Big Black Friday Sale 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exams65

ExamsBrite Dumps

PMI Risk Management Professional (PMI-RMP) Exam Question and Answers

PMI Risk Management Professional (PMI-RMP) Exam

Last Update Nov 30, 2025
Total Questions : 264

We are offering FREE PMI-RMP PMI exam questions. All you do is to just go and sign up. Give your details, prepare PMI-RMP free exam questions and then go for complete pool of PMI Risk Management Professional (PMI-RMP) Exam test questions that will help you more.

PMI-RMP pdf

PMI-RMP PDF

$36.75  $104.99
PMI-RMP Engine

PMI-RMP Testing Engine

$43.75  $124.99
PMI-RMP PDF + Engine

PMI-RMP PDF + Testing Engine

$57.75  $164.99
Questions 1

The project manager wants to use an objective method to evaluate the key project risks and develop response plans.

What action should the risk manager propose?

Options:

A.  

Ask the team to perform an earned value analysis.

B.  

Review the lessons learned from other projects.

C.  

Ask the team to prepare a Monte Carlo analysis.

D.  

Ask the risk expert to perform a PESTLE evaluation.

Discussion 0
Questions 2

A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.

Who should the project manager hold accountable for missing the risks?

Options:

A.  

The audit team

B.  

The risk manager

C.  

The risk owners

D.  

The discipline engineers

Discussion 0
Questions 3

A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?

Options:

A.  

Risk assessment criteria

B.  

Project management plan

C.  

Project assumptions

D.  

Risk management plan 

Discussion 0
Questions 4

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.

What should the risk manager do first to understand the impact on project cost?

Options:

A.  

Conduct a subject matter expert (SME) meeting.

B.  

Perform qualitative analysis.

C.  

Prioritize after quantitative analysis

D.  

Prioritize the stakeholders affected.

Discussion 0
Questions 5

A risk manager is preparing the risk strategy for a strategic project, which involves stakeholders based in multiple locations. What should the risk manager do at this stage?

Options:

A.  

Update the risk communications plan to include all stakeholders.

B.  

Define the risk processes and tools to be adopted.

C.  

Update the risk register to include this stakeholder-related risk.

D.  

Refine the risk assumptions and criteria to be used.

Discussion 0
Questions 6

In reviewing the team's identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project's incentive payment for early completion.

In implementing this plan, which response should the risk manager use?

Options:

A.  

Exploit

B.  

Accept

C.  

Share

D.  

Enhance 

Discussion 0
Questions 7

A project to deploy a new technology in field offices across the country has just been initiated. Some stakeholders are not supportive of this project because their teams will potentially be impacted by staff reductions once the technology is implemented.

How should the risk manager address this concern?

Options:

A.  

Invite these stakeholders to regular meetings to engage them in the definition of project assumptions.

B.  

Identify new stakeholders who might replace those involved thus far and are more closely aligned to the project goals.

C.  

Review the risk thresholds to potentially accommodate the concerns raised by these stakeholders.

D.  

Perform a stakeholder analysis to determine their interests and how they should be taken into account. 

Discussion 0
Questions 8

In the middle of a construction project, the primary construction materials provider canceled the contract and moved to a competitor offering a higher price. The risk manager considers

this a low-impact issue because many construction materials providers can fulfill the project demands. However, after informing the stakeholders of this issue, the major investor is about

to drop their intention to continue executing the project. The risk manager does not understand their decision.

What should the risk manager do next to understand the major stakeholder's decision regarding the project?

Options:

A.  

Perform a risk impact analysis.

B.  

Perform a risk reserve analysis.

C.  

Perform a procurement analysis.

D.  

Perform a stakeholder impact and influence analysis.

Discussion 0
Questions 9

While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?

Options:

A.  

Issue log

B.  

Change log

C.  

Assumption log

D.  

Risk-adjusted back log

Discussion 0
Questions 10

A project has a significant impact on an organization. Multiple stakeholders expressed concerns regarding the overall project risk during construction of the risk management plan, and they agreed that the risk appetite is low.

What should the project risk manager monitor closely?

Options:

A.  

