Pre-Summer Sale 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exams65

ExamsBrite Dumps

PMI Risk Management Professional (PMI-RMP) Exam Question and Answers

PMI Risk Management Professional (PMI-RMP) Exam

Last Update Apr 29, 2026
Total Questions : 278

We are offering FREE PMI-RMP PMI exam questions. All you do is to just go and sign up. Give your details, prepare PMI-RMP free exam questions and then go for complete pool of PMI Risk Management Professional (PMI-RMP) Exam test questions that will help you more.

PMI-RMP pdf

PMI-RMP PDF

$36.75  $104.99
PMI-RMP Engine

PMI-RMP Testing Engine

$43.75  $124.99
PMI-RMP PDF + Engine

PMI-RMP PDF + Testing Engine

$57.75  $164.99
Questions 1

A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.

Which technique should the risk manager use?

Options:

A.  

Political, economic, social, technological, legal, and environmental (PESTLE) analysis

B.  

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.  

Decision tree analysis

D.  

Cost-benefit analysis

Discussion 0
Questions 2

During a virtual workshop presenting a product to potential clients, a facilitator emails the product brochure and asks attendees to check their spam folder if the email does not appear in their inbox. What kind of threat strategy is the facilitator applying?

Options:

A.  

Accept actively

B.  

Mitigate

C.  

Accept passively

D.  

Share

Discussion 0
Questions 3

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.

What should the risk manager do first to understand the impact on project cost?

Options:

A.  

Conduct a subject matter expert (SME) meeting.

B.  

Perform qualitative analysis.

C.  

Prioritize after quantitative analysis

D.  

Prioritize the stakeholders affected.

Discussion 0
Questions 4

A stakeholder is asking a project team to hire an external vendor with more expertise and capacity to accelerate a delivery plan. The team has some concerns about this request. What should the risk manager do first?

Options:

A.  

Conduct a strengths weakness, opportunities, and threats (SWOT) analysis.

B.  

Create a contingency plan

C.  

Start a vendor assessment

D.  

Submit a change request

Discussion 0
Questions 5

A software development project team was preparing for a phased release when an unknown and unexpected risk occurred with potential for delaying one of the features for the planned release. The project team decided to go ahead with the release and address this missing feature at a later date. One of the end users learned about this and strongly opposed the planned release.

What should the risk manager have done to prevent this situation?

Options:

A.  

Engaged the sponsor and informed them of the decision to remove the planned feature.

B.  

Engaged the stakeholders more in risk management activities and decisions to get their buy-in and support.

C.  

Performed proper risk identification at the project outset to ensure this risk was identified and mitigated.

D.  

Created a schedule buffer in the plan to deal with unknown risks if and when they occurred. 

Discussion 0
Questions 6

An agriculture government agency faces different challenges with farmers and landlords In implementing its ambitious growth strategy. The agency decided to establish an enterprise risk management unit to identify risks, analyze risks, and provide a handbook showing how to handle the surrounding uncertainty.

What should the risk management expert recommend the agency do first to identify risks and develop the handbook?

Options:

A.  

Follow standard risk Identification tools dedicated for agriculture and tailor them to the environment.

B.  

Hire an agriculture expert who can develop the required handbook and discuss it with the agriculture minister.

C.  

Prepare a list of the key resources that will be used to compile a risk management plan.

D.  

Conduct meetings, facilitated workshops, and interviews with stakeholders to identify potential risks.

Discussion 0
Questions 7

An organization is executing two projects — Project A and Project B — simultaneously. A previously identified risk will impact the schedule for Project A. While executing the mitigation plan, a number of residual risks are identified that could provide cost savings for Project B.

Which action should the risk manager for Project A take?

Options:

A.  

Review the findings in Project A ' s closure documents and propose a new organizational process for portfolio risk management.

B.  

Consult with Project B ' s risk manager and determine where synergies might exist between the risk management plans for both projects.

C.  

Combine the risk registers for Project A and Project B and determine if there are any additional cross-project opportunities to exploit.

