PMI Risk Management Professional (PMI-RMP) Exam
Last Update Aug 24, 2026
Total Questions : 333
We are offering FREE PMI-RMP PMI exam questions. All you do is to just go and sign up. Give your details, prepare PMI-RMP free exam questions and then go for complete pool of PMI Risk Management Professional (PMI-RMP) Exam test questions that will help you more.
At the beginning of a small project, the risk manager facilitates workshops to identify and analyze risks. At the end of the sessions, a stakeholder says that there should be no need to meet again about the risk register now that it ' s complete since it is such a short and simple project.
How should the risk manager respond to this comment?
The trigger for a highly categorized threat has occurred. The risk has a set response plan.
Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?
At an oil and gas company, a major unified management information system is to be implemented. The project manager noted that risks gathered from the organization ' s business functions are not properly identified and categorized, making it difficult to develop an effective risk response.
How should the project manager handle this situation?
When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)
A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.
What type of risk is this?
A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.
What should the risk manager do in this scenario?
An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.
What should the risk manager do next?
A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?
A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.
How should the project manager handle stakeholder expectations?
A project has a S0S4 chance of a US$100 000 profit and a 40% chance of a US$100,000 loss. What is the expected monetary value for this project?
A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long.
What should the risk manager do in this case?
Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.
How should the risk manager proceed?
Stakeholder holiday schedules and availability of raw materials were two risks initially identified in a manufacturing project. The risk manager now notices that both risks are not quite as originally described and might require a plan change.
What should the risk manager do next?
A financial institution is creating a new product database tor their clients. The project sponsor of this project is concerned about failure of the digital platform that hosts the database. The risk manager states that this risk will only occur if there is a major power outage; however, the financial institution has back-up power generators in place.
What type of risk is being referred to here?
During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.
What should the risk manager do first?
An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.
What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)
In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.
Which technique is the risk manager using?
A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.
What should the project manager do?
A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.
What should the risk manager do next to find out the correct limit?
In reviewing the team ' s identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project ' s incentive payment for early completion.
In implementing this plan, which response should the risk manager use?
A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique.
Which technique should the risk manager use in this situation?
A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:
1 = Very Low
2 = Low
3 = Medium
4 = High
5 = Very High
What type of risk analysis is the risk manager performing?
One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.
Which risk response strategy is the program manager using in this scenario?
Many customers using the global positioning system (GPS) of several automobile companies are complaining about errors due to a recent update. This update included a major technological change to mitigate emerging risks with software deployment. Upon investigation, the risk manager realized that this issue was identified as a high-risk item during risk analysis, which required secondary risk identification that was never completed.
What was missed in the risk management process that led to this incident?
A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaired.
What type of risk response is this?
A project team in a multinational organization is working on a risk management plan for a multimillion-dollar project. This project involves three global regions with a wide range of critical stakeholders with varying degrees of risk appetite.
What should the risk manager advise the project team to do?
Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.
What should the risk manager do to avoid the previous issues?
During a project ' s planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk.
What should the risk manager document as the risk trigger?
During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?
The risk manager of a major project needs to ensure the organizational process assets (OPAsj are updated as a result of risk management activities. How will the risk manager accomplish this?
During the execution phase of a construction project, a risk response strategy is implemented to mitigate the risk of supply chain disruptions. However, this leads to a secondary risk of increased logistics costs.
What should the risk manager do to address the new risk of increased logistics costs?
The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin.
The project manager would like the risk manager to take full advantage of opportunities.
Which response should the risk manager take?
In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project ' s risk management activities? (Choose 3)
A project team is developing a software system for a financial organization and is conducting a failure modes and effects analysis (FMEA) to identify and evaluate potential failure points. The risk manager must guide the team on how to prioritize risks based on FMEA results for effective risk management.
What should the risk manager do?
A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.
Which kind of numerical analysis should be performed to understand the worst-case scenarios?
The stakeholders of a building construction project are not comfortable with the project manager ' s handling of the project as they believe there is a financial risk. The project manager asks the risk manager to assist in demonstrating to the stakeholders that the project risks are under a tolerable threshold.
What should the risk manager do first to demonstrate this to the stakeholders?
An eco-friendly sustainable textile-dyeing project has begun, with a focus on identifying and managing environmental risks. The risk manager, collaborating with the project manager, is tasked with reviewing and updating the project’s risk management plan. To inform this process, the risk manager needs relevant insights specifically related to environmental risk factors.
What should the risk manager do?
An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.
What is the current project risk exposure?
The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?
During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be
mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.
Which action should the risk manager take to address this risk?
The risk manager for a large-scale software development project with a tight deadline and multiple stakeholders highlights concerns about potential delays, communication gaps, and vendor reliability. During the early stages of the project, the project sponsor requests that the risk manager identify and address any potential risks that could disrupt project delivery.
What should the risk manager do?
In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.
How should the project manager address this concern with the health authorities?
A new risk manager has been hired on a project and meets with the project director. The project director supplies the project ' s risk register and asks the risk manager for an analysis of its effectiveness.
What two actions should the risk manager do next? (Choose two.)
in a complex and critical project, a sponsor asks the risk manager to determine where the project ' s concentration of risks is greatest by performing a quantitative risk analysis. There are no organizational process assets (OPAs)s about the risk categories.