Risk thresholds

B.  

Risk response strategies

C.  

Risk management reports

D.  

Risk breakdown structure (RBS)

Discussion 0
Questions 11

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

Options:

A.  

Recommend the removal of risks to the project manager to reduce project risk exposure.

B.  

Advise the client that the project has exhausted contingency.

C.  

Quantify the risk exposure that exceeds project contingency.

D.  

Generate reports to assess and communicate the project risk level.

Discussion 0
Questions 12

During a project meeting, the project sponsor asks to close a project risk. The team does not recommend closing the risk because it is expected to be present in the next phase of the project work.

How should the risk manager address this concern?

Options:

A.  

Compare the actual data with the historical data.

B.  

Compare the actual data with the subject matter expert (SME) criteria.

C.  

Compare the actual data with the risk baseline.

D.  

Compare the actual data with the project sponsor's expectation.

Discussion 0
Questions 13

When should the benefits of quantitative risk analysis be weighed against the effort required to ensure that the additional insights and value justify the extra effort?

Options:

A.  

During the Plan Risk Management process

B.  

Once all individual risks have been scored

C.  

After risks have been identified by stakeholders

D.  

Once the overall project risk has been estimated

Discussion 0
Questions 14

A project has suffered a big schedule delay and there are still some risks that are close to materializing. The project manager is concerned about communicating this risk level, because the stakeholders might suspend project funding and cancel the project.

How should the risk manager manage the risk level?

Options:

A.  

Communicate risk levels only to the supportive stakeholders.

B.  

Advise the sponsor to meet with the stakeholders to discuss the risk levels.

C.  

Collaborate with the project manager to communicate risk levels to stakeholders.

D.  

Coach the project manager on communicating risk levels to stakeholders.

Discussion 0
Questions 15

The project manager leading a company's digital signature initiative for engineering drawings has identified threats and opportunities using a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

What are two potential threats or opportunities under the SWOT analysis? (Choose two.)

Options:

A.  

The management team agreeing to include more resource for the digital signature initiative.

B.  

The organization's professional engineers having reservations about possible information tampering.

C.  

A growing number of competitors with digital signatures.

D.  

An elimination of manual steps associated with recording wet signatures

E.  

The growing adoption of mobile communications in the industry.

Discussion 0
Questions 16

 

One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.

Which risk response strategy is the program manager using in this scenario?

Options:

A.  

Escalate

B.  

Transfer

C.  

Enhance

D.  

Exploit 

Discussion 0
Questions 17

A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?

Options:

A.  

Execute the security risks contingency plan.

B.  

Get a report of customers affected by the risk.

C.  

Identify residual and secondary risks.

D.  

Coordinate a response with the risk owner.

Discussion 0
Questions 18

A risk manager for a new product development project has worked diligently with stakeholders and the project team to identify and document risks. These project risks vary widely in probability and impact.

Which three actions should the risk manager take to inform the identification of resource requirements for individual risk responses? (Choose 3).

Options:

A.  

Work with the project team to conduct a decision tree analysis for each risk or set of related risks.

B.  

Calculate the expected monetary value (EMV) of each risk and use these outputs to inform and defend project reserves.

C.  

Conduct a Monte Carlo simul-ation to understand the probabilities of various risk outcomes.

D.  

Use the risk breakdown structure (RBS) to calculate the total cost of mitigating all risks and ensure project reserves are adequate to cover this amount.

E.  

Focus attention and resources on identified risks with the highest potential to impact the project.

Discussion 0
Questions 19

What is an example of legal and regulatory requirements and/or constraints when assessing a project environment for threats and opportunities?

Options:

A.  

Organizational communication requirements

B.  

Organizational standard policies, processes, and procedures

C.  

Formal knowledge sharing and information sharing procedures

D.  

Confidentiality of project information

Discussion 0
Questions 20

After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.

What should the risk manager do to facilitate the sponsor's ask?

Options:

A.  

Monte Carlo analysis

B.  

Qualitative risk analysis

C.  

Sensitivity analysis

D.  

Quantitative risk analysis

Discussion 0
Questions 21

A risk manager is preparing risk reports to be included in the monthly status report for project executives. How should the risk manager present the information?

Options:

A.  

Earned value management (EVM) variance metrics

B.  

A risk burndown chart showing remaining risks

C.  

The format established in the risk management plan

D.  

An itemized list of remaining risks and their scores 

Discussion 0
Questions 22

After completing the sprint on an agile project, a team updates the risk burndown chart and notices that risk exposure has increased to levels that could negatively affect project completion. What should the risk manager do to return the project's risk exposure to an acceptable level?

Options:

A.  

Update the definition of done (DoD) to improve risk management.

B.  

Review the acceptance criteria for upcoming stories.

C.  

Prioritize risk mitigation stories for the next sprint.

D.  

Check stories in the product backlog to identify risks.

Discussion 0
Questions 23

A risk manager is reviewing documentation for a project following a risk planning workshop with project stakeholders and team members. Several items have been identified on the risk log that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.

Which response should the risk manager recommend for these risk items?

Options:

A.  

Mitigate

B.  

Accept

C.  

Enhance

D.  

Exploit

Discussion 0
Questions 24

The risk manager for a large-scale software development project with a tight deadline and multiple stakeholders highlights concerns about potential delays, communication gaps, and vendor reliability. During the early stages of the project, the project sponsor requests that the risk manager identify and address any potential risks that could disrupt project delivery.

What should the risk manager do?

Options:

A.  

Create a list of potential issues.

B.  

Consult the project management plan.

C.  

Conduct risk management exercises.

D.  

Perform qualitative risk analysis.

Discussion 0
Questions 25

A project manager for a large product development project assigned a risk manager to perform the risk management. The project sponsor questions why this project requires a risk manager as it is similar to a previous project with a developed risk strategy.

How should the risk manager explain the need for a risk strategy specific to this project?

Options:

A.  

A risk strategy is a best practice and ensures quality in the project planning.

B.  

A project specific risk strategy includes enough information to respond to audits and compliance requirements.

C.  

A risk strategy ensures alignment of the organizational structure to the specific project.

D.  

A risk strategy aligns individual project risk thresholds with organizational risk appetite. 

Discussion 0
Questions 26

A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (Choose two.)

Options:

A.  

Risks that are tied to the success of the organization

B.  

Risks as they apply to the organization's overall risk management philosophy and strategic ambition

C.  

Huge opportunities that possibly bring an additional 30% return for 10 projects in the next year

D.  

Risks related to cost that will impact the major projects that are currently in the execution phase

E.  

Risk mitigation actions that will require work from stakeholders

Discussion 0
Questions 27

Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.

What will help calculate the impact?

Options:

A.  

Risk analysis

B.  

Risk identification

C.  

Risk treatment

D.  

Risk evaluation

Discussion 0
Questions 28

A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks.

How should the project manager work with these risk handling strategies?

Options:

A.  

Review and revise the strategies periodically.

B.  

Implement the strategies after completing the risk analysis.

C.  

Implement the strategies immediately.

D.  

Ensure the strategies are approved by the stakeholders.

Discussion 0
Questions 29

it typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours.

Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?

Options:

A.  

4 hours

B.  

5 hours

C.  

6 hours

D.  

12 hours

Discussion 0
Questions 30

During a project's initial planning session, the project team identifies a possible risk. The team is under the impression that a critical vendor might delay delivery. This could impact both the project schedule and budget. The team shares insights on the risk's likelihood and impact with the risk manager.

What should the risk manager do?

Options:

A.  

Assume the vendor will deliver on time and focus only on internal risks.

B.  

Allocate contingency funds without first evaluating the risk's probability and impact.

C.  

Wait indefinitely for the vendor's update before analyzing the risk.

D.  

Assess the risk using a probability-impact matrix and prioritize it based on its score.

Discussion 0
Questions 31

A risk manager monitors risks on a medium-sized project by collecting inputs and data from individual project team members. What output is produced by the risk manager after analyzing the information they receive?

Options:

A.  

Updated probability and impact matrix

B.  

Updated risk register

C.  

