ISTQB Certified Tester Foundation Level
Last Update May 7, 2024
Total Questions : 332
We are offering FREE CTFL-Foundation ISTQB exam questions. All you do is to just go and sign up. Give your details, prepare CTFL-Foundation free exam questions and then go for complete pool of ISTQB Certified Tester Foundation Level test questions that will help you more.
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test strategy document
b. The overall estimated costs, timescales and resource requirements
c. A detailed schedule of testing activities
d. The development deliverables to be tested
e. Which test staff members (names) will be involved and when
f. Level of requirements coverage achieved
Which THREE of the above mentioned characteristics relate to the master test plan? 1 credit
As part of the test strategy, entry and exit criteria will be defined for each test level. Which is NOT a valid reason for using entry and exit criteria? 1 credit
Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits
Which test management control option is most appropriate to adopt under these circumstances? 2 credits
Which of the following is least likely to be used as a technique to identify project and product risks? 1 credit
Risks should be constantly reviewed. Given the current situation, which one of the following factors is most likely to lead to a revised view of product risk? 3 credits
The business has asked for a weekly progress report. Which of the following would be appropriate as a measure of test coverage? 2 credits
Which of the following phases in the fundamental test process is considered to deliver a document which can be used as a major input for test process improvement? 1 credit
During test process improvement it is recommended to use standards where possible. Standards originate from various sources and they cover different subjects in relation to testing Pick TWO sources of software standards, useful to software testing from the ones mentioned below. 1 credit
In addition to risk, identify TWO other components of a testing strategy. 1 credit
Part of the testing strategy indicates that you are going to be using systematic test design techniques. Your manager has asked that you present the main advantages of using these techniques at the next board meeting. Identify THREE main benefits of using systematic test design techniques within this company. 2 credits (for 2 out of 3 correct 1 credit)
You have been asked to write a testing strategy for the company. Which statement best explains how risk can be addressed within the testing strategy? 1 credit
Given is the following defect removal chart reported at the end of system testing - showing total defects detected and closed defects (fixed and successfully retested). A number of open defects are classified as critical. All tests have been executed.
Based on the chart above, what is the most appropriate next test phase? 1 credit
Comparing TMMi and TPI, which is not a valid reason for choosing either TPI or TMMi? 2 credits
The test improvement project will take place in an organization developing a safety-critical avionics application. Which one of the following standards do you believe would be most appropriate to take into account for compliance during your assignment? 1 credit
Under which of the following circumstances is maintenance testing required? [K1]
Which statement BEST describes when test planning should be performed? [K1]
What factors should be considered to determine whether enough testing has been performed?
(i)The exit criteria.
(ii)The budget.
(iii)How big the test team is.
(iv)The product's risk profile.
(v)How good the testing tools are.
(vi)Sufficient details of the system status to allow decisions
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test
b. strategy document
c. The overall estimated costs, timescales and resource
d. requirements
e. A detailed schedule of testing activities
f. The development deliverables to be tested
g. Which test staff members (names) will be involved and when
h. Level of requirements coverage achieved
Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit
Which of the following statements BEST describes the difference between testing and debugging?
In general which part of the testing activity is most difficult to estimate? 1 credit
Which of the following would you least expect to form part of the analysis of initial tool costs? 1 credit
Select THREE issues from the options provided that should at least be raised. 1 credit
Which of the following options explain why it is often beneficial to have an independent test function in an organisation?
During the development of a software change for a system, the developer makes a mistake in his work, which leads to a fault in the code. Unfortunately the fault is not found by software testing and is released into live.
What is the definite consequence of this mistake?
Your task is to compile a test execution schedule for the current release of software.
The system specification states the following logical dependencies:
• An admin user must create/amend/delete a standard user.
• A standard user is necessary to perform all other actions.
The test plan requires that re-tests must be performed first, followed by the highest priority tests. To save time, the test plan states that tests should be scheduled to create test data for the subsequent tests in the schedule.
The following test cases have been designed, with an indication of priority (1 being the highest priority) and whether the test has previously failed.
Which test execution schedule meets the test plan requirements and logical dependencies?
Based on the information given in the scenario, identify how the team could be improved most effectively? 2 credits
Which of the following is a valid drawback of independent testing? 1 credit
Relying only on the information provided in the scenario, select the TWO items and/or features for which sufficient information is available to proceed with test design. 2 credits
Given the following figures for the testing on a project, and assuming the failure rate for initial tests remains constant and that all retests pass, what number of tests remain to be run? 3 credits
Which of the following are valid reasons for adopting a different life cycle (from the V model), for increments after the first year? 2 credits
i. We do not have a clear understanding of the requirements from a customer perspective.
ii. We see the risk of delivering requested functionality late as being higher than the risk of delivering a lower quality product.
iii. We do not have a budget for additional regression testing which is needed to ensure that existing functionality is not compromised by future iterations.
iv. The company test strategy does not fit well within the V life cycle model.
Which of the following would you expect to see in the master test plan? 1 credit
Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits
Which of the following team roles would be most appropriate to enhance the team and why? 2 credits
What would be a test approach regarding the test design techniques to be applied that would fit an item with the highest risk? 2 credits
You have been given responsibility for the non-functional testing of a safety-critical monitoring & diagnostics package in the medical area. Which of the following would you least expect to see addressed in the test plan? 1 credit
Instead of having an independent test team within the company, the company is considering to outsource testing. What are THREE key challenges that are typical for outsourcing? 1 credit
You have investigated different possibilities and selected four of them to present to IT management. Which of the proposals will you most likely give your highest recommendations? 3 credits
A test assessment has been carried out using the selected model as a reference framework. A number of recommendations have been identified and you are asked to prioritize them. Based on your knowledge of the project, you are expecting severe resistance to change. Which of the following would be the most important selection criterion for defining the priority of the recommendations? 2 credits
The development manager is managing the review of the responses received from bidders, and has asked the in-house test manager to provide a review checklist for the test management aspects of the responses. Which of the following checkpoints would be appropriate? 2 credits
Regarding the process described above, what is the most important recommendation you would make using IEEE 1044 as a guide? 2 credits