

A.  

Product Manager

B.  

Risk Action Owner

C.  

Risk Owner

D.  

Project Manager

Discussion 0
Questions 3

At an oil and gas company, a major unified management information system is to be implemented. The project manager noted that risks gathered from the organization ' s business functions are not properly identified and categorized, making it difficult to develop an effective risk response.

How should the project manager handle this situation?

Options:

A.  

Outsource conducting the risk response plan to risk consultants.

B.  

Ask functional managers to improve their risk register and process.

C.  

Adjust the risk response plans to effectively handle the identified risks.

D.  

Coach the functional groups on how to properly conduct the process.

Discussion 0
Questions 4

When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)

Options:

A.  

Request a contingency reserve from management

B.  

Arrange a team meeting, review the project ' s scope, and discuss dependency mapping

C.  

Ensure participants review relevant documents before attending the meeting

D.  

Ensure that all the relevant stakeholders participate

E.  

Update the risk register during the team meeting.

Discussion 0
Questions 5

A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.

What type of risk is this?

Options:

A.  

Residual risk

B.  

Primary risk

C.  

Secondary risk

D.  

Normal risk

Discussion 0
Questions 6

A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.

What should the risk manager do in this scenario?

Options:

A.  

Review project schedule estimates.

B.  

Change the response strategies.

C.  

Reduce the contingency reserves.

D.  

Conduct a risk planning workshop.

Discussion 0
Questions 7

An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.

What should the risk manager do next?

Options:

A.  

Assess the identified secondary risk.

B.  

Implement the risk response plan.

C.  

Implement the risk contingency plan.

D.  

Communicate the identified residual risk.

Discussion 0
Questions 8

A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?

Options:

A.  

Risk mitigation

B.  

Risk transfer

C.  

Risk acceptance

D.  

Risk avoidance

Discussion 0
Questions 9

A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.

How should the project manager handle stakeholder expectations?

Options:

A.  

Add buffers to the schedule to accommodate risk.

B.  

Ensure the risk register includes all identified risks.

C.  

Discuss the risk response strategies with the stakeholders.

D.  

Develop a communication plan to share updates on risks.

Discussion 0
Questions 10

A project has a S0S4 chance of a US$100 000 profit and a 40% chance of a US$100,000 loss. What is the expected monetary value for this project?

Options:

A.  

US$20.000 loss

B.  

US$20,000 profit

C.  

US$40,000 loss

D.  

US$100,000 profit

Discussion 0
Questions 11

A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long.

What should the risk manager do in this case?

Options:

A.  

Document the risk in the risk register for analysis.

B.  

Document the detailed risk consequences,

C.  

Immediately start the contracting process.

D.  

Proceed with the quantitative risk analysis. 

Discussion 0
Questions 12

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.

How should the risk manager proceed?

Options:

A.  

Perform a qualitative risk analysis and update the results.

B.  

Update the assumptions/exclusions register with the new information.

C.  

Update the risk register and prepare for the Monte Carlo analysis.

D.  

Perform a quantitative risk analysis and update the results.

Discussion 0
Questions 13

Stakeholder holiday schedules and availability of raw materials were two risks initially identified in a manufacturing project. The risk manager now notices that both risks are not quite as originally described and might require a plan change.

What should the risk manager do next?

Options:

A.  

Consult with the project manager to agree that these risks should be removed from the risk register

B.  

Keep the risks in the risk register and continue to follow up until the change actually takes place.

C.  

Identify workarounds that can be implemented whether or not the change takes place.

D.  

Revisit the project the assumptions and constraints to potentially update the risk impact and response. 

Discussion 0
Questions 14

A financial institution is creating a new product database tor their clients. The project sponsor of this project is concerned about failure of the digital platform that hosts the database. The risk manager states that this risk will only occur if there is a major power outage; however, the financial institution has back-up power generators in place.

What type of risk is being referred to here?

Options:

A.  

Major risk

B.  

Residual risk

C.  