Updated mitigation plans

D.  

Updated project schedule 

Discussion 0
Questions 32

At an oil and gas company, a major unified management information system is to be implemented. The project manager noted that risks gathered from the organization's business functions are not properly identified and categorized, making it difficult to develop an effective risk response.

How should the project manager handle this situation?

Options:

A.  

Outsource conducting the risk response plan to risk consultants.

B.  

Ask functional managers to improve their risk register and process.

C.  

Adjust the risk response plans to effectively handle the identified risks.

D.  

Coach the functional groups on how to properly conduct the process.

Discussion 0
Questions 33

The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date.

What should be the risk manager's next step?

Options:

A.  

Check the schedule for constraints

B.  

Use the P90 date on the risk report

C.  

Decrease the number of iterations

D.  

Decrease the risk consequences

Discussion 0
Questions 34

A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?

Options:

A.  

Evaluate any new risks that are introduced due to the change in scope.

B.  

Update the risk management plan to reflect the scope change.

C.  

Reassess the identified risks that impact the project scope.

D.  

Update the risk register to identify, analyze, and plan a response for any new risk.

Discussion 0
Questions 35

When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)

Options:

A.  

Request a contingency reserve from management

B.  

Arrange a team meeting, review the project's scope, and discuss dependency mapping

C.  

Ensure participants review relevant documents before attending the meeting

D.  

Ensure that all the relevant stakeholders participate

E.  

Update the risk register during the team meeting.

Discussion 0
Questions 36

A new project is about to start, and the risk manager wants to review some documents that could be relevant for risk identification. Which document will help the risk manager in this process?

Options:

A.  

Detailed work breakdown structure (WBS)

B.  

Lessons learned from previous projects

C.  

Baselines approved by the project team

D.  

Actual data from the current project

Discussion 0
Questions 37

Project stakeholders can often be risk averse with little to no knowledge of the risk process. How should a risk manager increase stakeholder risk appetite?

Options:

A.  

Exclude risk averse stakeholders from future risk discussions

B.  

Explain risk handling and mitigation strategies

C.  

Increase the impact of all risks in the risk breakdown structure (RBS)

D.  

Develop a generous probabilistic cash flow model

Discussion 0
Questions 38

An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.

What should the risk manager do next?

Options:

A.  

Add only the threats to the risk register

B.  

Utilize different tools to identify the risks

C.  

Plan risk responses to the threats

D.  

Update the risk register with the identified risks

Discussion 0
Questions 39

What should the risk owner use as an effective information-gathering technique during the planning session?

Options:

A.  

Monte Carlo analysis

B.  

Update risk register

C.  

Brainstorming

D.  

Cost and time estimating

Discussion 0
Questions 40

A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen.

What should the risk manager do first?

Options:

A.  

Perform an assumptions and constraints analysis.

B.  

Use the Wideband Delphi method.

C.  

Use the brainstorming technique.

D.  

Perform a strength, weaknesses, opportunities, and threats (SWOT) analysis. 

Discussion 0
Questions 41

A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.

Which kind of numerical analysis should be performed to understand the worst-case scenarios?

Options:

A.  

Earned value analysis

B.  

Qualitative risk analysis

C.  

Sensitivity analysis

D.  

Root cause analysis

Discussion 0
Questions 42

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.

How should the risk manager interpret such a low CPI value?

Options:

A.  

The cost control processes is ineffective.

B.  

The cost baseline is inaccurate.

C.  

The actual reported costs are inaccurate.

D.  

The cost related risks are effectively managed.

Discussion 0
Questions 43

Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do?

Options:

A.  

Reduce the probabilities of those risks on the risk register

B.  

Transfer ownership of those risks to the customer

C.  

Implement the risk handling strategies for those risks

D.  

Request additional management reserve for those risks

Discussion 0
Questions 44

A risk manager is integrated into a team overseeing a crucial software development project. During the information gathering phase, the risk manager notices significant weaknesses in the maturity of the risk management process. The team needs to establish a more structured approach to managing risks, including the documentation of strategies, ownership structures, and details about the organization's project risk baseline.

What should the risk manager do?