D.  

Continue executing the planned risk mitigation to avoid any additional schedule impact to Project A.

Discussion 0
Questions 8

A new project is about to start, and the risk manager wants to review some documents that could be relevant for risk identification. Which document will help the risk manager in this process?

Options:

A.  

Detailed work breakdown structure (WBS)

B.  

Lessons learned from previous projects

C.  

Baselines approved by the project team

D.  

Actual data from the current project

Discussion 0
Questions 9

After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?

Options:

A.  

Probability of a response triggering a secondary risk

B.  

How the response will affect the quality of the components

C.  

If the risk response is tied to an activity on the critical path

D.  

Verify due dates for the actions have been identified

Discussion 0
Questions 10

The risk manager of a major project needs to ensure the organizational process assets (OPAsj are updated as a result of risk management activities. How will the risk manager accomplish this?

Options:

A.  

Ensuring that the project sponsor is kept well-informed

B.  

Arranging periodic risk: management process audits

C.  

Communicating the status of risks regularly to stakeholders

D.  

Monitoring costs with intervention when necessary

Discussion 0
Questions 11

Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.

What should the project manager do next?

Options:

A.  

Review assumptions and constraints around risks.

B.  

Develop the risk response plans for identified risks.

C.  

Determine the likelihood and impact of the risks.

D.  

Apply an iterative approach to risk identification.

Discussion 0
Questions 12

A highly complex project is about to start Considering that many changes and new information will arise as the work moves forward, key stakeholders are anxious about not addressing risks on time

What should the risk manager do in this situation?

Options:

A.  

Establish a formal and upfront risk identification process.

B.  

Use a detailed and quantitative risk assessment process.

C.  

Create an effective and clear risk communication process.

D.  

Adopt a dynamic and frequent risk management process.

Discussion 0
Questions 13

A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

Options:

A.  

Review potential next steps with the project team.

B.  

Review the scope of work to determine the prescribed project methodology.

C.  

Review the policies and practices that are outlined in the risk management plan.

D.  

Review the contract and determine the resources and project funding.

Discussion 0
Questions 14

During a project meeting, the project sponsor asks to close a project risk. The team does not recommend closing the risk because it is expected to be present in the next phase of the project work.

How should the risk manager address this concern?

Options:

A.  

Compare the actual data with the historical data.

B.  

Compare the actual data with the subject matter expert (SME) criteria.

C.  

Compare the actual data with the risk baseline.

D.  

Compare the actual data with the project sponsor ' s expectation.

Discussion 0
Questions 15

During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?

Options:

A.  

Strengths, weakness, opportunities, and threats (SWOT) analysis

B.  

Delphi technique

C.  

Decision tree analysis

D.  

Probability impact matrix

Discussion 0
Questions 16

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.

What is the total contingency budget that should be created?

Options:

A.  

US$68,000

B.  

US$52,000

C.  

US$120,000

D.  

US$80,000

Discussion 0
Questions 17

The risk manager for a large-scale software development project with a tight deadline and multiple stakeholders highlights concerns about potential delays, communication gaps, and vendor reliability. During the early stages of the project, the project sponsor requests that the risk manager identify and address any potential risks that could disrupt project delivery.

What should the risk manager do?

Options:

A.  

Create a list of potential issues.

B.  

Consult the project management plan.

C.  

Conduct risk management exercises.

D.  

Perform qualitative risk analysis.

Discussion 0
Questions 18

A company has implemented a policy requirement for employees to use complex passwords and update them regularly. A few employees are unable to make the changes, which increases the likelihood of cybercriminals compromising their passwords.

What should the risk manager do?

Options:

A.  

Increase the residual risk monitoring.

B.  

Increase the inherent risk monitoring.

C.  

Reassess the inherent risk level.

D.  

Reassess the residual risk level.

Discussion 0
Questions 19

The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date.

What should be the risk manager ' s next step?

Options:

A.  

Check the schedule for constraints

B.  