Secondary risk

D.  

Environment risk

Discussion 0
Questions 15

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

What should the risk manager do first?

Options:

A.  

Update the new risk in the risk register.

B.  

Plan responses for the new risk.

C.  

Passively accept the new risk.

D.  

Add the new risk to the watch list.

Discussion 0
Questions 16

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.

What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)

Options:

A.  

Develop checklists based on historical information

B.  

Conduct interviews, meetings, and focus groups

C.  

Assign a different risk manager for each portfolio unit

D.  

Employ brainstorming to generate spontaneous ideas

E.  

Perform qualitative and quantitative risk analyses 

Discussion 0
Questions 17

In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.

Which technique is the risk manager using?

Options:

A.  

Variance analysis

B.  

Residual impact analysis

C.  

Sensitivity analysis

D.  

Reserve analysis 

Discussion 0
Questions 18

A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.

What should the project manager do?

Options:

A.  

Avoid the risk

B.  

Transfer the risk

C.  

Ignore the risk

D.  

Accept the risk

Discussion 0
Questions 19

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.

What should the risk manager do next to find out the correct limit?

Options:

A.  

Review the agreed-upon risk tolerance

B.  

Perform a sensitivity analysis of the risk

C.  

Find out the stakeholders’ risk appetite

D.  

Use industry standard risk thresholds

Discussion 0
Questions 20

In reviewing the team ' s identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project ' s incentive payment for early completion.

In implementing this plan, which response should the risk manager use?

Options:

A.  

Exploit

B.  

Accept

C.  

Share

D.  

Enhance 

Discussion 0
Questions 21

A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique.

Which technique should the risk manager use in this situation?

Options:

A.  

Brainstorming

B.  

Delphi method

C.  

Focus group

D.  

Checklist analysis

Discussion 0
Questions 22

A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:

1 = Very Low

2 = Low

3 = Medium

4 = High

5 = Very High

What type of risk analysis is the risk manager performing?

Options:

A.  

Scenario-based risk analysis

B.  

Quantitative risk analysis

C.  

Qualitative risk analysis

D.  

Monte Carlo analysis 

Discussion 0
Questions 23

 

One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.

Which risk response strategy is the program manager using in this scenario?

Options:

A.  

Escalate

B.  

Transfer

C.  

Enhance

D.  

Exploit 

Discussion 0
Questions 24

Many customers using the global positioning system (GPS) of several automobile companies are complaining about errors due to a recent update. This update included a major technological change to mitigate emerging risks with software deployment. Upon investigation, the risk manager realized that this issue was identified as a high-risk item during risk analysis, which required secondary risk identification that was never completed.

What was missed in the risk management process that led to this incident?

Options:

A.  

The identification of the business driver.

B.  

The new technology ' s impact on existing controls

C.  

The risk management strategy quality assurance.

D.  

Project environmental factors

Discussion 0
Questions 25

A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaired.

What type of risk response is this?

Options:

A.  

Transfer

B.  

Accept

C.  

Mitigate

D.  

Avoid 

Discussion 0
Questions 26

A project team in a multinational organization is working on a risk management plan for a multimillion-dollar project. This project involves three global regions with a wide range of critical stakeholders with varying degrees of risk appetite.

What should the risk manager advise the project team to do?

Options:

A.  

Align the project risk thresholds with the risk appetite of a critical region.

B.  

Align the project risk thresholds with the organizational risk appetite.

C.  

Concentrate on the risk appetites of the influential stakeholders.

D.  

Concentrate on the risk appetites of the vulnerable stakeholders. 

Discussion 0
Questions 27

Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.

What should the risk manager do to avoid the previous issues?

Options:

A.  

Use the information for a risk workshop.

B.  

Improve monitoring and controlling of activities.

C.  

Document the issues in the lessons learned.

D.  

Create an issue log to share with the team.

Discussion 0
Questions 28

During a project ' s planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk.

What should the risk manager document as the risk trigger?

Options:

A.  

