We are offering FREE 93-Tall-Mass-Timber-Buildings International Code Council exam questions. All you do is to just go and sign up. Give your details, prepare 93-Tall-Mass-Timber-Buildings free exam questions and then go for complete pool of 93-Tall-Mass-Timber-Buildings test questions that will help you more.
In mass timber construction of Type IV-C, the fire-resistance ratings of bearing walls are permitted to be reduced by _____ where supporting a roof only.
Calculated mass timber fire resistance can include each of the following except:
Refer to the exhibit by clicking on the EXHIBIT button above.

In the detail shown, if the connections at the glulam beam and the steel plate required a fire-resistance rating of one (1) hour and the wood cover is designed per AWC Technical Report 10 to provide the entire one (1) hour of protection, the minimum required thickness for the wood block member providing protection for the bolt connections is _____ inches.
Which of the following provisions for mass timber used for interior exit and elevator hoistway enclosures is true?
The fire-resistance of a protected mass timber assembly is equivalent to the fire resistance time of the:
In Type IV-C construction, a connection between two members of the primary structural frame supporting a floor is required to be protected to achieve a minimum fire-resistance rating of:
In mass timber construction of Type IV-B, each of the following is suitable for use as fireblocking except:
In Type IV-C construction, the fire-resistance rating provided by protection over a connection can be determined by which of the following?
The maximum allowable height for a Group E building of Type IV-A construction with an automatic sprinkler system in accordance with Section 903.3.1.1 is _____ stories.
Each of the following is true for special inspection of mass timber construction except:
Regarding water supply for the protection of buildings under construction, when combustible building materials of the building under construction are delivered to a site, the minimum fire flow provided shall be _____ gpm.
All of the following combustible elements may be used in mass timber buildings except:
Which of the following best describes circumstances for which a separate inspection by a building official would be required for the fire protection of structural connections in buildings of Type IV-B construction?
Refer to the figure by clicking on the EXHIBIT button above.


The exterior wall section shown in the Figure provides the prescribed noncombustible protection required by which Construction Type?
Adhesives used to resist passage of air in construction Type IV-C, shall be in accordance with which of the following standards?
Which of the following products is not included in the definition of mass timber?
Given: A building of Type IV-B construction is designed to be greater than six stories above grade plane.
At least one layer of required noncombustible protection shall be installed on all of the following building elements except _____ on all floor levels more than four levels below active mass timber construction before erecting additional floor levels during construction.
The building owner shall be responsible for each of the following for fire safety during construction except:
Which of the following construction Types permit concealed spaces to be protected by completely filling the concealed space with noncombustible insulation?
Materials acceptable for use in fire-protecting connections in Type IV-A construction includes each of the following except:
For a sprinklered Business Occupancy (Group B) in a 15-story building of Type IV-A construction, the maximum allowable building area is:
Where Type X gypsum board serves as noncombustible protection for interior surfaces of wall and ceiling assemblies, all of the following code provisions are correct except:
The maximum allowable height for a Group I-4 building of Type IV-B construction provided with an automatic sprinkler system in accordance with Section 903.3.1.1 is _____ ft.
The fire-resistance of a protected mass timber assembly is equivalent to the fire resistance time of the: