Certified Associate in Project Management (CAPM) Certification
Last Update May 1, 2024
Total Questions : 748
We are offering FREE PMI-002 PMI exam questions. All you do is to just go and sign up. Give your details, prepare PMI-002 free exam questions and then go for complete pool of Certified Associate in Project Management (CAPM) Certification test questions that will help you more.
A series of consecutive points on the same side of the average is called ____________.
Which of the following is not a process of Project Communications Management?
Complete final contract performance reporting and verify product is done in _______.
If a project has an 80% chance of activity will take 2 weeks or less. what is the probability of the event?
The most effective method in developing a project team within a matrix organization is to follow the ________.
The ability of a product to be used for different purposes at different capacities and under different conditions determines its __________.
___________ is a groups of processes required to purchase or acquire the products, services, or results needed from outside the project team to perform the work.
The communications management plan is primarily dependent on the ____________.
An activity that consumes no time or resource and shows only that a dependency exists between two activities is called:
The team members report to two bosses: the project manager and the functional manager. Which type of organization this is ?
Risk event is the description of what may happen to the _____ of the project.
In which type of organization, a project manager is in complete control of the project?
A Precedence Diagramming Method (PDM) uses which of the following dependencies
At what point in a project do you have the highest probability that it will fail?
You are managing a project that will implement a new Insurance software package. Two project team members have difficulty working together. They come to you, for help resolving the issues. You immediately set up a meeting that includes the functional manager. After the meeting you and the functional manager discuss the issues and agree on a solution. What type of organizational structure you are working in?
You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?
Who is the person responsible for obtaining funding for a new project's conceptual study?
A schedule activity may start 5 days before the predecessor activity finishes. This is an example of ______________.
The project manager's leadership style should be matched to the corresponding developmental level of the project team and should move through successive steps in the following order: _____________.
The belief that management's high levels of trust, confidence and commitment to workers leads to high levels of motivation and productivity on the part of workers is a part of which motivation theory?
Which of the following techniques is used to control the project schedule?
Completion of the _____________ scope is measured against the project management plan.
Which is not the tools and techniques used in Contract Administration:
Contract change control system
Contract negotiation
Payment system
Performance rating
The amount of time that an activity can be delayed from its early start without delaying the project end date is called:
During the Develop Schedule process, a Project Manager may have to go through several iterations of the schedule before establishing the schedule baseline. All of the following are tools and techniques that may be used during this process:
A major assumption of all network scheduling methods is that the activity duration must be _____.
Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components?
A document which describes how project scope will be managed and how scope changes will be integrated into the project is: (choose the best answer)
Formal acceptance by the client or sponsor of the project should be prepared and distributed during which process?
According to the PMBOK Guide, the project statement of work (SOW) should contain or reference all the following elements except?
Which of the following is best for handling cross-functional project needs for a large, complex project?
______________ provides details about how the project scope may be changed.
The product description of a project can help to create procurement details. Which one of the following best describes product description?
You are project manager and now in middle of creating RFP (Request for proposal). RFP (Request for proposal) is done in _______.
Which type of network diagram is also referred to Activity-on-Node (AON) diagrams?
How many communication channels will be required in a project in which 10 individual are participating?
Who is responsibility for making sure that a message in the project team is understood
The independence of two events in which the occurrence of one is not related to the occurrence of the other is called _______.
___________ must be measured regularly to identify variance from the plan.
Collect Requirements includes alternatives identification, which can be conducted by the common technique of
What is the key difference between a contract close-out and an administrative closure?
Mathematical models using linear, dynamic, integer, or algorithm models are considered
As a project manager, you know that the most important activity to ensure customer and stakeholder satisfaction is which of the following?
You have been assigned to take over a project that is 60 percent complete according to the schedule. After evaluation, you find that the project is running far behind schedule, and that the project will probably take double the time originally estimated by the previous project manager. However, the sponsor has been told that the project is on schedule. What is the BEST course of action you will take?
You are in process of developing an approximation of the costs of resources needed to complete each schedule activity. Which of the following is the least helpful input?
You are project manager and the monthly report to the client showed zero schedule variance. However, member of the team know that a milestone has been missed which will cause an overall delay to the project. Which one of the following is being inadequately reported?
You are in the process of numerically analyzing the effects of identified risks. Which of the following are NOT tools or techniques you can use in the process?
How many communication channels will be required in a project having five individual participants?
You are a project manager for your organization. Management has asked you to help them determine which projects should be selected for implementation. In a project selection model, which one of the following is the most important factor?
As a project manager, you know that the most important activity to ensure customer and stakeholder satisfaction is which of the following?
According to the PMBOK guide, the project statement of work(SOW) should contain or reference to all the following elements except ?
_______________ must be measured regularly to identify variance from the plan.
Which of the following scheduling techniques incorporates a form of risk assessment?
You are the project manager and are considering recommending a project that costs $280,000; expected inflows are $10,000 per quarter for the first two years and then $25,000 per quarter thereafter. What is the payback period?
You are project manager of a project and the funding for your project has been reduced. What is the BEST action to take in response to this?