The probability and impact rating of the supplier ' s delay on the project

B.  

The response strategy, such as increasing inventory or finding an alternative supplier

C.  

The specific event or condition, such as the supplier missing a delivery deadline

D.  

The threshold for acceptable delay, such as a maximum of three days before impacting project milestones

Discussion 0
Questions 29

During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?

Options:

A.  

Contact the risk managers of the other projects and inform them

B.  

Include an escalation process in the risk management plan

C.  

Take note of the extensive impact of these risks in the risk register

D.  

Address the unique characteristics of these risks on a case-by-case basis

Discussion 0
Questions 30

The risk manager of a major project needs to ensure the organizational process assets (OPAsj are updated as a result of risk management activities. How will the risk manager accomplish this?

Options:

A.  

Ensuring that the project sponsor is kept well-informed

B.  

Arranging periodic risk: management process audits

C.  

Communicating the status of risks regularly to stakeholders

D.  

Monitoring costs with intervention when necessary

Discussion 0
Questions 31

During the execution phase of a construction project, a risk response strategy is implemented to mitigate the risk of supply chain disruptions. However, this leads to a secondary risk of increased logistics costs.

What should the risk manager do to address the new risk of increased logistics costs?

Options:

A.  

Accept the increased costs as part of the project ' s risk threshold.

B.  

Develop a contingency plan to cover additional logistics expenses.

C.  

Switch suppliers to potentially reduce logistics expenses.

D.  

Incorporate a cost-sharing arrangement with the suppliers.

Discussion 0
Questions 32

The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin.

The project manager would like the risk manager to take full advantage of opportunities.

Which response should the risk manager take?

Options:

A.  

Mitigate

B.  

Accept

C.  

Transfer

D.  

Exploit

Discussion 0
Questions 33

In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project ' s risk management activities? (Choose 3)

Options:

A.  

By helping to monitor variances and trends frequently throughout the project

B.  

By helping to determine the overall project risks

C.  

By helping the lessons learned from previous risks to be efficiently utilized

D.  

By helping to update the project scope statement document

E.  

By helping update the risk register and close out expired risks 

Discussion 0
Questions 34

A project team is developing a software system for a financial organization and is conducting a failure modes and effects analysis (FMEA) to identify and evaluate potential failure points. The risk manager must guide the team on how to prioritize risks based on FMEA results for effective risk management.

What should the risk manager do?

Options:

A.  

Direct the team to prioritize risks based solely on their likelihood to streamline the analysis.

B.  

Encourage the team to focus on documenting the most severe FMEA risks and disregard others.

C.  

Emphasize technical faults within the system as the highest priority for risk response planning.

D.  

Advise the team to prioritize risks using severity, occurrence, and detection ratings.

Discussion 0
Questions 35

A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.

Which kind of numerical analysis should be performed to understand the worst-case scenarios?

Options:

A.  

Earned value analysis

B.  

Qualitative risk analysis

C.  

Sensitivity analysis

D.  

Root cause analysis

Discussion 0
Questions 36

The stakeholders of a building construction project are not comfortable with the project manager ' s handling of the project as they believe there is a financial risk. The project manager asks the risk manager to assist in demonstrating to the stakeholders that the project risks are under a tolerable threshold.

What should the risk manager do first to demonstrate this to the stakeholders?

Options:

A.  

Gather other project risk historical information.

B.  

Gather and reconcile project risk report data.

C.  

Work with the sponsor to convince the risks are under control.

D.  

Work with the team to ensure the project is in good health. 

Discussion 0
Questions 37

An eco-friendly sustainable textile-dyeing project has begun, with a focus on identifying and managing environmental risks. The risk manager, collaborating with the project manager, is tasked with reviewing and updating the project’s risk management plan. To inform this process, the risk manager needs relevant insights specifically related to environmental risk factors.

What should the risk manager do?

Options:

A.  

Review process documents from Six Sigma to identify areas of process inefficiency.

B.  

