Pre-Winter Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: agile70

ExamsBrite Dumps

Platform Development Lifecycle and Deployment Architect Question and Answers

Platform Development Lifecycle and Deployment Architect

Last Update Oct 12, 2026
Total Questions : 118

We are offering FREE Plat-Arch-202 Salesforce exam questions. All you do is to just go and sign up. Give your details, prepare Plat-Arch-202 free exam questions and then go for complete pool of Platform Development Lifecycle and Deployment Architect test questions that will help you more.

Plat-Arch-202 pdf

Plat-Arch-202 PDF

$31.5  $104.99
Plat-Arch-202 Engine

Plat-Arch-202 Testing Engine

$37.5  $124.99
Plat-Arch-202 PDF + Engine

Plat-Arch-202 PDF + Testing Engine

$49.5  $164.99
Questions 1

What three tools should an architect recommend to support application lifecycle methodology? Choose 3 answers

Options:

A.  

Database management systems

B.  

Version control repository

C.  

Middleware

D.  

Continuous integration tool

E.  

Issue tracking Tool

Discussion 0
Questions 2

Universal Containers (UC) is working with Salesforce CPQ, which uses configuration SObjects to drive business logic. What are two best practice recommendations an architect should propose to allow UC to deploy CPQ features as part of their CI/CD process? Choose 2 answers

Options:

A.  

Use data loader to deploy CSV files.

B.  

Use an open source SFDX plugin and version control.

C.  

Build an Apex framework to deploy CPQ records.

D.  

Use a third-party product.

Discussion 0
Questions 3

Universal Containers is a global organization that maintains regional production instances of Salesforce. One region has created a new application to track shipping containers. The CIO has requested that this new application be used globally by all the Salesforce instances and further maintained and modified regionally by local administrators.

Which two deployment tools will support the request? Choose 2 answers

Options:

A.  

Change Sets

B.  

Developer Console

C.  

ANT Migration Tool

D.  

VS Code with Salesforce Extension

Discussion 0
Questions 4

Universal Containers (UC) have developed a managed package targeted for AppExchange. The product includes some Apex code to customize and create layouts. UC is in the testing phase of the package, so it ' s not certified yet. During testing on the target org, the Apex code for the layouts fails.

Why are the Apex classes not able to access the metadata of the target org during testing?

Options:

A.  

Apex Settings to allow the access to metadata is not switched on.

B.  

UC needs to turn on Apex Settings within the custom metadata type.

C.  

UC needs to get the managed package certified by the Salesforce security review.

D.  

The solution is flawed. UC should utilize the Tooling API from a web service call to modify the layouts.

Discussion 0
Questions 5

Universal Containers (UC) had been using change sets for deploying all of the modifications to its Sales Cloud apps. After multiple business units joined the single Salesforce instance, there is a need to evaluate which development model is the most suitable for UC. The IT management has shown a particular interest in finding out more about the package development model.

As an architect, which two statements can be made to articulate the differences between the change set model and package development model? Choose 2 answers

Options:

A.  

In package development, the source of truth is the metadata in the package project, which makes it easy to integrate to a version control System.

B.  

A change set can be retrieved from the developer ' s workbench as a package, then pushed into the version control system to achieve the Versioning control.

C.  

In change set development, the source of truth is a combination of the metadata already in the environment and the content of your change Set.

D.  

In package development, the best practice is to consider the dependencies and build the dependencies into the package so it can be deployed In any other target orgs.

Discussion 0
Questions 6

What is a main characteristic of an agile team?

Options:

A.  

The team uses Scrum, Kanban, and Extreme Programming.

B.  

The team has biweekly sprints to ensure on-time delivery.

C.  

The team delivers new releases on dates defined in the beginning of the project, following a project plan

D.  

The team improves and evolves its processes and frequently delivers value to the end users.

Discussion 0
Questions 7

Universal Containers (UC) uses a managed package to install an internal Sales app in five orgs. Within each org there are integrations and local processes with the objects of the managed package. UC wants to use unlocked packages for better integration with CI/CD processes.

What would the Salesforce architect recommend for this migration?

Options:

A.  

