Certified Associate in Project Management (CAPM)
Last Update Aug 24, 2026
Total Questions : 1337
We are offering FREE CAPM PMI exam questions. All you do is to just go and sign up. Give your details, prepare CAPM free exam questions and then go for complete pool of Certified Associate in Project Management (CAPM) test questions that will help you more.
The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?
Which two processes should be used to influence costs in the early stages of a project?
The Perform Integrated Change Control process occurs in which Process Group?
Which of the following is a tool or technique of the Define Activities process?
A project manager is seeking assistance from the business analyst for an IT project. What assistance can the business analyst provide?
A project manager is working with the team to prepare the estimates for various work items. The team needs to compare the relative sizing of the items. What should the project manager suggest the team use?
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?
As the project progresses, which of the following is routinely collected from the project activities?
Which process determines the risks that may affect the project and documents their characteristics?
What process in Project Schedule Management identifies and documents specific actions to be performed to produce a project’s deliverables?
Which of the following is an input to the Direct and Manage Project Execution process?
Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
A software development team is working on a project to adapt an application to new, government-established data-privacy rules. What factor led to the creation of this project?
Two members of the team are having a conflict..............or partially resolve the problem
Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.
Which technique should the project manager use?
Directing another person to get from one point to another using a known set of expected behaviors and the ability to lead a team and inspire them to do their jobs well is related to?
Which of the following is least influenced by a project manager, according to the project manager ' s sphere of influence?
Which of the following must be included in the risk register when the project manager completes the Identify Risks process?
A project manager is leading a project in a volatile industry. Industry standards are updated often, which requires the project team to make frequent adjustments to their work.
What should the project manager create to manage the possible changes?
The key benefit of the Monitoring and Controlling Process Group is the ability to:
Stakeholder communication requirements should be included as a component of:
To ensure stakeholder satisfaction; identified stakeholder needs should all be
After recommending to Tan (client) to leave the feature out, what should the project manager do?

The basis of identification for current or potential problems to support later claims or new procurements is provided by:
Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:
The process to ensure that appropriate quality standards and operational definitions are used is:
What prototyping technique shows a sequence or navigations through a series of images or illustrations?
Which of the following involves making information available to project stakeholders in a timely manner?
The following is a network diagram for a project.

The shortest non-critical path for the project is how many days in duration?
A project manager can choose from several techniques to resolve conflicts between team members. Which technique can result in a win-win solution?
Which of the following project documents is an input to the Control Scope process?
For which kind of quantitative risk analysis chart can a tornado diagram represent values?
What is one reason why stakeholders must be identified when performing business analysis?
An employee was hired to work on ongoing, repetitive activities in the accounting department. The employee ' s duties are managing and controlling day-to-day activities. Which type of managing is the employee performing?
Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?
How can a project manager represent a contingency reserve in the schedule?
How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?
During what project management process does the project manager invest the most effort into creating the work breakdown structure (WBS)?
An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:
Which three processes are generally included in risk management? (Choose three)
Which of the following characteristics are found in a functional organizational structure?
The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:
A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?
A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?
In adaptive projects, who should approve the prioritization of the backlog?
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?
Which defines the portion of work included in a contract for items being purchased or acquired?
Which organizational process asset can make an impact on the outcome of a project?
The following chart contains information about the tasks in a project.

Based on the chart, what is the schedulevariance (SV) for Task 8?
What is a characteristic of the relationship among projects, programs, and portfolios?
During the execution of a predicted project, the need for a new product feature has been proposed by the customer. What should the project manager do next?
During project planning, team members seemed clear on deliverables. However, as the project progressed deeper into the execution phase, team members expressed the need for smaller components to better understand what must be delivered.
What should the project manager do?
Project governance refers to framework.......which of the following is a portfolio?
Pioject governance refers lo framework, functions, and processes that guide project management activates with a defined hierarchy between projects, programs and poctfotos. According to this hierarchy, which ot Die following is a portfolio?
Product requirements specify a functionality that depends upon expertise that is unavailable internally. What process should be implemented to generate a make-or-buy decision?
Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?
Which enterprise environmental factors should be considered when creating a new procurement contract?