Refer to standards for information security management systems to ensure compliance.

C.  

Consult environmental enthusiasts for informal feedback on potential risks.

D.  

Use prompt lists to systematically identify and analyze environmental risk factors.

Discussion 0
Questions 38

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.

What is the current project risk exposure?

Options:

A.  

US$18,000

B.  

US$72.000

C.  

US$30,000

D.  

US$48,000

Discussion 0
Questions 39

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

Options:

A.  

Recommend the removal of risks to the project manager to reduce project risk exposure.

B.  

Advise the client that the project has exhausted contingency.

C.  

Quantify the risk exposure that exceeds project contingency.

D.  

Generate reports to assess and communicate the project risk level.

Discussion 0
Questions 40

During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be

mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.

Which action should the risk manager take to address this risk?

Options:

A.  

Accept the identified risk because other stakeholders feel that there are higher priority risks to address.

B.  

Mitigate the identified risk in order to reduce the probability of impacting the stakeholder ' s team.

C.  

Escalate the identified risk to the project sponsor and allow them to determine the best course of action.

D.  

Add the identified risk to the risk register for future probability and impact analysis.

Discussion 0
Questions 41

The risk manager for a large-scale software development project with a tight deadline and multiple stakeholders highlights concerns about potential delays, communication gaps, and vendor reliability. During the early stages of the project, the project sponsor requests that the risk manager identify and address any potential risks that could disrupt project delivery.

What should the risk manager do?

Options:

A.  

Create a list of potential issues.

B.  

Consult the project management plan.

C.  

Conduct risk management exercises.

D.  

Perform qualitative risk analysis.

Discussion 0
Questions 42

In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.

How should the project manager address this concern with the health authorities?

Options:

A.  

Suspend the project as the secondary risk will negatively impact residents ' health which is not acceptable.

B.  

Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.

C.  

Assess and record associated secondary risks and proceed to treat them as any other risks.

D.  

Proceed with the project as normal since a minor number of residents will be effected negatively.

Discussion 0
Questions 43

A new risk manager has been hired on a project and meets with the project director. The project director supplies the project ' s risk register and asks the risk manager for an analysis of its effectiveness.

What two actions should the risk manager do next? (Choose two.)

Options:

A.  

Check to ensure that the risk is supported by a Monte Carlo simul-ation.

B.  

Check to ensure that the risks are gathered using Delphi technique.

C.  

Check for risk classification and that probability and impact are identified.

D.  

Check to ensure that risk origin, triggering event, and ownership is identified.

E.  

Check to ensure the risk meeting agenda and supporting documents are distributed.

Discussion 0
Questions 44

in a complex and critical project, a sponsor asks the risk manager to determine where the project ' s concentration of risks is greatest by performing a quantitative risk analysis. There are no organizational process assets (OPAs)s about the risk categories.

Which tool could the risk manager use to discover the project risk categories?

Options:

A.  

Work breakdown structure (WBS)

B.  

Affinity diagram

C.  

Monte Carlo simul-ation

D.  

Mind mapping

Discussion 0
Questions 45

A project team is presenting a delivery plan to a client. Some of the client ' s experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.

What should the risk manager do first?

Options:

A.  

Review and update the project quality management plan.

B.  

Conduct a risk assessment process for the critical stage.

C.  

Create a more detailed work breakdown structure (WBS).

D.  

Add additional time to the delivery plan to cover issues.  

Discussion 0
Questions 46

A risk manager is tasked with establishing a risk management strategy for a multinational project with varying regulations and stakeholder priorities. The team is divided on how to approach risk management. Some suggest implementing rigid procedures to ensure consistency across regions, while others advocate for a flexible approach to adapt to the dynamic nature of local risks. Meanwhile, the sponsor emphasizes the need for a strategy that aligns with the overall project objectives.

What should the risk manager do?

Options:

A.  

Implement a strict, standardized approach to ensure consistency across all regions.

B.  

Develop a strategy combining structure with flexibility to address global and local uncertainties.