Export all data from objects/fields of the managed package, uninstall it, install the unlocked package with the same namespace as the Managed package and restore all data.

B.  

Export all data from objects/fields of the managed package, uninstall it, install the unlocked package without namespace and restore all data.

C.  

Do not change to unlocked package as it is possible to perform all CI/CD processes with the managed package.

D.  

Migrate all classes, Visualforce, and components from the managed package to the unlocked package. Install the new version of the managed package (objects/fields only) and the unlocked package with the other components.

Discussion 0
Questions 8

Universal Containers (UC) is a large enterprise with a complex system landscape. UC is currently rolling out new infrastructure and strategies around Salesforce DevOps. Some of the key feature ' s UC

is looking to support is rollback of metadata after a deployment, and the backup and restore of data to help recover from deployment issues, system bugs, or outages in their downstream systems.

Regulations in the industry mean that UC must be able to provide strategies to recover and rollback from issues. The regulator has discovered UC is not currently providing these, and must do so as soon as possible to remain compliant.

What should an architect advise?

Options:

A.  

Salesforce backs up all data and will restore it for customers on request.

B.  

Evaluate third-party and AppExchange products.

C.  

Advise stakeholders that rollback is not possible for Salesforce.

D.  

Custom build a feature rollback and data restore tool for Salesforce.

Discussion 0
Questions 9

What are three benefits of managing change with Packaged Development? Choose 3 answers

Options:

A.  

Manage the number of sandboxes needed to successfully deploy.

B.  

Clearly divides developers and testers.

C.  

Modular development process with specification of dependencies among packages.

D.  

Versioning to help with change management.

E.  

Making the release cycle more efficient and agile.

Discussion 0
Questions 10

At Universal Containers, Salesforce administrators are making changes to the permission sets under instruction from the business. Randomly, various SOQL statements are failing.

What strategy could be advised to bring this issue to the developer ' s attention earlier?

Options:

A.  

Extract each permission set, commit and merge to source control, and run through CI checks.

B.  

Ask administrators to only make changes to profiles instead

C.  

Create a sandbox refresh strategy to ensure each sandbox is refreshed every day.

D.  

Advice developers to switch to SOSL queries that are more robust instead.

Discussion 0
Questions 11

A Salesforce partner intends to build a commercially available application by creating a managed package for distribution through AppExchange.

What two types of environments can the partner use for development of the managed package? Choose 2 answers

Options:

A.  

Developer Edition

B.  

Developer Pro sandbox

C.  

Developer sandbox

D.  

Partner Developer Edition

Discussion 0
Questions 12

Universal Containers (UC) is planning to move to Salesforce Sales Cloud and retire its homegrown on-premise system. As part of the project, UC will need to migrate 5 million Accounts, 10 million Contacts, and 5 million Leads to Salesforce.

Which three areas should be tested as part of data migration? Choose 3 answers

Options:

A.  

Page layout assignments

B.  

Lead assignment

C.  

Account and Lead ownership

D.  

Data transformation against source system

E.  

Contact association with contact account

Discussion 0
Questions 13

Universal Containers (UC) has multi-cloud architecture in a single org. The Sales Cloud dev team is working in a Dev Pro sandbox (DevPro1) of delivering a release in three months. The business requirements from Service Cloud warrant a quicker release in four weeks, but need part of the Sales Cloud work that is completed in DevPro1. The decision of using a separate Dev Pro sandbox (DevPro2) is still pending. The DevPro1 was upgraded to preview for next Salesforce major release two weeks ago.

What should an Architect recommend?

Options:

A.  

Ask the second work stream team to work on the same DevPro1 sandbox.

B.  

Push back on the requirements because adding another work stream will bring some risks with it.

C.  

Clone the DevPro1 sandbox and name it DevPro2 for the second work stream to work on the Service Cloud requirements.

D.  

DevPro1 cannot be cloned because it is on a different version from Production. Just create new DevPro2, and migrate metadata from DevPro1.

Discussion 0
Questions 14

Universal Containers (UC) is considering implementing a minor change policy for a series of low-risk user stories that are commonly received by the UC admins. The policy would allow admins to make these changes directly in production. UC does not have continuous integration/continuous delivery (CI/CD) in place.