Use the P90 date on the risk report

C.  

Decrease the number of iterations

D.  

Decrease the risk consequences

Discussion 0
Questions 20

A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed.

Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?

Options:

A.  

Schedule and resource assumptions

B.  

Contingency reserves

C.  

Work breakdown structure (WBS)

D.  

Risk impact matrix

Discussion 0
Questions 21

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

Options:

A.  

Remind the project team to keep an open mind

B.  

Review the results with the project manager afterward

C.  

Review published operational experience reports

D.  

Use the mean answers provided by the project team 

Discussion 0
Questions 22

 

During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.

Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)

Options:

A.  

Compatibility

B.  

Urgency

C.  

Usability

D.  

Proximity

E.  

Detectability 

Discussion 0
Questions 23

The stakeholders of a building construction project are not comfortable with the project manager ' s handling of the project as they believe there is a financial risk. The project manager asks the risk manager to assist in demonstrating to the stakeholders that the project risks are under a tolerable threshold.

What should the risk manager do first to demonstrate this to the stakeholders?

Options:

A.  

Gather other project risk historical information.

B.  

Gather and reconcile project risk report data.

C.  

Work with the sponsor to convince the risks are under control.

D.  

Work with the team to ensure the project is in good health. 

Discussion 0
Questions 24

The major investor in a road construction project is constantly asking project team members for information about the project ' s execution. This has resulted in the project team working 20% of their day preparing project reports for the stakeholders.

What should the risk manager do to enhance the project team ' s approach to risk reports?

Options:

A.  

Talk to the project team and ensure they avoid direct communication with this stakeholder.

B.  

Engage with the team to enhance the project risk reports sent to the stakeholders.

C.  

Highlight to the stakeholders the agreed predetermined frequency of risk reports.

D.  

Work with the project sponsor to ensure stakeholders avoid directly influencing the project team.

Discussion 0
Questions 25

A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?

Options:

A.  

Risk mitigation

B.  

Risk transfer

C.  

Risk acceptance

D.  

Risk avoidance

Discussion 0
Questions 26

.

A project manager is identifying risks on a project and decides to use a risk checklist to gather historical data accumulated from similar projects. With several different historical project files to choose from, which two pieces of information should the project manager include in their risk checklist? (Choose two.)

Options:

A.  

Budget variance data from previously completed projects.

B.  

Project scope and cost management plans from previous projects.

C.  

Lessons learned from similar completed projects.

D.  

Previous project risks that may be relevant to this project.

E.  

Stakeholder analysis metrics from projects with similar risk profiles.

Discussion 0
Questions 27

The project manager asks the risk manager to determine the initial risk assessment for a six month initiative that is about to kick-off. Which two artifacts will help the risk manager conduct the related analysis? (Choose two.)

Options:

A.  

Work breakdown structure (W & S)

B.  

Project organizational chart

C.  

Configuration management plan

D.  

Brainstorming

E.  

Monte Carlo analysis

Discussion 0
Questions 28

During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be

mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.

Which action should the risk manager take to address this risk?

Options:

A.  

Accept the identified risk because other stakeholders feel that there are higher priority risks to address.

B.  

Mitigate the identified risk in order to reduce the probability of impacting the stakeholder ' s team.

C.  

Escalate the identified risk to the project sponsor and allow them to determine the best course of action.

D.  

Add the identified risk to the risk register for future probability and impact analysis.

Discussion 0
Questions 29

A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen.

What should the risk manager do first?

Options:

A.  

Perform an assumptions and constraints analysis.

B.  

Use the Wideband Delphi method.

C.  

Use the brainstorming technique.

D.  

Perform a strength, weaknesses, opportunities, and threats (SWOT) analysis. 

Discussion 0
Questions 30

When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)

Options:

A.  

Request a contingency reserve from management

B.  

Arrange a team meeting, review the project ' s scope, and discuss dependency mapping

C.  

Ensure participants review relevant documents before attending the meeting

D.  

