Certified Associate in Project Management (CAPM)
Last Update Nov 30, 2025
Total Questions : 1305
We are offering FREE CAPM PMI exam questions. All you do is to just go and sign up. Give your details, prepare CAPM free exam questions and then go for complete pool of Certified Associate in Project Management (CAPM) test questions that will help you more.
In which of the Risk Management processes is the project charter used as an input?
Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?
The following is a network diagram for a project.

The total float for the project is how many days?
The following is a network diagram for a project.

The free float for Activity H is how many days?
Power, urgency, and legitimacy are attributes of which stakeholder classification model?
In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?
The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:
Which components of the project management plan are inputs used when creating the stakeholder engagement plan?
What communication methods would a project manager use for overall effective project communication?
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:
What scenario describes when a project must be created due to market demand?
Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?
What conflict resolution technique involves delaying the issue or letting others resolve it?
Which of the following is an input to Direct and Manage Project Execution?
When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process.
Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?
The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?
Which document includes the project scope, major deliverables, assumptions, and constraints?
Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?
Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?
Which defines the portion of work included in a contract for items being purchased or acquired?
Which organizational process assets update is performed during the Close Procurements process?
Once the make-or-buy analysis is completed, which document defines the project delivery method?
In a project using agile methodology, who may perform the quality control activities?
Which tool should a project manager consider to deal with multiple sources of risk?
A project manager is assigned to a strategic project Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project.
Which entities will the project manager attempt to influence?
Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:
Which are examples of processes that may be used once or at predefined points in the project life cycle?
A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:
Which process is included in the Project Integration Management Knowledge Area?
Information collected on the status of project activities being performed to accomplish the project work is known as what?
Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?
A firm contracted an event management company to conduct the annual sales day event. The agreement states that the event management company will charge the firm for the actuals and receive 8% of the total cost. What type of contract Is this?
A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
Which of the following involves making information available to project stakeholders in a timely manner?
Which enterprise environmental factors are considered during Estimate Costs?
Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?
Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?
In which organizational structure would the project manager have most authority?
A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?
A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?
The project leam is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive, iterative methods. What is the team trying to address?
In an organization with a projectized organizational structure, who controls the project budget?
A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables.
Which process is the project manager executing?
Due to today's competitive global market, organizations require more than technical project management skills. Which of the following skills can support long-range strategic objectives that contribute to the bottom line?
Which of the following describes the similarities of the process groups and project life cycle?
Which tool is used to develop technical details within the project management plan?
What charts and (igures should project managers use during the Perform Quantitative Risk Analysis process?
A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?
At which point of the project is the uncertainty the highest and the risk of failing the greatest?
Match the project manager's sphere of influence with the associated primary role.