Which three best practices should the architect suggest UC follow for their new change policy? Choose 3 answers

Options:

A.  

Minor changes should be thoroughly documented and follow some type of standard cadence.

B.  

Minor changes do not need to be documented and can be made at any time.

C.  

Downstream environments will not be automatically updated when production changes.

D.  

All changes should still be tested.

E.  

CI/CD is required in to successfully manage minor changes.

Discussion 0
Questions 15

Universal Containers (UC) has multiple teams with major projects working concurrently in their own developer sandboxes. After deploying to production, a bug is discovered. Due to tight timelines, the development team has suggested correcting the bug in the user acceptance testing (UAT) environment, which is a full copy sandbox.

What should the architect recommend?

Options:

A.  

UC should spin up a new sandbox to use as a hot fix environment. Once the bug is corrected, the change should be applied to production and downstream environments.

B.  

The fix should be made in the developer environment where the project work was done. Once the fix has been made, it should go through a full deployment/testing process and adhere to the normal project cadence.

C.  

Since the issue was found in production, it should be treated as a change request and go into the backlog as an enhancement.

D.  

Correcting the bug in UAT is ideal. Since UAT is a full copy, it will be the fastest location to fix and test the resolution.

Discussion 0
Questions 16

Universal Containers wants to introduce data volume testing to resolve ongoing performance defects earlier in the lifecycle. Regulations prohibit the use of production data in non-production environments.

Which two options can the architect recommend? Choose 2 answers

Options:

A.  

Perform data masking on full sandbox after a refresh.

B.  

Generate mock data that mimics production data shape and volume.

C.  

Use Query Analyzer in production.

D.  

Request a partial Sandbox copy after the next Salesforce release.

Discussion 0
Questions 17

Universal Containers has many backlog items and competing stakeholders who cannot agree on priority.

What should an architect do to overcome this?

Options:

A.  

Take over prioritization for the stakeholders.

B.  

Facilitate the design of a prioritization model with the stakeholders.

C.  

Organize a sprint planning meeting with the Scrum team.

D.  

Allow the delivery teams to pick the best work for the business.

Discussion 0
Questions 18

The CEO at Universal Containers (UC) is receiving constant complaints from business stakeholders that the development teams are not frequently delivering value to the end-user. The CEO talked with the CTO, who argues the opposite, explaining that the development teams are delivering value every Sprint.

The architect suggests to the CTO to implement Kanban to solve this disagreement. How can Kanban help clarify whether value is being delivered to the business?

Options:

A.  

Kanban teams respond to unplanned work and changes by dropping everything and jumping on the new request, ensuring agility.

B.  

Kanban traits includes metrics, like lead time and throughput, which increases transparency.

C.  

Kanban can make use of the Salesforce Agile Accelerator to speed up delivery.

D.  

Kanban limits work in progress, so the executives will know the development team is not overworked.

Discussion 0
Questions 19

A technical lead is performing all code reviews for a team and is finding many errors and improvement points. This is delaying the team ' s Deliveries.

Which two actions can effectively contribute to the quality and agility of the team? Choose 2 answers

Options:

A.  

Choose the most senior developer to help the technical lead in the code review.

B.  

Create development standards and train teams in those standards.

C.  

Skip the code review and focus on functional tests and UAT.

D.  

Use static code analysis tool in the pipeline before manual code review.

Discussion 0
Questions 20

Universal Containers (UC) is looking for advice on how often it should refresh its sandboxes. UC currently uses a development lifecycle that starts with developer environments and moves to integration testing, QA testing, UAT, and then production. They have many scrum teams working concurrently and the teams do not agree on when refreshes should occur.

What two recommendations should the architect suggest? Choose 2 answers

Options:

A.  

Development environments should generally be refreshed after each working feature has been successfully migrated.

B.  

Sandboxes should be refreshed on the day when the refresh is allowed for that type of sandbox.

C.  

Productions is the only pristine environment.

D.  

Integration sandboxes should be refreshed rarely because of the burden of maintaining the various API.