Technical capability, past performance, and intellectual property rights are examples of:
A project manager should communicate to stakeholders about resolved project issues by updating the:
What can a requirements traceability matrix enable regardless of the project methodology being used?
Due to today ' s competitive global market, organizations require more than technical project management skills. Which of the following skills can support long-range strategic objectives that contribute to the bottom line?
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
Which process involves developing an approximation of the monetary resources needed to complete project activities?
The creation of an internet site to engage stakeholders on a project is an example of which type of communication?
Power, urgency, and legitimacy are attributes of which stakeholder classification model?
When presenting a product roadmap to an adaptive team, which form of communication is the most appropriate?
During a retrospective, the team finds that all of the user stories are not complete. What should be done with the incomplete user stories?
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
The project manager and project team are developing approximations of the cost of resources needed to complete the project work. On which process are they working?
Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?
A firm contracted an event management company to conduct the annual sales day event. The agreement states that the event management company will charge the firm for the actuals and receive 8% of the total cost. What type of contract Is this?
A technique used to determine the cause and degree of difference between baseline and actual performance is:
Which project document is updated in the Control Stakeholder Engagement process?
A project sponsor has asked the project manager to determine how soon the project can be completed. Which of the following methods can a project manager use to find this information?
The following chart contains information about the tasks in a project.

Based on the chart, what is the cost performance index (CPI) for Task 2?
Which additional considerations should the project manager make when managing risks in an agile/adaptive project?
Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?
Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?
Which of the following reduces the probability of potential consequences of project risk events?
A software project has completed the first iteration, and the testing manager noted that some features were not incorporated and would not approve the software. The business unit manager who will use the software is satisfied with the software and wants to start the rollout.
What should the project manager do?
Which tool is used to develop technical details within the project management plan?
The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?
Which Manage Communications tool or technique focuses on identifying and managing barriers?
An adaptive project manager is migrating the company ' s new website. The project manager must work with the team to invest full capacity on this project because it is the company ' s top-ranked project in the portfolio. In order to increase throughput and provide consistent delivery, the project manager needs to assign members who are currently involved with other projects.
How should the project manager assign the team members to this project?
A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge. Which dimension of PMI’s Talent Triangle best relates to this need to improve?
An executive sponsor wants to be briefed on how the product will change over time. Which document should the business analyst use to prepare their presentation?
It’s time to perform code review on a software project that has over three million lines of code written. Which management tool should the project manager use?
Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?
In an interactive communication model, how is the sender ensured that the message was understood by the receiver?
A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager.
What should the project manager do to address this issue?
A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure an effective requirements elicitation.
What should the business analyst do?
When paying a consultation fee to a technical expert, what type of contract is often used ' ?
Change requests are an output from which Project Integration Management process?
Which subsidiary management plan.... during the project ilfe cycle?
Which Subsidiary management plan would a project manager create to manage Information dissemination during the project life cycle?
Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?
A project manager has joined the sponsor to verify the last deliverable of the project. The sponsor is measuring and examining the deliverable to determine whether it meets the requirements and product acceptance criteria. Which activity is being performed?
Which of the following Process Groups covers all nine Project Management Knowledge Areas?
A project team is working on a new driverless vehicle and is organizing a workshop with experts to analyze the data received from the prototype. Who should the project manager invite to provide expert advice?
What are the project management processes associated with project quantity management?
A complete set of concepts, terms, and activities that make up an area of specialization is known as:
The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:
What should be the frequency for meetings when transitioning from Scrum to Kanban?
Which type of analysis is used as a general management technique within the Plan Procurements process?
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?
A project manager has reached an agreement on the requirements and now needs to define the workflow for the end user. A critical step must be completed and validated by the end user before proceeding.
Which modeling tool best describes this process?
A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?
A stakeholder is reading project documents given by the project manager. The stakeholder is
curious about the difference between a verified deliverable and an accepted deliverable.
Which of the following definitions can the project manager use to explain the difference?
One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?
Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?
Which of the following response strategies are appropriate for negative risks or threats?
Stakeholder identification and engagement should begin during what phase of the project?
Which document describes the necessary information to determine if a project is worth the required investment?
