Last Update Jul 11, 2026
Total Questions : 57
We are offering FREE BIM_MGT_101 Autodesk exam questions. All you do is to just go and sign up. Give your details, prepare BIM_MGT_101 free exam questions and then go for complete pool of Autodesk Certified Professional in BIM Management for Building Design test questions that will help you more.
A federated model has been created for a multidisciplinary project, but clashes are being reported in areas where coordination should already be resolved. Upon investigation, the BIM manager finds that some models were exported with outdated links and local coordinates.
What is the most appropriate next step before proceeding with coordination analysis?
Due to unpredictable material tariffs, a campus project anticipates possibly changing its structural framing system once pricing is finalized. This could affect floor-to-floor heights across several buildings.
What method would best ensure both initial and ongoing coordination of Levels and Grids across a large multidisciplinary Revit project?
The BIM manager is working on a mixed-use project in which consultants are on different platforms and delivery timelines. The client requires COBie-compliant data handover and weekly coordination uploads.
What is the best approach to ensure project-specific BIM processes are effectively implemented from the outset?
A BIM manager is preparing to share a federated model package with an external cost estimator. The estimator only needs access to quantities and location-based metadata, but not design intent or proprietary elements from other teams.
What is the first step the BIM manager should take to ensure appropriate use and minimize data-related risk?
A team member accidentally unpinned and dragged a linked CAD file, and it is no longer aligned according to the Shared Coordinates.
How can the BIM manager realign the linked CAD file in the Revit model?
A government facility project requires unique data formatting and export requirements that comply with a global data-management initiative. A workflow utilizing a newly released add-on tool is developed to perform this task.
How should a BIM manager define training and ensure the appropriate staff receive it?
A project manager who is not familiar with Autodesk Forma has asked a BIM manager to lead clash detection for their Revit project. The project manager would like to review the issue lists weekly, by discipline, to track progress and coordinate with consultants as needed.
What should the BIM manager do to fulfil this request efficiently?
A regional user group raised awareness about a third-party add-on tool that enables a team to establish thresholds for model warnings. In addition, it automates suppressing warnings deemed negligible to a specific project.
Which two data points should a BIM manager gather to build a business case to have the tool approved for use across the firm? (Select two.)
Refer to the exhibit.

A designer cannot see a 2x4 tile ceiling in the hallway area of their Reflected Ceiling Plan, but that same ceiling is visible in a 3D view. The 2x2 ceilings in the other rooms are visible in both views.
What are two possible reasons for this? (Select two.)
The BIM manager is conducting a health check of a design model submitted by a consultant to assess its readiness for coordination. Several model performance concerns have been raised, including long open times, sluggish navigation, and excessive file size.
Which of the following actions would best help to evaluate the model’s health and identify areas of improvement?
An AEC company has received a design model from the Architect of Record to begin creating construction documentation. The BIM Execution Plan identifies a fast-track delivery schedule, and the project team includes new consultants with limited exposure to the client’s preferred toolset and workflows. The BIM manager must determine how best to prepare the delivery team and assess the model’s compatibility with internal systems.
As the BIM manager prepares for the Project Kickoff meeting, which two pieces of information are most critical to avoid issues related to digital compatibility? (Select two.)
A BIM manager is reviewing a consultant’s architectural model before the next coordination milestone. The project requires each model to conform to a defined naming convention, include COBie parameters, and populate shared parameters according to the Model Element Table. The BIM manager notices that several elements are missing metadata and that some naming is inconsistent.
Which step best supports a systematic evaluation of completeness and compliance with project standards?
A designer needs to add Area Lines in an Area Plan, but upon adding them, they receive a message stating that none of the created elements are visible.

Where can they check to resolve the issue?
The BIM manager is working in an Architectural model that uses the phases Existing and New Construction . They have linked in a Structural model that uses only Phase 1 for existing and Phase 2 for new construction. After linking, they notice that demolition elements from the Structural model do not display correctly in the demolition views.
Which approach allows the BIM manager to display linked elements correctly based on this phase setup, without changing the phases in the linked model?
During a model health check, a BIM manager notices that an international airport project’s models are 1 GB each. The team has not mentioned any issues, but they did miss a recent 50% Construction Documents deadline.
What should the BIM manager do?
A BIM manager is preparing to onboard a group of subcontractors into Autodesk Forma for a large healthcare project. These subcontractors need access to a limited set of model files related only to interior partitions, but should not be able to view or modify structural, MEP, or scheduling content.
What two actions should the BIM manager take to manage data security in this scenario? (Select two.)
During a project onboarding meeting, the client provides their current BIM standards and templates to the BIM manager. The project will involve multiple consultants across different regions and is being delivered under a fast-track schedule with a high volume of design iterations. The client has also indicated that they plan to use a new collaboration platform not previously piloted on similar project types.
The BIM manager must evaluate whether the client’s materials are sufficient and aligned with digital-delivery expectations, collaboration goals, and coordination requirements.
Given these factors, which two of the client’s BIM resources must be prioritized for review to evaluate their ability to support digital delivery and coordination across regions, teams, and time constraints? (Select two.)