Discussion 0
Questions 21

Universal Containers (UC) has decided to improve the quality of work by the development teams. As part of the effort, UC has acquired some code review software Licenses to help the developers with code quality.

Which are two recommended practices to follow when conducting secure code reviews? Choose 2 answers

Options:

A.  

Conduct a review that combines human efforts and automatic checks by the tool to detect all flaws.

B.  

Use the code review software as the tool to flag which developer has committed the errors, so the developer can improve.

C.  

Generate a code review checklist to ensure consistency between reviews and different reviewers.

D.  

Focus on the aggregated reviews to save time and effort, to remove the need to continuously monitor each meaningful change.

Discussion 0
Questions 22

Universal Containers has an active production org and they are planning to release some new features to it next month. The team is working to prepare a deployment plan and reached out to the technical architect for inputs on rollback strategy.

What should a technical architect recommend?

Options:

A.  

Backup the existing metadata using ANT Migration Tool. To roll back deployment, manually delete new components and deploy again to production using backed up metadata.

B.  

Backup the existing metadata using the ANT Migration Tool. To roll back deployment, deploy again to production using backed up metadata.

C.  

Create a sandbox from production to take the backup of existing metadata. To roll back deployment, manually delete new components and then deploy again to production Using metadata from this sandbox.

D.  

Create a sandbox from production to take the backup of existing metadata. To roll back deployment, use destructivechanges.xml to delete new components and then Deploy again to production using metadata from this sandbox.

Discussion 0
Questions 23

Universal Containers is delivering many changes to its Salesforce system. Adoption reports are discovering that many features are unused. The steering committee wants this to change and is looking to the architect for advice.

What should an architect recommend to overcome this?

Options:

A.  

Using Lightning Web Components for every user interface.

B.  

Adopting user centered design to understand user needs before building the solution.

C.  

Stop development until current features start being used.

D.  

Sending weekly communication emails reporting on least engaged users.

Discussion 0
Questions 24

Universal Containers uses multiple Salesforce orgs for its different lines of business (LOBS). In a recent analysis, the architect found that UC could have a more complete view of its customers by gathering customer data from different orgs.

What two options can an architect recommend to accomplish the customer 360-degree view? Choose 2 answers

Options:

A.  

Implement a Complete Graph multi-org strategy by allowing each org to connect directly to every other, reading and writing customer data from the orgs where it has originally created.

B.  

Migrate from multi-org to single-org strategy, consolidating customer data in the process.

C.  

Implement a Single Package multi-org strategy by developing and deploying to all orgs a managed package which reads and consolidates customer 360-degree view from the different orgs.

D.  

Implement a Hub-and-Spoke multi-org strategy by consolidating customer data in a single org, which will be the master of customer data, and using integration strategies to let the LOBS orgs read and write from it.

Discussion 0
Questions 25

Cloud Kicks is considering using an automated testing tool to help manage deployments between environments.

When should the architect recommend the use of an automated testing tool?

Options:

A.  

Automated tests should be run when branches are merged.

B.  

Automated tests should be run daily in all Developer Orgs.

C.  

Automated tests should be run only when merging into Full or Partial Copy sandboxes.

D.  

Automated tests should be run daily in all Developer Orgs, and when branches are merged.

Discussion 0
Questions 26

Cloud Kicks is switching to Salesforce from a different CRM. They have existing datasets for all standard Salesforce objects.

In which optimized order should the architect recommend these objects be loaded?

Options:

A.  

Accounts, Contacts, Leads, Products, Opportunities, Opportunity Line Items

B.  

Leads, Contacts, Accounts, Opportunities, Products, Opportunity Line Items

C.  

Leads, Accounts, Contacts, Products, Opportunities, Opportunity Line Items

D.  

Accounts, Contacts, Opportunities, Products, Opportunity Line Items, Leads

Discussion 0
Questions 27

Universal Containers is a Salesforce AppExchange partner and they are planning to launch a new app. The technical architect recommended that they use a partner development org for development.

What are the three benefits of using a partner development org over an individual development org in this scenario? Choose 3 answers

Options:

A.  