Ensure that all the relevant stakeholders participate

E.  

Update the risk register during the team meeting.

Discussion 0
Questions 31

The sponsor of a construction project is upset about the results of the risk management team. The sponsor believes the team did not properly identify the risks that could affect the project. The team did manage the risks; however, some of the risk response strategies created secondary risks.

What should the risk management team have done to manage this situation?

Options:

A.  

Ensured to include the stakeholders in the team discussions

B.  

Encouraged involvement of the project team during the review meetings

C.  

Enhanced communication with the sponsor regarding secondary risk impact

D.  

Ensured the sponsor got more involved with the project risk planning

Discussion 0
Questions 32

After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.

How could the risk manager have avoided the board ' s response?

Options:

A.  

Engaging the key stakeholders during the prioritization process

B.  

Prioritizing the risks based on the project sponsor ' s risk appetite

C.  

Engaging with the project sponsor before presenting to the board

D.  

Working with an established industry standard prioritization method

Discussion 0
Questions 33

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.

What should the project manager have done to avoid this?

Options:

A.  

Provided regular training to the risk owners for plan implementation

B.  

Determined risk triggers and thresholds in the risk response plan

C.  

Increased communications to influence stakeholder risk responses

D.  

Updated the project schedule, adding risk owner implementation tasks.

Discussion 0
Questions 34

Some project risks are applicable for the project ' s lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

Options:

A.  

When the forecast activity date has been met or exceeded

B.  

When the stakeholders agree a risk is no longer applicable

C.  

When the risk has been realized and can no longer happen again

D.  

When iterative data analysis determines the risk is not applicable

Discussion 0
Questions 35

The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder.

What should the project risk manager do next to identify risks?

Options:

A.  

Review the risk breakdown structure to ensure project scope is covered.

B.  

Use the brainstorming technique to remove personal bias.

C.  

Use expert judgment to remove ego or emotional conflict.

D.  

Consider the Delphi technique to gather all stakeholder opinions.

Discussion 0
Questions 36

During the monthly executive review meeting, the project sponsor would like to understand how the project team has planned to manage risks that were identified in the last meeting. What should the project manager do?

Options:

A.  

Utilize a Monte Carlo assessment to provide risk related impacts.

B.  

React to the secondary and residual risks only if they occur.

C.  

Include secondary and residual risks as part of the response.

D.  

Transfer secondary and residual risks to the project sponsor.

Discussion 0
Questions 37

A project manager is leading a complex, high-risk construction project in the city center. To address risk based on lessons learned from similar past building projects, the risk manager assigns a team member to assess and confirm risk thresholds for the project.

What should the risk manager do?

Options:

A.  

Develop risk assessment processes and tools to quantify risk thresholds.

B.  

Work with stakeholders to achieve consensus on risk thresholds.

C.  

Use subject matter experts and historical data to estimate risk thresholds.

D.  

Review regulatory requirements and the contract to identify risk thresholds.

Discussion 0
Questions 38

A project is in the execution phase and involves large volumes of supplies. The project is the last phase of a 10-year initiative. The project sponsor asks the project manager to provide the performance report for the whole initiative.

Which analysis should the risk manager do to provide the project manager with the performance report?

Options:

A.  

Time Series Analysis

B.  

Regression Analysis

C.  

Variance Analysis

D.  

Monte Carlo Analysis 

Discussion 0
Questions 39

The trigger for a highly categorized threat has occurred. The risk has a set response plan.

Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?

Options:

A.  

Product Manager

B.  

Risk Action Owner

C.  

Risk Owner

D.  

Project Manager

Discussion 0
Questions 40

A risk manager has a well-structured risk management process in place for a complex project with a tight schedule. Despite implementing preventive actions, one of the risks identified in the early stages of the project has still occurred and is now an issue.

What should the risk manager do next?

Options:

A.  

Meet with the project team to brainstorm potential solutions to the problem.

B.  

Implement the risk response plan to remedy the problem as soon as possible.

C.  

