SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management Question and Answers

SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management

Last Update Apr 24, 2024
Total Questions : 82

We are offering FREE C_S4PPM_2021 SAP exam questions. All you do is to just go and sign up. Give your details, prepare C_S4PPM_2021 free exam questions and then go for complete pool of SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management test questions that will help you more.

C_S4PPM_2021 pdf

C_S4PPM_2021 PDF

$35  $99.99
C_S4PPM_2021 Engine

C_S4PPM_2021 Testing Engine

$42  $119.99
C_S4PPM_2021 PDF + Engine

C_S4PPM_2021 PDF + Testing Engine

$56  $159.99
Questions 1

In project management, what data can be copied from a project template during creation of a new project?

NOTE: There are 3 correct answers to this question.

Options:

A.  

Authorizations

B.  

Project structure

C.  

Checklist

D.  

Dates

E.  

Responsible organizational unit

Discussion 0
Questions 2

No upcoming milestone are shown in the my projects SAP Fiori app.

What are the reasons for this?

NOTE: There are 2 correct answers to this question

Options:

A.  

You are not defined as the project Responsible

B.  

Milestone is not identified as mandatory

C.  

Project is not released

D.  

Milestone is not identified as critical

Discussion 0
Questions 3

Which system behavior are enabled when a create a project with multiple phase?

NOTE: There are 2 correct answers to this question.

Options:

A.  

Determination of the start-dates of subsequent phases

B.  

Rollup of activity cost allocations to phases

C.  

Rollup of resource requirements of tasks to phases

D.  

Determination of the start- and end-dates of tasks

Discussion 0
Questions 4

Which customizing activity do you use to integrate capacity planning of an item with financial planning?

Options:

A.  

Define financial integration scenarios

B.  

Define portfolio type

C.  

Define financial and capacity views

D.  

Define financial planning settings

Discussion 0
Questions 5

How are capacity planning values rolled up along the bucket hierarchy?

Options:

A.  

Item values are rolled up to buckets via the collection

B.  

Item values are rolled up to buckets via the review

C.  

Item values are rolled up directly to buckets

D.  

Project values are rolled up directly to buckets

Discussion 0
Questions 6

You have created a portfolio with the bucket levels and wants to create a portfolio item.

When can you create the portfolio item?

Options:

A.  

At any bucket level

B.  

At the highest bucket level

C.  

At multiple bucket levels

D.  

At the lowest bucket level

Discussion 0
Questions 7

You review the capacity planning values at bucket level in portfolio management.

Which function can you use to view the items that are assigned to a bucket directly in capacity planning?

Include subobjects

Options:

A.  

BCV Reporting

B.  

View Chart

C.  

Distribution

Discussion 0
Questions 8

What must you configure to view portfolio item data in project management projects?

Options:

A.  

Set the project management flag to active in customizing for the linking item type

B.  

Set the business content data source for portfolio management in customizing

C.  

Set the objects link flag to active in customizing for the project management structure

D.  

Set the portfolio management flag to active in customizing for the project type

Discussion 0
Questions 9

In portfolio management to which of the following does the logical system refer In the definition of the PS project definition object link?

Options:

A.  

BCV system for reporting

B.  

Target system for integration

C.  

Business intelligence (BI) system for reporting

D.  

Web server for integration

Discussion 0
Questions 10

You are planning resources.

Which period types are available?

NOTE: There are 3 correct answers to this question.

Options:

A.  

Weekly

B.  

Hourly

C.  

Monthly

D.  

Daily

Discussion 0
Questions 11

Which information can be assigned to a business partner in project management?

NOTE: There are 3 correct answers to this question

Options:

A.  

Work centers

B.  

Areas and locations

C.  

Personal numbers

D.  

Production resources or tools (PRT)

E.  

SAP users

Discussion 0
Questions 12

Which of the following can you use to create multiple portfolio items simultaneously?

Options:

A.  

Item template

B.  

Primavera import

C.  

Microsoft Excel import

D.  

Microsoft project import

Discussion 0