Options:

A.  

Prioritize the risk management plan.

B.  

Arrange the risk mitigation plan.

C.  

Create a risk action plan with risk owners.

D.  

Prioritize the risk register.

Discussion 0
Questions 45

The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk.

What should the team perform in this scenario?

Options:

A.  

Quantitative risk analysis

B.  

Risk response planning

C.  

Monitor and control risks

D.  

Risk urgency assessment

Discussion 0
Questions 46

At the beginning of a small project, the risk manager facilitates workshops to identify and analyze risks. At the end of the sessions, a stakeholder says that there should be no need to meet again about the risk register now that it's complete since it is such a short and simple project.

How should the risk manager respond to this comment?

Options:

A.  

The risk register must only be updated if a change is approved during the project.

B.  

Agree on the condition that the risk register be updated if the project environment changes.

C.  

Compromise by updating the risk register at the end of each phase only.

D.  

Insist on continuous review and updating of the risk register during the project.

Discussion 0
Questions 47

During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict.

How should the risk manager handle this situation?

Options:

A.  

Request for a skilled facilitator to help resolve conflicts that have arise.

B.  

Refer to the team’s ground rules on how to resolve conflicts.

C.  

Run a sensitivity analysis to check which risks have the most impact.

D.  

Use the assumption analysis techniques to validate the assumptions.

Discussion 0
Questions 48

While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

What should the project manager do next?

Options:

A.  

Identify secondary or residual risks for associated risk plans.

B.  

Develop risk response plans for all identified risks.

C.  

Update the communications management plan to avoid future issues

D.  

Monitor and control secondary and residual risks in the risk register.

Discussion 0
Questions 49

In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost.

What should the risk manager do?

Options:

A.  

Document the concern over the potential excessive additional cost.

B.  

Manage the potential excessive additional cost as a new risk.

C.  

Ensure the project sponsor has the risk appetite for the residual risk created by allowing overtime.

D.  

Prepare a detailed response plan for the residual risk with a clear owner and time line to ensure there are no impacts to the project. 

Discussion 0
Questions 50

Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.

What should the risk manager do to avoid the previous issues?

Options:

A.  

Use the information for a risk workshop.

B.  

Improve monitoring and controlling of activities.

C.  

Document the issues in the lessons learned.

D.  

Create an issue log to share with the team.

Discussion 0
Questions 51

In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.

Which technique is the risk manager using?

Options:

A.  

Variance analysis

B.  

Residual impact analysis

C.  

Sensitivity analysis

D.  

Reserve analysis 

Discussion 0
Questions 52

Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager's company.

How should the project manager address this concern?

Options:

A.  

Evaluate the risk with the team and update the issueing

B.  

Discuss the concern with the local business owners.

C.  

Update the key risks and perform a quantitative risk analysis.

D.  

Adjust construction work hours to after business hours.

Discussion 0
Questions 53

A project team has failed to complete an important project milestone on time. The team was counting on an external provider to deliver key equipment on a specific date but the provider was delayed.

What should the risk manager have done to prevent missing the milestone?

Options:

A.  

Better schedule monitoring and controlling.

B.  

Identify and analyze project plan assumptions.

C.  

Have a detailed work breakdown structure (WBS).

D.  

Use management reserves to cover delays.

Discussion 0
Questions 54

A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

Options:

A.  

Review potential next steps with the project team.

B.  

Review the scope of work to determine the prescribed project methodology.

C.  

Review the policies and practices that are outlined in the risk management plan.

D.  

Review the contract and determine the resources and project funding.

Discussion 0
Questions 55

A risk manager is conducting a qualitative risk analysis for a renewable energy project that faces tight deadlines. The team identifies risks such as weather unpredictability, material cost fluctuations, and potential regulatory delays. While some members advocate prioritizing high-likelihood risks, others emphasize addressing unlikely but high-impact risks.

What should the risk manager do?

Options:

A.  

Focus on high-probability concerns first to proactively address the most immediate threats.

B.  

Delegate the assessment of lower-priority concerns to team leads while addressing critical ones.

C.  