C.  

Use organizational guidelines to create a strategy that prioritizes efficiency over adaptability.

D.  

Adopt a fully flexible approach that allows teams to manage issues based on local context.

Discussion 0
Questions 47

A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?

Options:

A.  

Develop and employ an Ishikawa diagram

B.  

Analyze the assumptions and constraints

C.  

Perform a review of project documents

D.  

Create prompt lists for expert interviews

Discussion 0
Questions 48

The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?

Options:

A.  

Use the Delphi technique involving experts who have identified opportunities in the past

B.  

Interview more stakeholders who have a positive mindset

C.  

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D.  

Conduct a political, economic, sociological, technological, legal, and environmental (PESTLE) analysis

Discussion 0
Questions 49

A risk manager is conducting a qualitative risk analysis for a renewable energy project that faces tight deadlines. The team identifies risks such as weather unpredictability, material cost fluctuations, and potential regulatory delays. While some members advocate prioritizing high-likelihood risks, others emphasize addressing unlikely but high-impact risks.

What should the risk manager do?

Options:

A.  

Focus on high-probability concerns first to proactively address the most immediate threats.

B.  

Delegate the assessment of lower-priority concerns to team leads while addressing critical ones.

C.  

Evaluate all identified concerns and consider likelihood and impact to prioritize the concerns effectively.

D.  

Prioritize uncertainties that align closely with the project ' s primary deliverables.

Discussion 0
Questions 50

The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date.

What should be the risk manager ' s next step?

Options:

A.  

Check the schedule for constraints

B.  

Use the P90 date on the risk report

C.  

Decrease the number of iterations

D.  

Decrease the risk consequences

Discussion 0
Questions 51

When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.

How does centralizing the risk management function help resolve the problem?

Options:

A.  

Enhance the process of identification of different Individual project risks.

B.  

Allows monitoring the impact against the overall project risk exposure.

C.  

Establishes risk sources and ownership for trigger monitoring.

D.  

Creates a single repository for all project risk documents.

Discussion 0
Questions 52

As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?

Options:

A.  

Close and communicate the results of the risk response actions.

B.  

Run a workshop to analyze the effectiveness of the risk plan.

C.  

Conduct a risk reserve analysis and document the results.

D.  

Verify that all risk response actions have been documented. 

Discussion 0
Questions 53

During the early planning stages of an AI-based software development project, the project team begins outlining the risk management activities. The risk manager notices that key stakeholders, such as data scientists, product owners, and external data vendors, lack a shared understanding of risk management principles.

What should the risk manager do to educate stakeholders?

Options:

A.  

Conduct risk workshops tailored to all stakeholders.

B.  

Invite all stakeholders to daily coordination meetings.

C.  

Distribute risk-policy documents to all stakeholders.

D.  

Provide project management training to all stakeholders.

Discussion 0
Questions 54

The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.

What should the project manager do first?

Options:

A.  

Include the risk in the register and communicate with the stakeholders.

B.  

Communicate with the client to provide the previous shutdown plan.

C.  

Review and update the project schedule.

D.  

Interview the other project manager to learn more details.

Discussion 0
Questions 55

A project team is leading a software development project. During the project kickoff meeting, the risk manager discovers that a vendor has not finalized the timeline for delivering an essential component. This creates uncertainty in the overall project schedule.

What should the risk manager do to address the risk?

Options:

A.  

Hold a meeting to assess the risk ' s impact and create a response plan with alternative timelines.

B.  

Adjust the overall project schedule based on assumptions about the vendor ' s timeline.

C.  

Defer the risk discussion until the vendor finalizes the timeline to prioritize the project ' s start.

D.  

Focus on internal risks and assume the vendor will resolve the issue independently.

Discussion 0
Questions 56

A project team is discussing which risk requires more attention and resources for response planning. The team evaluated the schedule to determine which activity had the greatest impact on the project ' s total duration.

After analyzing the quantitative analysis results, which activity should the team pay more attention to?