Initiate discussions with the project manager to decide how to manage the problem.

D.  

Escalate the problem to the project sponsor to agree on the best course of action. 

Discussion 0
Questions 41

A project team has completed the risk response plan for a newly identified major project risk. Some team members argue the plan does not totally eliminate the risk, considering the effort required to implement it, and feel the planned response should be thrown out altogether.

What should the risk manager do in this situation?

Options:

A.  

Accept the response because there are no secondary risks were identified.

B.  

The response plan should be discontinued and the risk should be accepted and dealt with if it occurs.

C.  

Accept the residual risk as it is compatible with the organization ' s risk appetite.

D.  

All identified risks must be addressed because they might significantly impact the project if they occur. 

Discussion 0
Questions 42

A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.

Which kind of numerical analysis should be performed to understand the worst-case scenarios?

Options:

A.  

Earned value analysis

B.  

Qualitative risk analysis

C.  

Sensitivity analysis

D.  

Root cause analysis

Discussion 0
Questions 43

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.

What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)

Options:

A.  

Develop checklists based on historical information

B.  

Conduct interviews, meetings, and focus groups

C.  

Assign a different risk manager for each portfolio unit

D.  

Employ brainstorming to generate spontaneous ideas

E.  

Perform qualitative and quantitative risk analyses 

Discussion 0
Questions 44

During a project progress meeting, a project team member is concerned that one of the risks has triggered several other low-level risks. These risks should be responded to quickly or there will be severe consequences for the project deliverables.

What should the risk manager do?

Options:

A.  

Update the watchlist.

B.  

Initiate a risk response when these risks occur.

C.  

Address only the high-priority risk.

D.  

Perform a risk urgency assessment. 

Discussion 0
Questions 45

In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.

What should the risk manager do?

Options:

A.  

Update the risk register accordingly and review it in regular project meetings.

B.  

Accept the risk because residual risks are often low.

C.  

Ask a subject matter expert (SME) to assess the residual risk and take action.

D.  

Assign a risk owner and set it as high priority and high impact.

Discussion 0
Questions 46

A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?

Options:

A.  

Develop and employ an Ishikawa diagram

B.  

Analyze the assumptions and constraints

C.  

Perform a review of project documents

D.  

Create prompt lists for expert interviews

Discussion 0
Questions 47

When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project ' s contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.

What should the project manager do?

Options:

A.  

Process the freight invoices at higher shipping costs against the project ' s contingency allowance.

B.  

Request a formal change order from the customer to increase the project ' s total budget.

C.  

Process the freight invoices for the budgeted amount and hope the shipping company will forgive the difference.

D.  

Ask the project sponsor to cover the additional shipping costs on the company ' s reserves account.

Discussion 0
Questions 48

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.

What should the risk manager do next to find out the correct limit?

Options:

A.  

Review the agreed-upon risk tolerance

B.  

Perform a sensitivity analysis of the risk

C.  

Find out the stakeholders’ risk appetite

D.  

Use industry standard risk thresholds

Discussion 0
Questions 49

At an oil and gas company, a major unified management information system is to be implemented. The project manager noted that risks gathered from the organization ' s business functions are not properly identified and categorized, making it difficult to develop an effective risk response.

How should the project manager handle this situation?

Options:

A.  

Outsource conducting the risk response plan to risk consultants.

B.  

Ask functional managers to improve their risk register and process.

C.  

Adjust the risk response plans to effectively handle the identified risks.

D.  

Coach the functional groups on how to properly conduct the process.

Discussion 0
Questions 50

A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:

1 = Very Low

2 = Low

3 = Medium

4 = High

5 = Very High

What type of risk analysis is the risk manager performing?

Options:

A.  

Scenario-based risk analysis

B.  

Quantitative risk analysis

C.  

Qualitative risk analysis

D.  

Monte Carlo analysis 

Discussion 0
Questions 51

As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?

Options:

A.  

Close and communicate the results of the risk response actions.

B.  