Evaluate all identified concerns and consider likelihood and impact to prioritize the concerns effectively.

D.  

Prioritize uncertainties that align closely with the project's primary deliverables.

Discussion 0
Questions 56

Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project’s success and do not believe that the benefits are significant.

What should the risk manager do?

Options:

A.  

Schedule a meeting to review and develop realistic risk thresholds with the project team.

B.  

Motivate and influence the project team with risk engagement activities like workshops.

C.  

Ensure that risk management responsibilities are clearly identified in the risk management plan.

D.  

Ensure that the risk language used by all stakeholders is consistent with the risk management plan.

Discussion 0
Questions 57

The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.

What should the project manager do?

Options:

A.  

Implement the risk response strategies into the risk plan.

B.  

Inform the sponsor that these risks should be added according to experience.

C.  

Add the risks to the risk register and determine a contingency.

D.  

Discuss and evaluate the identified risks with the project team.

Discussion 0
Questions 58

A financial institution is creating a new product database tor their clients. The project sponsor of this project is concerned about failure of the digital platform that hosts the database. The risk manager states that this risk will only occur if there is a major power outage; however, the financial institution has back-up power generators in place.

What type of risk is being referred to here?

Options:

A.  

Major risk

B.  

Residual risk

C.  

Secondary risk

D.  

Environment risk

Discussion 0
Questions 59

A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?

Options:

A.  

Highlight this situation to the project manager

B.  

Conduct a cost-benefit analysis

C.  

Change the risk response strategy

D.  

Analyze the situation and meet with the risk owner

Discussion 0
Questions 60

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

What should the risk manager do first?

Options:

A.  

Update the new risk in the risk register.

B.  

Plan responses for the new risk.

C.  

Passively accept the new risk.

D.  

Add the new risk to the watch list.

Discussion 0
Questions 61

There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders, and this delays the decision-making process.

Options:

A.  

Organize training sessions to create awareness around the agile values for stakeholders.

B.  

Facilitate a face-to-face discussion and have stakeholders agree to shift to agile for future projects.

C.  

Recommend an external facilitator as no one in the organization is able to eliminate this roadblock.

D.  

Allow stakeholders to discuss without the scrum master's intervention.

Discussion 0
Questions 62

A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of delivering the solution on time and within budget, as this project could lead to significant future opportunities. The risk manager recognizes that the team lacks a standardized approach to managing risks and that some team members are unfamiliar with risk management practices.

What should the risk manager do?

Options:

A.  

Ask the sponsor to define the risk strategy to align with client needs.

B.  

Develop a framework and engage the team in creating a risk plan.

C.  

Train the team on basic techniques and defer the risk strategy for later.

D.  

Concentrate on high-priority risks to meet the sponsor's expectations.

Discussion 0
Questions 63

A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

Options:

A.  

Perform a sensitivity analysis.

B.  

Perform a qualitative risk analysis.

C.  

Perform a constraint analysis.

D.  

Perform a root-cause analysis. 

Discussion 0
Questions 64

When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project's contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.

What should the project manager do?

Options:

A.  

Process the freight invoices at higher shipping costs against the project's contingency allowance.

B.  

Request a formal change order from the customer to increase the project's total budget.

C.  

Process the freight invoices for the budgeted amount and hope the shipping company will forgive the difference.

D.  

Ask the project sponsor to cover the additional shipping costs on the company's reserves account.

Discussion 0
Questions 65

The risk manager also serves as a facilitator for a project and realizes the project team members have biases impacting how they perceive risks. What analysis is currently being used?

Options:

A.  

Quantitative risk analysis

B.  

Force field analysis

C.  

Qualitative risk analysis

D.  

Stakeholder analysis

Discussion 0
Questions 66

A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long.

What should the risk manager do in this case?

Options:

A.  

Document the risk in the risk register for analysis.

B.  

Document the detailed risk consequences,

C.  

Immediately start the contracting process.

D.  

Proceed with the quantitative risk analysis. 

Discussion 0
Questions 67

The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project's budget, potentially increasing the duration by two weeks.

What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?

Options:

A.  