Use the chart for the analysis.

Options:

A.  

Activity 3.2

B.  

Activity 2.3

C.  

Activity 3.5

D.  

Activity 1.2

Discussion 0
Questions 57

A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.

How should the risk manager improve collaboration during risk planning?

Options:

A.  

Gather risk information from all parties and compile all submissions into a strength, weaknesses, opportunities, and threats (SWOT) analysis template.

B.  

Create a repository for project documents and related artifacts that can be accessed by all parties.

C.  

Communicate program metrics to all parties and create a scorecard to measure the effectiveness.

D.  

Work with the project manager to develop a start-up workshop and colocate the team if permitted. 

Discussion 0
Questions 58

A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.

What should the risk manager do next with the data set?

Options:

A.  

Perform a probability and impact assessment

B.  

Perform Monte Carlo simul-ations

C.  

Perform a sensitivity analysis

D.  

Perform a risk data quality assessment

Discussion 0
Questions 59

Business rhythm can fluctuate greatly between different industries and vary between companies within the same industry. What should be used 10 determine how often a project ' s risk register should be updated or reviewed in a given year when the project is in an industry with a very high business rhythm?

Options:

A.  

The risk management plan

B.  

The risk triggers

C.  

The risk prioritization criteria

D.  

The portfolio management plan

Discussion 0
Questions 60

A project with impending risks has 12 deliverables as subprojects, which will be executed in three different locations involving multiple stakeholders. What should the risk manager do to organize the prevailing risks?

Options:

A.  

Combine individual and focus groups to identify risks and create the overall risk register.

B.  

Use focus groups to conduct group risk assessments of the project to identify risks.

C.  

Request individual assessments of the project and its deliverables to identify risks.

D.  

Use the external risk assessment of the project and its deliverables to identify risks.

Discussion 0
Questions 61

A highly complex project is about to start Considering that many changes and new information will arise as the work moves forward, key stakeholders are anxious about not addressing risks on time

What should the risk manager do in this situation?

Options:

A.  

Establish a formal and upfront risk identification process.

B.  

Use a detailed and quantitative risk assessment process.

C.  

Create an effective and clear risk communication process.

D.  

Adopt a dynamic and frequent risk management process.

Discussion 0
Questions 62

A risk manager is assigned to a new system deployment project with a strict contractually agreed-on schedule. One of the key risks identified is the availability of experts because many are shared on other strategic projects in the organization.

What should the risk manager do to address this situation?

Options:

A.  

Implement a disciplined tracking method and report to stakeholders accordingly.

B.  

Call for a project team meeting to review risk strategies and make required adjustments.

C.  

Escalate the staffing topic to the sponsor and request more budget for contingencies.

D.  

Revisit the project charter for scope adjustments and sign them off with the customer.

Discussion 0
Questions 63

A project has suffered a big schedule delay and there are still some risks that are close to materializing. The project manager is concerned about communicating this risk level, because the stakeholders might suspend project funding and cancel the project.

How should the risk manager manage the risk level?

Options:

A.  

Communicate risk levels only to the supportive stakeholders.

B.  

Advise the sponsor to meet with the stakeholders to discuss the risk levels.

C.  

Collaborate with the project manager to communicate risk levels to stakeholders.

D.  

Coach the project manager on communicating risk levels to stakeholders.

Discussion 0
Questions 64

After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.

What should the risk manager do to facilitate the sponsor ' s ask?

Options:

A.  

Monte Carlo analysis

B.  

Qualitative risk analysis

C.  

Sensitivity analysis

D.  

Quantitative risk analysis

Discussion 0
Questions 65

In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost.

What should the risk manager do?

Options:

A.  

Document the concern over the potential excessive additional cost.

B.  

Manage the potential excessive additional cost as a new risk.

C.  

Ensure the project sponsor has the risk appetite for the residual risk created by allowing overtime.

D.  

Prepare a detailed response plan for the residual risk with a clear owner and time line to ensure there are no impacts to the project. 