Run a workshop to analyze the effectiveness of the risk plan.

C.  

Conduct a risk reserve analysis and document the results.

D.  

Verify that all risk response actions have been documented. 

Discussion 0
Questions 52

As part of standard procedure to monitor and control a project, a risk manager should constantly update the risk register. The risk register updates should include information on risk reassessment, risk audits, and periodic risk reviews.

What additional information should the risk manager prioritize in the risk register updates?

Options:

A.  

Actual outcomes and performance of risk management strategies

B.  

Actual outcomes of the project ' s risks and risk responses

C.  

Actual costs and schedule delays of risk events

D.  

Actual cost impact of risk events

Discussion 0
Questions 53

While executing an oil extraction project in an environmentally sensitive area, weather is the main cause of delay in the project work. The risk manager was aware that the delays caused by the weather could not be avoided or mitigated.

What should the risk manager do to manage this risk?

Options:

A.  

Perform time recovery actions.

B.  

Execute the prevention plans.

C.  

Execute the contingency plans.

D.  

Perform change management.

Discussion 0
Questions 54

A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?

Options:

A.  

Include all stakeholders in the project ' s governance.

B.  

Communicate response strategies to all stakeholders.

C.  

Ignore any risks beyond stakeholders ' tolerance.

D.  

Consider stakeholders ' positions and opinions regarding the project’s output.

Discussion 0
Questions 55

After the initial assessment of a new project, a project manager found that in order to complete the expected results, detailed and exhaustive planning will be required to ensure the product ' s characteristics and quality. What should the risk manager propose to the project manager what to do?

Options:

A.  

Use a predictive approach for the delivery.

B.  

Use a hybrid approach for the delivery.

C.  

Use an adaptive approach for the delivery.

D.  

Use an agile approach for the delivery. 

Discussion 0
Questions 56

A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?

Options:

A.  

Evaluate any new risks that are introduced due to the change in scope.

B.  

Update the risk management plan to reflect the scope change.

C.  

Reassess the identified risks that impact the project scope.

D.  

Update the risk register to identify, analyze, and plan a response for any new risk.

Discussion 0
Questions 57

What should the risk owner use as an effective information-gathering technique during the planning session?

Options:

A.  

Monte Carlo analysis

B.  

Update risk register

C.  

Brainstorming

D.  

Cost and time estimating

Discussion 0
Questions 58

A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.

What should the project manager do?

Options:

A.  

Avoid the risk

B.  

Transfer the risk

C.  

Ignore the risk

D.  

Accept the risk

Discussion 0
Questions 59

A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager ' s department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.

What should the risk manager of the related project have done to prevent this situation from happening?

Options:

A.  

Reformed the risk monitoring and closing process properly.

B.  

Created the project work plan and budget more accurately.

C.  

Educated the project team on budget change requests.

D.  

Communicated better with the organization ' s CEO.

Discussion 0
Questions 60

it typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours.

Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?

Options:

A.  

4 hours

B.  

5 hours

C.  

6 hours

D.  

12 hours

Discussion 0
Questions 61

A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team ' s tasks have yet to be completed.

What should the risk manager do next?

Options:

A.  

Start a quantitative analysis to understand the impact.

B.  

Crash the schedule to mitigate the risk consequences.

C.  

Transfer the risk to the external team.

D.  

Ask the risk owners to review the risk response plan.

Discussion 0
Questions 62

A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.

What should the project manager have done differently?

Options:

A.  

Executed the risk strategy response and recorded it in the risk register.

B.  

Performed an analysis to affirm the request is valid before submitting.

C.  

Informed the client and the project sponsor that the request is being submitted.

D.  

Contacted the other stakeholders so they know the request is in process.

Discussion 0
Questions 63

A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of delivering the solution on time and within budget, as this project could lead to significant future opportunities. The risk manager recognizes that the team lacks a standardized approach to managing risks and that some team members are unfamiliar with risk management practices.

What should the risk manager do?

Options:

A.  