A project manager needs to request outside support......manager need to create
A project manager needs to request outside support for a statement ot work (SOW) that is not precise. Which kind of contract does the project manager need to create?
The project manager and the project team are in the process of documenting procurement decisions. Which of the following will be the procurement strategy?
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
The milestone list is an input to which process from the Planning Process Group?
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
An adaptive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project manager coaches the team to complete the planning.
Which two of the following items should be included in the planning? (Choose two)
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?
Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?
Which of the following is a narrative description of products, services, or results to be delivered by a project?
In one of the project meetings during project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?
Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?
The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?
A project manager is performing a specific process and has..........is being referred to?
A project manager is performing a specific process and has a list of accepted deliverables One of the stakeholders points out that they have just reviewed the verified deliverables, and come up with the list of accepted deliverables Which process is being referred to?
The project manager is looking at a precedence diagram.... the duration of this task?
The project manager is looking at a precedence diagram and needs to report back about the project status The total duration of the task is ten days, and both Activity A and B need be completed. Activity A has a duration of six days, and activity B has a duration of four days Activity B has a finish-to-start relationship with activity A Under current circumstances, activity A will take about seven days to complete.
What is the outcome of the duration of this task ' ?
The project leam is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive, iterative methods. What is the team trying to address?
Which Project Time Management process includes bottom-up estimating as a tool or technique?
Which Process Group ' s purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?
How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?
What cost control technique is used to compare actual project performance to planned or expected performance?
In the Plan Procurement Management process, which source selection criteria analyzes if the seller ' s proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?
The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:
Which type of estimating is used to improve the accuracy of an activity ' s duration?
The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:
Which of the following correctly explains the term " progressive elaboration ' ?
Which enterprise environmental factors are considered during Estimate Costs?
In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
Which of the following is contained within the communications management plan?
Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
The following chart contains information about the tasks in a project.

Based on the chart, what is the cost variance (CV) for Task 6?
A team member, who is close to an influential stakeholder, has joined the project team. The stakeholder is routing requests for multiple reports through the new team member, and the team member reaches out to the project manager regarding this. What should the project manager do first?
Which tools or techniques are used in the Plan Schedule Management process?
The table represents the possible durations of a specific project task.
Using the three-point estimating technique what is the expected number of days it should take to complete the task?
A project manager oversees a project in an adaptive environment. After each iteration, which type of meeting should the project manager conduct?
Which process numerically analyzes the effect of identified risks on overall project objectives?
Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?
What method for categorizing stakeholders is suitable for small projects with simple relationships among stakeholders ' ?
What type of project structure is a hierarchically organized depiction of the resources by type?
A project team is meeting to seek solutions on a new problem that occurred recently. The meeting is comprised of two parts: the first is a generation of ideas and the second is an analysis.
Which technique is the team using?
In the Define Activities process, the schedule management plan is used to:
If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?
Which of the following is an input to Direct and Manage Project Execution?
The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:
A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure effective requirements elicitation. What should the business analyst do?
A project manager in a bank is developing market risk-related processes and is midway through the project. More than half of the product backlog items are developed and delivered to the customer. Due to regulatory and compliance changes in the industry, new backlog items were added to the product backlog with a significant impact on the project schedule. Who should the project manager send this change request to?
Variance and trend analysis is a tool and technique used in which process?
Which of the following statements correctly characterizes pull communication?
A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:
The procurement process that documents agreements and related documentation for future reference is known as:
Which of the following is used as input to prepare a cost management plan?
A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?
The process of identifying and documenting relationships among the project activities is known as:
A Project manager received a change request from a key stakeholder, documented it reviewed it with the team, and then presented if for decision. What was project manager trying to do?
A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.
Which technique is the project manager using?
Given the following information.
Activity A takes one week.
Activity B takes three weeks.
Activity C takes two weeks.
Activity D takes five weeks.
Activity A starts at the same time as Activity B.
Activity C follows Activity B and Activity A.
Activity D follows Activity C.
How long will it take to complete the project?
After winning a large government contract, a company needs to hire a portfolio manager What vital qualification should candidates possess?
The project manager is leading a construction project that has been ongoing for eight years. The project manager needs to calculate the correct static payback period and consults the cash flow statement of the construction project investment.