Discussion 0
Questions 66

During project implementation, a risk manager wants to determine the effectiveness of risk response plans and which risk will have an impact on the project outcome. Which analysis should the risk manager do?

Options:

A.  

Perform Pareto analysis.

B.  

Perform sensitivity analysis.

C.  

Perform contingency analysis.

D.  

Perform qualitative analysis.

Discussion 0
Questions 67

A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.

Which data analysis tool should the risk manager use to forecast future performance?

Options:

A.  

Sensitivity analysis

B.  

What-if scenario analysis

C.  

Regression analysis

D.  

Decision tree analysis

Discussion 0
Questions 68

A risk manager has been assigned to a project constructing a chemical laboratory. Unfamiliar with chemical laboratories, the risk manager is unsure of where to start objectively identifying risks.

What should the risk manager do?

Options:

A.  

Import a risk register from other industry chemical laboratories.

B.  

Define chemical laboratory safety risk thresholds.

C.  

Review published operational experience reports.

D.  

Draft threat and opportunity risks that come to mind.

Discussion 0
Questions 69

A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.

What is an effect of adding the correlation to the model?

Options:

A.  

Allows more risks to be included in the model.

B.  

Reduces the project completion duration.

C.  

Increases the standard deviation of the model.

D.  

Increases the probability of correlated activities finishing on time.

Discussion 0
Questions 70

An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?

Options:

A.  

Update the risk register

B.  

Meet with the project ' s stakeholders

C.  

Revise the risk management plan

D.  

Ensure sufficient resources are available

Discussion 0
Questions 71

A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue.

What should the risk manager do?

Options:

A.  

Execute the risk response plan defined for the risk.

B.  

Postpone the software launch to sort out the technical issue.

C.  

Assess the impacts and define the response actions with the subject matter experts (SMEs).

D.  

Meet with the project manager to revisit the project schedule.

Discussion 0
Questions 72

A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?

Options:

A.  

Highlight this situation to the project manager

B.  

Conduct a cost-benefit analysis

C.  

Change the risk response strategy

D.  

Analyze the situation and meet with the risk owner

Discussion 0
Questions 73

A software development project team was preparing for a phased release when an unknown and unexpected risk occurred with potential for delaying one of the features for the planned release. The project team decided to go ahead with the release and address this missing feature at a later date. One of the end users learned about this and strongly opposed the planned release.

What should the risk manager have done to prevent this situation?

Options:

A.  

Engaged the sponsor and informed them of the decision to remove the planned feature.

B.  

Engaged the stakeholders more in risk management activities and decisions to get their buy-in and support.

C.  

Performed proper risk identification at the project outset to ensure this risk was identified and mitigated.

D.  

Created a schedule buffer in the plan to deal with unknown risks if and when they occurred. 

Discussion 0
Questions 74

A project team has just initiated a large project to move an organization ' s headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.

What should the risk manager consider?

Options:

A.  

Aligning with the project manager to hold an open brainstorm session with all stakeholders will suffice.

B.  

The ideal solution is to find alternate documents that provide good visibility on the environment.

C.  

The risk identification process can be carried out as long as the project statement is available.

D.  

Risk evaluation will be challenging without these elements as a frame of reference.

Discussion 0
Questions 75

The project team has correctly identified, assessed, and planned responses for a project ' s risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.

What are two options the risk manager should consult for the analysis? (Choose two.)

Options:

A.  

Proximity dales for open risks

B.  

Backlog of change orders to be submitted to client

C.  

Risks that have materialized and the overall risk profile

D.  

Number of schedule baseline changes approved

E.  

Risks due to the number of claims submitted to the client

Discussion 0
Questions 76

 

During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.

Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)

Options:

A.  

Compatibility

B.  

Urgency

C.  

Usability

D.  

Proximity

E.  