Ask the sponsor to define the risk strategy to align with client needs.

B.  

Develop a framework and engage the team in creating a risk plan.

C.  

Train the team on basic techniques and defer the risk strategy for later.

D.  

Concentrate on high-priority risks to meet the sponsor ' s expectations.

Discussion 0
Questions 64

While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?

Options:

A.  

Issue log

B.  

Change log

C.  

Assumption log

D.  

Risk-adjusted back log

Discussion 0
Questions 65

An organization that spans across different countries undergoes a digital transformation project. The project manager has assigned a risk management team leader who is a risk management certified candidate in their domain.

What should the risk management team leader do in the early stages of the project?

Options:

A.  

Conduct qualitative risk analysis to prioritize potential risks.

B.  

Plan a solid risk response plan and secure the necessary funding.

C.  

Educate stakeholders on best practices to perform risk management.

D.  

Benchmark to an organization which has executed a similar project,

Discussion 0
Questions 66

A risk manager schedules workshops for identifying risks about an initiative involving multiple business units, recruitments for different roles, procurements, technological uplift, training, and changes in the ways of working. Who should participate in the risk management activity?

Options:

A.  

Core project team

B.  

Internal and external stakeholders

C.  

Key business stakeholders

D.  

Internal stakeholders only

Discussion 0
Questions 67

During project development, a risk manager notices that a major update in the country ' s regulations might be happening in the upcoming months. These changes will affect the materials used in building some of the components of the final product. The project team is unsure if this risk will affect the project negatively or positively.

Which tool should the project team use to determine this?

Options:

A.  

Sensitivity analysis

B.  

Threshold analysis

C.  

Reserve analysis

D.  

Strengths, weaknesses, opportunities, and threats (SWOT) analysis 

Discussion 0
Questions 68

A project team has just initiated a large project to move an organization ' s headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.

What should the risk manager consider?

Options:

A.  

Aligning with the project manager to hold an open brainstorm session with all stakeholders will suffice.

B.  

The ideal solution is to find alternate documents that provide good visibility on the environment.

C.  

The risk identification process can be carried out as long as the project statement is available.

D.  

Risk evaluation will be challenging without these elements as a frame of reference.

Discussion 0
Questions 69

A risk manager for a cross-functional project is initiating the risk identification process. The risk manager conducted some meetings for stakeholders to express their concerns, but some stakeholders are complaining that their opinions were not considered.

How should the risk manager address these concerns?

Options:

A.  

Refer to the requirements documentation to confirm stakeholder requirements as they relate to risks.

B.  

Refer to the project charter to find guidelines and stakeholder communication channels.

C.  

Review the stakeholder register and stakeholder engagement plan to communicate and solicit stakeholder input.

D.  

Rewrite the risk register to include the additional possible risks and inform the stakeholders.

Discussion 0
Questions 70

The project manager performed ' a variance analysis on the project during the execution phase. The variances were shown as increasing

What does this result imply?

Options:

A.  

The uncertainty and risk are increasing.

B.  

The project schedule is lagging behind.

C.  

There is no potential for future deviation.

D.  

The project is over budget.

Discussion 0
Questions 71

An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.

What should the risk manager do next?

Options:

A.  

Add only the threats to the risk register

B.  

Utilize different tools to identify the risks

C.  

Plan risk responses to the threats

D.  

Update the risk register with the identified risks

Discussion 0
Questions 72

A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.

What should the risk management professional do next?

Options:

A.  

Perform a sensitivity analysis to the higher-level aggregate activities

B.  

Develop a risk breakdown structure (RBS) identifying the potential risk categories

C.  

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D.  

Perform a base line Monte Carlo simul-ation to address overall threats to project objectives

Discussion 0
Questions 73

During a project ' s initial planning session, the project team identifies a possible risk. The team is under the impression that a critical vendor might delay delivery. This could impact both the project schedule and budget. The team shares insights on the risk ' s likelihood and impact with the risk manager.

What should the risk manager do?