What equation should the project manager use?
Cash Flow Statement of the Project Investment Unit: US$ Billion
Period: 0, 1, 2, 3, 4, 5, 6, 7, 8
Cash inflow: 0, 0, 0, 0, 1200, 1200, 1200, 1200
Cash outflow: 0, 700, 800, 500, 700, 700, 700, 700, 700
Net cash flow (NCF): 0, -700, -800, 300, 500, 500, 500, 500, 500
Accumulative total of net cash flow: 0, -700, -1500, -1200, -700, -200, 300, 800, 1300
The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
A project manager is reviewing a few techniques that can be used to evaluate solution results. The intent is to uncover whether the solution responds properly to unintended cases.
Which evaluation technique should be used here?
An international company that is starting to practice an adaptive approach has several development teams located globally. They are having problems with multiple time zones and repetitive project schedule slippage.
What effective tools should the project teams use to collaborate?
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three)
During the execution phase of a multibillion-dollar project, the project manager encountered performance issues with some of the team members. In a performance review meeting, the project manager noticed that the team members do not follow SMART objectives.
What are SMART objectives?
When developing a schedule which tools and techniques should a project manager use?
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
Which components of the project management plan are inputs used when creating the stakeholder engagement plan?
A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller ' s performance. The most appropriate agreement with the supplier is:
A Project manager is using agile in a project. As development life cycle is adaptive, how does the project manager handle key stakeholder involvement?
In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?
Which can be used to convert a verified deliverable to an accepted deliverable?
How can a project manager determine if the project activities comply with organizational and project policies, processes, and procedures?
What do top project managers do to maximize their sphere of influence within a project team?
During a project ' s execution phase, the project manager reviews the communications management plan for communication technology factors. What can affect the choice of communications?
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?
Which project life cycle follows a plan reviewed and approved by the stakeholders?
When planning communications management what input identifies key stakeholders?
A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager ' s key responsibility during this phase?
Information collected on the status of project activities being performed to accomplish the project work is known as what?
Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?
A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members know their roles and responsibilities. What are the four elements of a RACI chart?
Select three processes that are associated with Project Schedule Management.
A team has been tasked with designing a product to address a problem they have never faced before. The project team is struggling to get traction as the solutions are not clear. What should the project manager do next?
The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:
A company has implemented an adaptive project management framework for a new project. When planning for an iteration, how should risks be addressed? Choose two.
Which of the following is used as an input to prepare a cost management plan?
Which are the most important competencies required for a project manager?
A project manager has recently been assigned a new agile project and needs to determine an appropriate leadership style. The project manager aims to empower the team members so they feel committed and motivated to deliver value.
Which leadership style should be used for this project?
What internal enterprise environmental factor (EEF) can impact a project?
A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?
When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process.
A project manager is reviewing a past project with similar.... team choosing for tailoring?
A project manager is reviewing a past project with similar requirements to the project that is currently chartered. The project team decided to adopt quality tools, techniques and templates recommended at the organizational level after reviewing the lessons learned of the previous project What specific area of quality, is the project team choosing for tailoring?
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
Lessons learned documentation is gathered during which of the following Project Management Process Groups?
A project manager called for a team meeting...................method did the team use
A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated. Which estimation method did the team use?
In a project, the cost performance indicator (CPI) is less than 1 and the schedule performance indicator (SPI) is more than 1. What is the status of the project?
Which of the following is part of the project sponsor ' s responsibility?
Which of the following are processes associated with Project Cost Management?
A project manager is in the process of onboarding resources to start work on a project. Which of the following components of a project management plan will the project manager update after completing this activity?
Which two of the following can be used as communication tools between the business analyst and the rest of the project team? (Choose two)
In which type of organization does the project manager have the maximum influence
A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?
A project manager is creating a project charter to provide a direct link between the project and the organization ' s strategic objectives. What must be considered when creating this document?
A project manager was assigned to a project with high uncertainty. What is the recommended method to calculate the project budget?
A business manager wants to start a project to launch a new product and submits a business case to the Portfolio Steering Committee for review. The committee asks the manager for details about the expected business value of the project.
How can the manager document the business value for the Portfolio Steering Committee?