What is a tailoring consideration for the application of Project Risk Management processes?
A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:
Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?
A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?
Which statement about identification and engagement of stakeholders during a project is correct?
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?
Following a project planning meeting with the team, a few team members approach the project manager to follow up on actions required. How can the project manager assess the effectiveness of the meeting?
A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?
Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?
Which quality tool incorporates the upper and lower specification limits allowed within an agreement?
Which tools or techniques are used during the Close Project or Phase process?
What is the term assigned to products or services having the same functional use but different technical characteristics?
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?
Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?
What cost control technique is used to compare actual project performance to planned or expected performance?
The creation of an internet site to engage stakeholders on a project is an example of which type of communication?
The integrative nature of project management requires which Process Group to interact with the other Process Groups?
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
A procurement management plan is a subsidiary of which other type of plan?
Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
What should a project manager do to prepare a risk management plan with a lot of technical uncertainty?
A project manager is managing a small project that has a time constraint. What should the project manager do to ensure the delivery is on time?
What tern describes an intentional activity to modify a nonconforming product or product component?
A product owner reviews the list of stakeholders to confirm their continued involvement with the product team. A new stakeholder is identified as actively involved in the next product release.
What should the project manager do next to engage the new stakeholder?
The project manager needs to manage a critical issue immediately, and this requires action from the upper management of a specific stakeholder group. Which plan should plan the project manager consult?
A new project manager is assigned to a high-visibility project. The project manager starts with the requirements analysis process. Who should the project manager onboard to assist with the requirements traceability matrix or analysis?
A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members knows their roles and responsibilities.
What are the four elements of a RACI chart?
A project manager is preparing a monthly status report for the project, which includes project performance compared to the baseline schedule. How can the project manager calculate the schedule variance (SV) for tasks on the critical path?
Which subsidiary management plan.... during the project ilfe cycle?
Which Subsidiary management plan would a project manager create to manage Information dissemination during the project life cycle?
An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project. What data should be included in this information radiator?
A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:
A project manager is responsible for delivering new software for their company. Based on previous experiences, the project manager decides to use the dynamic systems development method (DSDM). The project manager will use this method to prioritize the scope to meet project constraints.
Which elements are included in the DSDM framework?
Which of the following can a project manager use to represent dellned team member roles in a group of tasks?
Which of the following factors within a company cloud trigger the creation of a project?
A project manager is working on the communications management plan. Which of these documents are inputs to consider?
The project manager is creating the communications management plan Which group of inputs Is required to begin?
A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members know their roles and responsibilities. What are the four elements of a RACI chart?
An organization's project management office (PMO) has issued guidelines that require a specific template to be used for onboarding resources for a project. Where can the project manager find this template?
During the planning phase, a project manager must create a work breakdown structure (WBS) to improve management of the project's components. What should be included in the WBS?
What type of stakeholder is part of a project manager 's sphere of influence on a project?
A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure effective requirements elicitation. What should the business analyst do?
A stakeholder is reading project documents given by the project manager. The stakeholder is
curious about the difference between a verified deliverable and an accepted deliverable.
Which of the following definitions can the project manager use to explain the difference?
A project manager oversees a project in an adaptive environment. After each iteration, which type of meeting should the project manager conduct?
A business analyst needs to ensure the project team understands the most critical roles and responsibilities within the requirements change process. Which responsibility is the most important?
What is the discipline that focuses on the interdependences between projects to determine the optimal approach for managing them?
A project manager has reached an agreement on the requirements and now needs to define the workflow for the end user. A critical step must be completed and validated by the end user before proceeding.
Which modeling tool best describes this process?
At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?
Which statement describes the relationship between Manage Quality process and Control process?
The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.
What are these elements called?
What purpose does the hierarchical locus of stakeholder communications serve?
A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?
Which tasks should a project manager accomplish in order to manage project scope correctly?
A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?
Progressively elaborating high-level information into detailed plans is performed by the:
The following is a network diagram for a project.

How many possible paths are identified for this project?
Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?
Specification of both the deliverables and the processes is the focus of:
The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
The process of obtaining seller responses, selecting a seller, and awarding a contract is called:
Activity cost estimates and the project schedule are inputs to which Project Cost Management process?
In the Define Activities process, the schedule management plan is used to:
The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:
A project manager should communicate to stakeholders about resolved project issues by updating the:
Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?
The zero duration of milestones in project planning occurs because milestones:
A project manager requesting industry groups and consultants to recommend project intervention is relying on:
A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
When closing a project or phase, part of the process may require the use of which type of analysis?
The following is a network diagram for a project.

What is the critical path for the project?
Technical capability, past performance, and intellectual property rights are examples of:
Stakeholder communication requirements should be included as a component of:
A risk that arises as a direct result of implementing a risk response is called a:
The following chart contains information about the tasks in a project.

Based on the chart, what is the schedulevariance (SV) for Task 8?
In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?
Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?
The following is a network diagram for a project.

The total float for the project is how many days?
Whose approval may be required for change requests after change control board (CCB) approval?
A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:
Which change request is an intentional activity that realigns the performance of the project work with the project management plan?
The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:
Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?
A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:
Which project document is updated in the Control Stakeholder Engagement process?
The following is a network diagram for a project.

The critical path for the project is how many days in duration?
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:
The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?
In which of the risk management processes is the processes is the project charter used as an input?
Which of the following is an input to the Develop Project Charter process?
A project team is reviewing project performance. During the execution phase, the project team discovers that there is an off-the-shelf (OTS) product, which could reduce the timeline for development.
What should the project manager do next?
The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:
Two resources are performing a peer review of an artifact. What should be the outcome of the peer review?
In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Which of the following response strategies are appropriate for negative risks or threats?
Who determines which dependencies are mandatory during the Sequence Activities process?
Which of the following set of items belongs to the communications management plan?
Which of the following is least influenced by a project manager, according to the project manager's sphere of influence?
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
Which type of dependency is contractually required or inherent in the nature of the work?
A project team is working on a new driverless vehicle and is organizing a workshop with experts to analyze the data received from the prototype. Who should the project manager invite to provide expert advice?
In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?
An adaptive project team is meeting for the first time and deciding on the project management approach. After defining the project artifacts, one team member argues that the events are missing. The scrum master coaches the team to complete the planning.
Which two of the following elements should be included? (Choose two)
Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?
Activity cost estimates are quantitative assessments of the probable costs required to:
Which organizational process asset can make an impact on the outcome of a project?
The project team is inspecting the completed project scope to determine if the requirements have been satisfied. What is the result of this inspection?
Exhibit A is an example of which of the following types of Sequence Activities?