Options:

A.  

Assume the vendor will deliver on time and focus only on internal risks.

B.  

Allocate contingency funds without first evaluating the risk ' s probability and impact.

C.  

Wait indefinitely for the vendor ' s update before analyzing the risk.

D.  

Assess the risk using a probability-impact matrix and prioritize it based on its score.

Discussion 0
Questions 74

A financial institution is creating a new product database tor their clients. The project sponsor of this project is concerned about failure of the digital platform that hosts the database. The risk manager states that this risk will only occur if there is a major power outage; however, the financial institution has back-up power generators in place.

What type of risk is being referred to here?

Options:

A.  

Major risk

B.  

Residual risk

C.  

Secondary risk

D.  

Environment risk

Discussion 0
Questions 75

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

Options:

A.  

Recommend the removal of risks to the project manager to reduce project risk exposure.

B.  

Advise the client that the project has exhausted contingency.

C.  

Quantify the risk exposure that exceeds project contingency.

D.  

Generate reports to assess and communicate the project risk level.

Discussion 0
Questions 76

A risk manager has been assigned to replace a risk manager on sick leave. The new risk manager notices that the risk register is missing data that are key to the risk management process.

Which data will the risk manager require first?

Options:

A.  

Risk description risk response, and quantitative data

B.  

Project plan, risk complexity, and secondary risk

C.  

Project plan, risk priority, and tool availability

D.  

Risk description, risk probability, and risk impact 

Discussion 0
Questions 77

A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?

Options:

A.  

Risk assessment criteria

B.  

Project management plan

C.  

Project assumptions

D.  

Risk management plan 

Discussion 0
Questions 78

A project has a S0S4 chance of a US$100 000 profit and a 40% chance of a US$100,000 loss. What is the expected monetary value for this project?

Options:

A.  

US$20.000 loss

B.  

US$20,000 profit

C.  

US$40,000 loss

D.  

US$100,000 profit

Discussion 0
Questions 79

A risk manager has identified multiple risks in an innovation project and needs to prioritize the use of resources to respond to the risks. Which analysis will help the risk manager in this situation?

Options:

A.  

Sensitivity analysis

B.  

Qualitative analysis

C.  

Statistical analysis

D.  

Impact analysis 

Discussion 0
Questions 80

A risk manager for a large project has completed documenting the risk management plan. The project is moving from planning to execution.

Which three actions should the risk manager take to ensure the risk management plan remains effective during the project timeframe? (Choose 3)

Options:

A.  

Verify whether or not any identified risks might occur and implement the risk response plan.

B.  

Regularly check and report on the status of risks identified according to their prioritization.

C.  

Monitor the status and oversee execution of the risk response plan for each identified risk.

D.  

Ensure management reserves are sufficient to cover the mitigation plans for all identified risks.

E.  

Allocate and lock in project resources according to the initial risk prioritization for all identified risks.

Discussion 0
Questions 81

A software company has recently completed a project that delivered a new web application. Throughout the project, several issues were realized that resulted in cost and schedule overruns. The project ' s executive sponsor has requested a deep-dive into what went wrong since the company will be developing additional web applications in the future.

What should the risk manager do?

Options:

A.  

Gather the project ' s status reports and meeting minutes to determine when issues occurred and how quickly the issues were addressed.

B.  

Conduct a retrospective meeting with stakeholders and inquire about what went well and what could be improved on future projects.

C.  

Work with the project manager to determine if additional resources could have prevented or mitigated the issues that arose on the project.

D.  

Review the project ' s risk register and determine how comprehensive and effective each risk and issue response was.

Discussion 0
Questions 82

In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.

How should the project manager address this concern with the health authorities?

Options:

A.  

Suspend the project as the secondary risk will negatively impact residents ' health which is not acceptable.

B.  

Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.

C.  

Assess and record associated secondary risks and proceed to treat them as any other risks.

D.  

Proceed with the project as normal since a minor number of residents will be effected negatively.

Discussion 0