SAP Certified Application Associate - SAP S/4HANA Project Systems Question and Answers

SAP Certified Application Associate - SAP S/4HANA Project Systems

Last Update Apr 30, 2024
Total Questions : 110

We are offering FREE C_TS412_2021 SAP exam questions. All you do is to just go and sign up. Give your details, prepare C_TS412_2021 free exam questions and then go for complete pool of SAP Certified Application Associate - SAP S/4HANA Project Systems test questions that will help you more.

C_TS412_2021 pdf

C_TS412_2021 PDF

$35  $99.99
C_TS412_2021 Engine

C_TS412_2021 Testing Engine

$42  $119.99
C_TS412_2021 PDF + Engine

C_TS412_2021 PDF + Testing Engine

$56  $159.99
Questions 1

For which objects can billing plans be created? Note: There are 2 correct answers to this question

Options:

A.  

WBS elements

B.  

Project definition

C.  

Sales order items

D.  

Milestones

Discussion 0
Questions 2

You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?

Note : there are 2 correct answers for this question.

Options:

A.  

The procurement type in the material master is set to in-house Production.

B.  

The item category of the materials is set tstock item.

C.  

The material have no material number.

D.  

The item category of the materials is set tnon-stock item.

Discussion 0
Questions 3

Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

Options:

A.  

Individual overview capacity requirements

B.  

Capacity load work center view

C.  

Extended capacity evaluation

D.  

Structure overview

Discussion 0
Questions 4

You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation.,

and have entered the quotation ...

What is the typical sequence for the following business transactions and document.

Options:

A.  

Benefic check - Acceptance of performed service- vendor selection - purchase order handing- purchase order monitoring-Good receipt - invoce ..

B.  

Vendor selection - purchase order handing- purchase order monitoring- Benefic Check- Acceptance of performed services.

C.  

Vendor selection - purchase order handing - invoice receipt - purchase order monitoring -Good receipt.

D.  

Vendor selection- Purchase order handing-purchase order monitoring-Good receipt- Invoice receipt.

Discussion 0
Questions 5

Revenues & Payment

A customer use cross- company - code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?

Options:

A.  

Settle the WBS element to the highest billing element before you do the result analysis.

B.  

Split the project intdifferent project according to each company code.

C.  

Change the project structure so that it correspond better to the company's organization structure.

D.  

Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.

Discussion 0
Questions 6

You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question

Options:

A.  

Maintain subordinate internal activity elements assigned to other work centres

B.  

Increase the capacities of the work center in the project planning board.

C.  

Trigger automatic capacity leveling inside the project planning board

D.  

Shift activities backward or forward on the time axis where more capacities are available

Discussion 0
Questions 7

Project structure.

You intent to work with predefined project coding mask to create project definitions. What do you have to consider?

Options:

A.  

You can create project coding mask X... event if there are project numbers beginning with X.

B.  

The standard project definition must differ from the definition of the operative project.

C.  

You can use only numbers for a project coding mask definition.

D.  

You can use an indicator to determine that only coded project numbers may be used within the project system.

Discussion 0
Questions 8

Where do you control whether a project stock is managed as valuated or non-valuated project stock?

Options:

A.  

In the network activity

B.  

In the project definition

C.  

In the WBS element

D.  

In the material master

Discussion 0
Questions 9

Which of the following statements apply to project versions? Note: There are 2 correct answers to this question

Options:

A.  

Project versions can be changed

B.  

Project versions are mandatory for Milestone Trend Analysis (MTA)

C.  

Project versions can be created automatically based on user status

D.  

Manually Created project versions always require a project version profile

Discussion 0
Questions 10

How can you update the degree of processing for an activity?

Options:

A.  

By using results analysis

B.  

By changing the activity

C.  

By scheduling the activity

D.  

By confirming the activity

Discussion 0
Questions 11

Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question

Options:

A.  

The materials must allow sales order or project stock

B.  

The exact lot size procedure must be used

C.  

The procurement type of the material must be internal

D.  

An MRP group must be assigned

Discussion 0
Questions 12

What PPIDS master data is necessary for using PP/DS? Note: There are 2 correct answers to this question

Options:

A.  

Location

B.  

Material

C.  

Production version

D.  

Resource

Discussion 0
Questions 13

You have saved a network and activates with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?

Options:

A.  

Missing budget for material components

B.  

Missing reservations for material components

C.  

Missing material availability

D.  

Missing authorizations to release material components

Discussion 0
Questions 14

How are earliest dates and latest dates of activities scheduled?

Options:

A.  

Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates

B.  

Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling

C.  

Earliest dates and latest dates are scheduled by forward scheduling

D.  

Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling

Discussion 0
Questions 15

An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?

Options:

A.  

The network profile

B.  

The control key

C.  

The table of MRP controllers

D.  

The scheduling parameters for the network

Discussion 0
Questions 16

Dates

How are earliest dates and latest dates of activities schedule?

Options:

A.  

Earliest dates are scheduled by backward scheduling, and the latest dates by forward scheduling.

B.  

Earliest dates are scheduled by forward scheduling , and the latest dates by backward scheduling.

C.  

Earliest dates and latest dates are scheduled by forward scheduling.

D.  

Earliest dates are scheduled by backward scheduling, and the lates dates by copying the earliest dates.

Discussion 0