Which risk response strategy is common for both positive and negative risks?
When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?
Which process is engaged when a project team member makes a change to project budget with project manager's approval
The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?
Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?
Which type of project management office (PMO) supplies templates, best practices, and training to project teams?
Which characteristic defines the Delphi technique of group decision-making?
In one of the project meetings during project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?
Which Process Group and Knowledge Area include the Sequence Activities process?
Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?
Which tool or technique is effective in a project in which the deliverable is not a service or result?
An employee was hired to work on ongoing, repetitive activities in the accounting department. The employee's duties are managing and controlling day-to-day activities. Which type of managing is the employee performing?
Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?
During what project management process does the project team begin identifying risks?
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
Which three of the following are key traits of a project leader? (Choose three)
The project manager is looking at a precedence diagram.... the duration of this task?
The project manager is looking at a precedence diagram and needs to report back about the project status The total duration of the task is ten days, and both Activity A and B need be completed. Activity A has a duration of six days, and activity B has a duration of four days Activity B has a finish-to-start relationship with activity A Under current circumstances, activity A will take about seven days to complete.
What is the outcome of the duration of this task'?
Which additional considerations should the project manager make when managing risks in an agile/adaptive project?
Which of the following lists represents trends and emerging practices in Project Risk Management?
What is the Project Schedule Management practice used to deliver incremental value to the customer'?
Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
Processes in the Planning Process Group are typically carried out during which part of the project life cycle?
Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:
A project manager builds consensus and overcomes obstacles by employing which communication technique?
Which process in Project Time Management includes reserve analysis as a tool or technique?
Which tool or technique is used to manage change requests and the resulting decisions?
The process of prioritizing risks for further analysis or action is known as:
Funding limit reconciliation is a tool and technique used in which process?
How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?
Which document defines how a project is executed, monitored and controlled, and closed?
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
Which of the following reduces the probability of potential consequences of project risk events?
Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?
While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?
The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:
When does the project team determine which dependencies are discretionary?
The basis of identification for current or potential problems to support later claims or new procurements is provided by:
Which tool or technique is used in the Develop Project Management Plan process?
Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
Which input will be used when tasked with developing the human resource plan?
A technique used to determine the cause and degree of difference between baseline and actual performance is:
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
Which of the following includes how requirements activities will be planned, tracked, and reported?
Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?
A temporary endeavor that creates a unique product or service is called a:
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
Which tools or techniques are used in the Plan Schedule Management process?
The process to ensure that appropriate quality standards and operational definitions are used is:
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
A large portion of a projects budget is typically expended on the processes in which Process Group?
The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?
The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
Which of the following is a strategy to deal with positive risks or opportunities?
Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?
Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?
In the basic communication model, which term refers to the method that is used to convey the message?
The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:
Which of the following types of a dependency determination is used to define the sequence of activities?
Which of the following is an input to the Perform Qualitative Risk Analysis process?
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
The milestone list is an input to which process from the Planning Process Group?
In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?
The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
Which of the following tools and techniques is used in the Verify Scope process?
Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
Which of the following is an information gathering technique in Identify Risks?
Documented identification of a flaw in a project component together with a recommendation is termed a:
How is the schedule variance calculated using the earned value technique?
Managing procurement relationships and monitoring contract performance are part of which process?
Project contracts generally fall into which of the following three broad categories?
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
The process of identifying the stakeholders' information needs is completed during:
A tool or technique in Perform Quality Control that a project manager would use is:
Which is the correct formula for calculating expected activity cost for three-point estimating?
When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
What is the responsibility of the project manager and the functional manager respectively?
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
Which of the following Process Groups covers all nine Project Management Knowledge Areas?
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?
The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager's disposal?
When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:
Lessons learned documentation is gathered during which of the following Project Management Process Groups?
Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?
Which technique helps to determine the risks that have the most potential impact on a project?
To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:
Which type of chart is a graphic representation of a process showing the relationships among process steps?
In which process is a project manager identified and given the authority to apply resources to project activities?
Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?