Partner development org has a greater number of licenses available for the team.

B.  

Partner development org offers higher API limit.

C.  

Only partner development org supports managed beta testing.

D.  

Partner development org never expires.

E.  

Partner development org offers more storage.

Discussion 0
Questions 28

An architect has been working on a large project for the past 6 months. This project must be live by the end of the current month.

Which two planning techniques should the architect use to ensure all metadata changes deploy smoothly and on time? Choose 2 answers

Options:

A.  

Create a new sandbox and perform a test deployment to that environment.

B.  

Ensure all code that is being deployed is checked into source control.

C.  

Upload a change set from sandbox to production as early as possible.

D.  

Validate the final deployment package against production prior to go-live

Discussion 0
Questions 29

Universal Containers has defined a software tool to support Agile processes, but the development team is not regularly updating the status of their work in progress.

What Scrum value is compromised by this bad practice, and why?

Options:

A.  

Courage, because the teams should be transparent about progress and speak up when they need help.

B.  

Openness, because the team is not open to a new methodology.

C.  

Focus, because the teams are not focusing in the agile process expected activities.

D.  

Commitment, because the team is not committed to follow the Agile methodology.

Discussion 0
Questions 30

Universal Containers (UC) is looking at implementing a large number of features using an AppExchange product. This product uses Sobjects to store and configure important business logic within the application.

Which two options should an architect recommend, as the source of truth for storing this reference data? Choose 2 answers

Options:

A.  

Store the records in sandboxes and production.

B.  

Store the records in a version control system.

C.  

Use a third-party product to manage these records.

D.  

Attach CSV files to the user stories in a project management system.

Discussion 0
Questions 31

Universal Containers (UC) is embarking on a large program of work, with different projects and different vendors. UC created a center of excellence (COE) that struggling with scope creep between the different projects.

What role should the architect suggest be added to the COE?

Options:

A.  

Change managers

B.  

Scrum master

C.  

Product owner

D.  

Release managers

Discussion 0
Questions 32

Universal Containers has a highly customized Salesforce org, with many different pieces of configuration and code.

Which configuration item should be covered by executable tests?

Options:

A.  

Active Process Builders

B.  

Validation Rules

C.  

Workflow Rules

D.  

Case Assignment Rules

Discussion 0
Questions 33

Universal Containers has seven orgs in different regions. Its processes are global and standardized but each region needs the flexibility to be able to understand the global code and customize some aspects for its regions.

Which development model is optimized for this need?

Options:

A.  

Create a centralized Git with all the code and where the global team approves the changes made by the local teams.

B.  

Use a managed package for global code and another managed package for all regions code.

C.  

Use unlocked packages to deploy the global code and allow each country to create its customized unlocked package extensions.

D.  

Use a managed package to deploy the global code and allow local teams to request the addition of code within that package.

Discussion 0
Questions 34

Which two statements are accurate about why Mock objects are needed when writing test classes? Choose 2 answers

Options:

A.  

Mock is needed whenever the code makes an HTTP callout.

B.  

Some methods are invoking long running processes, using Mock is a shortcut of bypassing the long executions.

C.  

Mock can also be used on the classes that extend the batchable interface to bypass the batch jobs.

D.  

Using a Mock allows the test class to bypass the dependencies of other objects, methods, state, or behaviors. Therefore, the developer has total control of his own code.

Discussion 0
Questions 35

In the effort of improving the code quality, Universal Containers (UC) has asked a third-party system integrator to perform some independent code reviews. One piece of the feedback is the development team is seemingly not doing enough negative unit testing.

Which are three usual symptoms of inadequate negative tests? Choose 3 answers

Options:

A.  

Developers often have to turn to the debug log for details of the failed Apex executions.

B.  

When an Apex batch job runs at a scheduled time, an increased number of Apex execution errors occur over all.

C.  

An Apex process runs into an un-handled exception when an HTTP callout has an unexpected status code in the response body.

D.  

Developers constantly ask the testers for a screenshot of the error and the exact steps of reproducing the error.

E.  

The delivered user interfaces are regularly not meeting the expectations of the business users.