Which tool could the risk manager use to discover the project risk categories?
A project team is presenting a delivery plan to a client. Some of the client ' s experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.
What should the risk manager do first?
A risk manager is tasked with establishing a risk management strategy for a multinational project with varying regulations and stakeholder priorities. The team is divided on how to approach risk management. Some suggest implementing rigid procedures to ensure consistency across regions, while others advocate for a flexible approach to adapt to the dynamic nature of local risks. Meanwhile, the sponsor emphasizes the need for a strategy that aligns with the overall project objectives.
What should the risk manager do?
A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?
The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?
A risk manager is conducting a qualitative risk analysis for a renewable energy project that faces tight deadlines. The team identifies risks such as weather unpredictability, material cost fluctuations, and potential regulatory delays. While some members advocate prioritizing high-likelihood risks, others emphasize addressing unlikely but high-impact risks.
What should the risk manager do?
The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date.
What should be the risk manager ' s next step?
When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.
How does centralizing the risk management function help resolve the problem?
As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?
During the early planning stages of an AI-based software development project, the project team begins outlining the risk management activities. The risk manager notices that key stakeholders, such as data scientists, product owners, and external data vendors, lack a shared understanding of risk management principles.
What should the risk manager do to educate stakeholders?
The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.
What should the project manager do first?
A project team is leading a software development project. During the project kickoff meeting, the risk manager discovers that a vendor has not finalized the timeline for delivering an essential component. This creates uncertainty in the overall project schedule.
What should the risk manager do to address the risk?
A project team is discussing which risk requires more attention and resources for response planning. The team evaluated the schedule to determine which activity had the greatest impact on the project ' s total duration.
After analyzing the quantitative analysis results, which activity should the team pay more attention to?
Use the chart for the analysis.
A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.
How should the risk manager improve collaboration during risk planning?
A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.
What should the risk manager do next with the data set?
Business rhythm can fluctuate greatly between different industries and vary between companies within the same industry. What should be used 10 determine how often a project ' s risk register should be updated or reviewed in a given year when the project is in an industry with a very high business rhythm?
A project with impending risks has 12 deliverables as subprojects, which will be executed in three different locations involving multiple stakeholders. What should the risk manager do to organize the prevailing risks?
A highly complex project is about to start Considering that many changes and new information will arise as the work moves forward, key stakeholders are anxious about not addressing risks on time
What should the risk manager do in this situation?
A risk manager is assigned to a new system deployment project with a strict contractually agreed-on schedule. One of the key risks identified is the availability of experts because many are shared on other strategic projects in the organization.
What should the risk manager do to address this situation?
A project has suffered a big schedule delay and there are still some risks that are close to materializing. The project manager is concerned about communicating this risk level, because the stakeholders might suspend project funding and cancel the project.
How should the risk manager manage the risk level?
After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.
What should the risk manager do to facilitate the sponsor ' s ask?
In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost.
What should the risk manager do?
During project implementation, a risk manager wants to determine the effectiveness of risk response plans and which risk will have an impact on the project outcome. Which analysis should the risk manager do?
A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.
Which data analysis tool should the risk manager use to forecast future performance?
A risk manager has been assigned to a project constructing a chemical laboratory. Unfamiliar with chemical laboratories, the risk manager is unsure of where to start objectively identifying risks.
What should the risk manager do?
A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.
What is an effect of adding the correlation to the model?
An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?
A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue.
What should the risk manager do?
A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?
A software development project team was preparing for a phased release when an unknown and unexpected risk occurred with potential for delaying one of the features for the planned release. The project team decided to go ahead with the release and address this missing feature at a later date. One of the end users learned about this and strongly opposed the planned release.
What should the risk manager have done to prevent this situation?
A project team has just initiated a large project to move an organization ' s headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.
What should the risk manager consider?
The project team has correctly identified, assessed, and planned responses for a project ' s risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.
What are two options the risk manager should consult for the analysis? (Choose two.)
During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.
Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)
A web page for weather reports will be online next quarter. During the retrospective, discrepancies were discovered with the customer’s requests and the user experience (UX). There is a disagreement between the product owner and the development team about what may have gone wrong and led to this.
What should the Extreme Programming (XP) coach do to keep the project on track and deliver on time?
A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.
Which technique should the risk manager use?
A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project ' s technical debt and meet the project deadline.
What should the risk manager advise the project manager to do to address this situation?
A project manager was informed that the testing of the latest component in the project ' s software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.
What should the project manager do next to avoid similar risks?
While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?
A newly appointed risk manager for a critical project is working with a project team to develop a risk management strategy. One team member suggested creating an influence diagram to help analyze the options, risks, outcomes, and their relationships. Another team member feels the influence diagram is not enough because this project is important and complex.
Which approach should the risk manager take to improve the quality of the project risk analysis?
.
A project manager is identifying risks on a project and decides to use a risk checklist to gather historical data accumulated from similar projects. With several different historical project files to choose from, which two pieces of information should the project manager include in their risk checklist? (Choose two.)
A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.
Which risk identification technique should the risk manager use?
A risk manager for a large project has completed documenting the risk management plan. The project is moving from planning to execution.
Which three actions should the risk manager take to ensure the risk management plan remains effective during the project timeframe? (Choose 3)
A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?