Detectability 

Discussion 0
Questions 77

A web page for weather reports will be online next quarter. During the retrospective, discrepancies were discovered with the customer’s requests and the user experience (UX). There is a disagreement between the product owner and the development team about what may have gone wrong and led to this.

What should the Extreme Programming (XP) coach do to keep the project on track and deliver on time?

Options:

A.  

Release this version and leave changes to be done at the end of the project phase.

B.  

Arrange a workshop where all ideas will be discussed and take corrective actions ensuring value delivery.

C.  

Ask the development team to brainstorm and come up with suggestions that will improve the delivery date.

D.  

Run a spike, identify what went wrong during implementation, and request a change to enhance value delivery.

Discussion 0
Questions 78

A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.

Which technique should the risk manager use?

Options:

A.  

Political, economic, social, technological, legal, and environmental (PESTLE) analysis

B.  

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.  

Decision tree analysis

D.  

Cost-benefit analysis

Discussion 0
Questions 79

A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project ' s technical debt and meet the project deadline.

What should the risk manager advise the project manager to do to address this situation?

Options:

A.  

Immediately hire as soon as the project begins to fall behind schedule.

B.  

Hire as soon as the project metrics trigger a risk response.

C.  

Only hire when it is economically feasible to do so.

D.  

Only hire if risk response is escalated and approved by the stakeholders. 

Discussion 0
Questions 80

A project manager was informed that the testing of the latest component in the project ' s software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.

What should the project manager do next to avoid similar risks?

Options:

A.  

Add contingencies to other tasks to mitigate similar risks.

B.  

Reassess risks with a new assumptions and constraints analysis.

C.  

Review the risk response plan looking for lessons learned.

D.  

Log the event in the issue log and update the project management plan.

Discussion 0
Questions 81

While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?

Options:

A.  

Issue log

B.  

Change log

C.  

Assumption log

D.  

Risk-adjusted back log

Discussion 0
Questions 82

A newly appointed risk manager for a critical project is working with a project team to develop a risk management strategy. One team member suggested creating an influence diagram to help analyze the options, risks, outcomes, and their relationships. Another team member feels the influence diagram is not enough because this project is important and complex.

Which approach should the risk manager take to improve the quality of the project risk analysis?

Options:

A.  

Use brainstorming to identify more possible risks.

B.  

Use a Monte Carlo simulation to identify risks.

C.  

Use a work breakdown structure (WBS) to help analyze risks.

D.  

Use a qualitative or quantitative analysis to analyze identified risks.

Discussion 0
Questions 83

.

A project manager is identifying risks on a project and decides to use a risk checklist to gather historical data accumulated from similar projects. With several different historical project files to choose from, which two pieces of information should the project manager include in their risk checklist? (Choose two.)

Options:

A.  

Budget variance data from previously completed projects.

B.  

Project scope and cost management plans from previous projects.

C.  

Lessons learned from similar completed projects.

D.  

Previous project risks that may be relevant to this project.

E.  

Stakeholder analysis metrics from projects with similar risk profiles.

Discussion 0
Questions 84

A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.

Which risk identification technique should the risk manager use?

Options:

A.  

Prompt lists

B.  

Interviews

C.  

Delphi technique

D.  

Nominal group technique

Discussion 0
Questions 85

A risk manager for a large project has completed documenting the risk management plan. The project is moving from planning to execution.

Which three actions should the risk manager take to ensure the risk management plan remains effective during the project timeframe? (Choose 3)

Options:

A.  

Verify whether or not any identified risks might occur and implement the risk response plan.

B.  

Regularly check and report on the status of risks identified according to their prioritization.

C.  

Monitor the status and oversee execution of the risk response plan for each identified risk.

D.  

Ensure management reserves are sufficient to cover the mitigation plans for all identified risks.

E.  

Allocate and lock in project resources according to the initial risk prioritization for all identified risks.

Discussion 0
Questions 86

A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?

Options:

A.  

Risk assessment criteria

B.  

Project management plan

C.  

Project assumptions

D.  

Risk management plan 

Discussion 0