Stakeholder management and communication tools

B.  

Team performance reports and analysis tools

C.  

Schedule management tools (i.e., Gantt Charts)

D.  

Estimation and probability analysis tools (i.e. Monte Carlo simul-ations) 

Discussion 0
Questions 68

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X's project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.

How should project X's project manager avoid this situation in the future?

Options:

A.  

Prepare a contingency response plan to implement when delays occur

B.  

Ask the other project manager to officially confirm the new date in writing

C.  

Request that the other project manager be added to relevant reports

D.  

Request that the other project manager inform if any additional delays are expected

Discussion 0
Questions 69

A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.

Which data analysis tool should the risk manager use to forecast future performance?

Options:

A.  

Sensitivity analysis

B.  

What-if scenario analysis

C.  

Regression analysis

D.  

Decision tree analysis

Discussion 0
Questions 70

In the middle of a project to improve internal workflows, the team realizes that some previously identified challenges, such as lack of stakeholder engagement, have diminished. However, the risk manager determines that concerns related to resource availability and regulatory compliance are becoming more significant.

Which measures should the risk manager implement?

Options:

A.  

Concentrate on monitoring only high-visibility risks to conserve resources.

B.  

Focus on tracking the risks identified at the project's start to maintain consistency.

C.  

Reassess risk priorities carefully and update the risk register on a regular basis.

D.  

Delegate all monitoring responsibilities entirely to individual team members for efficiency.

Discussion 0
Questions 71

During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?

Options:

A.  

A potential need to share the space with other machinery

B.  

A different type of equipment received before installation

C.  

A time delay during air conditioning installation activities

D.  

A quality nonconformance issue raised during the inspection

Discussion 0
Questions 72

A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?

Options:

A.  

Risk mitigation

B.  

Risk transfer

C.  

Risk acceptance

D.  

Risk avoidance

Discussion 0
Questions 73

A project with impending risks has 12 deliverables as subprojects, which will be executed in three different locations involving multiple stakeholders. What should the risk manager do to organize the prevailing risks?

Options:

A.  

Combine individual and focus groups to identify risks and create the overall risk register.

B.  

Use focus groups to conduct group risk assessments of the project to identify risks.

C.  

Request individual assessments of the project and its deliverables to identify risks.

D.  

Use the external risk assessment of the project and its deliverables to identify risks.

Discussion 0
Questions 74

A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team's tasks have yet to be completed.

What should the risk manager do next?

Options:

A.  

Start a quantitative analysis to understand the impact.

B.  

Crash the schedule to mitigate the risk consequences.

C.  

Transfer the risk to the external team.

D.  

Ask the risk owners to review the risk response plan.

Discussion 0
Questions 75

A risk manager has noticed that response actions are not working as expected when a risk occurs, mainly because the risk triggers are not well-defined. Which tool should the risk manager use to facilitate risk trigger identification in the upcoming risk review assessment?

Options:

A.  

Risk burndown chart

B.  

Ishikawa diagram

C.  

Risk breakdown structure (RBS)

D.  

Affinity diagram

Discussion 0
Questions 76

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.

What is the current project risk exposure?

Options:

A.  

US$18,000

B.  

US$72.000

C.  

US$30,000

D.  

US$48,000

Discussion 0
Questions 77

The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?

Options:

A.  

Review the assumptions analysts

B.  

Conduct a checklist analysis on each risk

C.  

Create a risk response plan for those risks

D.  

Review the risk register to check for the new risks

Discussion 0
Questions 78

A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?

Options:

A.  

Each cause has a degree of uncertainty

B.  

Each cause has well defined owner

C.  

The causes represent actual conditions

D.  

The causes must be validated by the risk owner

Discussion 0
Questions 79

A project is in the execution phase and involves large volumes of supplies. The project is the last phase of a 10-year initiative. The project sponsor asks the project manager to provide the performance report for the whole initiative.

Which analysis should the risk manager do to provide the project manager with the performance report?

Options:

A.  

Time Series Analysis

B.  

Regression Analysis

C.  

Variance Analysis

D.  

Monte Carlo Analysis 

Discussion 0