Which statement about identification and engagement of stakeholders during a project is correct?
A quality management plan describes how the project and product scopes are managed in accordance with which of the following items?
The zero duration of milestones in project planning occurs because milestones:
A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?
Processes in the Planning Process Group are typically carried out during which part of the project life cycle?
Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?
A project team for a marketing company is acquiring leaflets and materials from competitors. The team is working on a project to release new products, and they are trying to get ideas on how to most efficiently market these new products.
Which activity is the project team conducting?
Which of the following investigates the likelihood that each specific risk will occur?
Which of the following is an output of the Distribute Information process?
A project manager is newly assigned to a project. Which document can help the project manager understand the project scope?
A project team is working on a complex product and the work breakdown structure (WBS) is finalized. The team determines that the best approach is to use an adaptive delivery method and is now tasked with converting the WBS for adaptive delivery.
How can the team manage the conversion of the existing WBS to an adaptive approach?
A project manager is preparing to meet with three crucial project stakeholders on a new project Which tools and techniques can the project manager use to capture stakeholder interest?
Projects programs subsidiary portfolios.... objectives refer to?
Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives refers to?
Which tool or technique is effective in a project in which the deliverable is not a service or result?
Which of the following set of elements is part of an effective communications management plan?
When managing costs in an agile environment, what should a project manager consider?
The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:
In which domain of project management would a Pareto chart provide useful information?
Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
Which illustrates the connection between work that needs to be done and its project team members?
A temporary endeavor that creates a unique product or service is called a:
What tool or technique will establish expected behaviors for project team members?
A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?
Which tools and techniques will a project manager use to develop a project charter?
The Agile principle " welcome changing requirement, even late in development " relates to which agile manifesto?
Which cost estimate technique includes contingencies to account for cost uncertainty?
Which of the following sets are inputs to the Collect Requirements process?
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
The project manager is new to the company in order to effectively manage the project, which components of the organizational governance framework does the project manager need to take into account?
Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
What provides information regarding the ways people, teams, and organizational units behave?
Which tools and techniques should a project manager use when estimating costs?
What is the most important skill that project managers should possess to lead stakeholders throughout a project?
Which are the competing constraints that project manager should address when tailoring a project?
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
The project manager is explaining to others the essential business aspects of the project. To which skill category does this ability belong?
Which of the following is an input to Direct and Manage Project Execution?
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
What is a tailoring consideration for the application of Project Risk Management processes?
A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?
Agile release planning provides a high-level summary timeline of the release schedule based on.
The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.
What are these elements called?
It you established a contingency reserve including time, money, and resources, how are you handling risk?
Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?
In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?
Which of the following is the key construction to controlling the costs and achieving the schedule in projects with high variability?
Which standard has interrelationships to other project management disciplines such as program management and portfolio management?
The degree, amount, or volume of risk that an organization or individual will withstand is called risk:
Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?
Which of the following is an information gathering technique in Identify Risks?
Which quality tool incorporates the upper and lower specification limits allowed within an agreement?
A business case is being assembled. Which two elements are necessary to complete this process? (Choose two)
Which is the correct formula for calculating expected activity cost for three-point estimating?
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?
Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:
For what project management process is work performance information an output?
The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?
Which tools and techniques should a project manager use to monitor risks?
What is the number of stakeholders, if the project has 28 potential communication channels?
A project manager is assigned to a strategic project Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project.
Which entities will the project manager attempt to influence?
How should a project manager plan communication for a project which has uncertain requirements?
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?
A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:
Which of the following factors within a company cloud trigger the creation of a project?
A project is composed of three phases that are implemented in parallel without affecting one another. The baselines for each individual phase have been approved by the major stakeholders, and there is a minimal ability to vary the baselines during the execution of the project.
Which methodology did the project manager adopt?
Which of the following are components of the technical project management skill?
A project manager is leading a technology project that is about to enter the execution phase. The project requires the procurement of certain key components from an external vendor. The project manager has been notified that because of a government regulation, some parts can no longer be used in the country and the vendor will be unable to deliver them.
What should the project manager do?
When establishing a contingency reserve, including time, money and resources, how is the risk being handled?
What should a project manager do to prepare a risk management plan with a lot of technical uncertainty?